Contract 38238: 2002-070-00 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION
Project Number:
Title:
Lapwai Creek Anadromous Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
38238
Contract Title:
2002-070-00 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
32840: 2002-070-00 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION
  • 42391: 200207000 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Contract History:

The Restoring Anadromous Fish Habitat in the Lapwai Creek Watershed, project 2002-070-00, began in 2003.  This multi-year project focuses on restoring and improving fish habitat within the Lapwai Creek watershed.  The limiting factors addressed include low summer flows, wide fluctuation in annual stream flows, connectivity, loss of all or partial floodplain, sedimentation of spawning and rearing habitat, high summer stream temperatures, and lack of in-stream cover.  Past accomplishments have entailed the installation of land improvement projects to address these limiting factors, including 7.32 miles of riparian fencing, 6.21 miles of upland fencing, 50 acres of weed control, two livestock waste systems, 8,000 LF of riparian plantings, one low flow stream crossing, 10.5 miles of road improvements, 1.5 miles of streambank bioengineering restoration, 4.5 acres of wetland enhancement, 15,209 acres of direct seeding, 27 alternative watering systems for livestock, 13 water and sediment control structures, and the development of 24 habitat conservation plans.  

Prior to the initiation of this project, a massive data gap existed on fish, the condition of fish habitat, and limiting factors within the watershed.  Under the FY 2007 contract, we focused primarily on the analysis and compilation of the fish presence and abundance data, and stream habitat data collected annually since 2003.  The data was analyzed and converted into a GIS-compatible format and then combined with other available, watershed-wide data sets developed by the Nez Perce Soil and Water Conservation District and the NPT Water Resources Division.  The synergistic effect of these combined data sets came together in the development of the "Strategy for the Ecological Restoration of Lapwai Creek Watershed," a document intended to direct efforts and resources toward the highest priority restoration projects and areas of the Lapwai Creek Watershed.  This document provides an accurate assessment of the status and health of the aquatic resources within the watershed, and will allow us to spatially prioritize the implementation of future watershed protection and restoration projects for the Lapwai Creek Watershed.
                                                                                                                                                                          
FY 08 Contract Summary:

The "Strategy for the Ecological Restoration of Lapwai Creek Watershed," which was completed under the FY 07 contract, was the main reference for prioritizing implementation and developing the FY 08 SOW.  

Under this contract the NPSWCD plans to install 4,000 LF of fence, control 30 acres of noxious weeds, plant 15 acres with native trees and shrubs, install 2 water developments, install 11 erosion control structures, remove four passage barriers, reconnect a historic side channel, and remove a dike to restore floodplain function.  

Status and Trend and Implementation/Effectiveness monitoring:  The Nez Perce Tribe conducts the monitoring and evaluation required to determine population status and trends, as well as the physical and biological response to the habitat/watershed restoration efforts.  The Nez Perce Soil and Water Conservation District (District) utilizes the Nez Perce Tribe's monitoring data to prioritize habitat improvement and site specific project areas.  Since the majority of the land within the watershed is privately owned, the District also coordinates with the landowners to obtain project approval for both the NPT and the NPSWCD to continue habitat restoration actions throughout the Lapwai Creek watershed.
Account Type(s):
Expense
Contract Start Date:
05/01/2008
Contract End Date:
08/31/2009
Current Contract Value:
$259,103
Expenditures:
$259,103

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

Description: Site prior to barrier removal. Shows barrier.

Contract(s):

38238

Dimensions: 2048 x 1536

Description: Map showing knapweed infestation area and spot spraying control area.

Contract(s):

38238

Dimensions: 1100 x 648

Description: Spot spraying knapweed with Correctional Facility Labor.

Contract(s):

38238

Dimensions: 3072 x 1819

Description: Construction photo showing removal of bridge end.

Contract(s):

38238

Dimensions: 2052 x 2012

Description: Removal of BST from Bridge Surface

Contract(s):

38238

Dimensions: 2492 x 1745

Description: After BST removal. Bridge deck is prepared for removal.

Contract(s):

38238

Dimensions: 2615 x 1837

Description: Deck removal stage 1

Contract(s):

38238

Dimensions: 2421 x 1617

Description: Removal of deck - stage 2

Contract(s):

38238

Dimensions: 2389 x 1958

Description: Deck Removal Stage 3

Contract(s):

38238

Dimensions: 2600 x 1801

Description: deck removal stage 4

Contract(s):

38238

Dimensions: 1744 x 1596

Description: Deck removal completed

Contract(s):

38238

Dimensions: 3072 x 1503

Description: Bridge Abutment Removal

Contract(s):

38238

Dimensions: 2411 x 2304

Description: Bridge Abutment Removal

Contract(s):

38238

Dimensions: 2788 x 1651


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA A: 165. Environmental Compliance 07/30/2009 07/30/2009
Design package for 8 land improvement projects B: 175. Prepare Engineering and Technical Designs 03/31/2009 03/31/2009
Install 1,500 linear feet of fence along Lapwai Creek C: 40. Site 0522 Livestock Exclusion from Lapwai Creek 08/22/2009 08/28/2009
Remove Herndon Bridge D: 184. Site 0522 Fish Passage Barrier Removal 09/19/2008 08/31/2008
Reconnect Half Moon Draw with Lapwai Creek E: 30. Site 0522 Reconnect Half Moon Draw with Lapwai Creek 08/31/2009 08/24/2009
Restore floodplain connectivity F: 180. Site 0522 Restore Floodplain Connectivity 12/12/2008 08/06/2008
15 Acres of Invasive Plant Management G: 53. Site 0522 Treat 15 acres of Exotic Invasive Plant Species 11/21/2008 08/07/2008
Install native tree, shrub and grass seed in riparian, upland and post construction areas H: 47. Site 0522 Plant Vegetation in Riparian and Construction Areas 03/31/2009 03/31/2009
Install 1,000 linear feet of fence along Lapwai Creek I: 40. Site 0848 Install Fence 08/27/2009 08/27/2009
Install native tree, shrub and grass seed in riparian and adjacent upland area J: 47. Site 0848 Plant Vegetation 05/31/2009 05/21/2009
Install 800 linear feet of fence along Lapwai Creek K: 40. Site 0849 Install Fence 06/30/2009 06/24/2009
Install 1,000 linear feet of fence along Lapwai Creek L: 40. Site 0850 Install Fence 06/30/2009 06/24/2009
Alternative water source installed M: 34. Site 0850 Create Alternative Water Source for Livestock Along Lapwai Creek 03/31/2009 03/31/2009
Plant native tree, shrub and grass in riparian and upland area N: 47. Site 0855 Plant 15 Acres with Native Trees and Shrubs 03/31/2009 03/31/2009
30 Acres of Invasive Plant Management O: 53. Site 0852 Treat 30 Acres of Exotic Invasive Plant Species 11/28/2008 11/28/2008
Road improvement completed P: 38. Site 0851 Improve Road to Reduce Sediment Delivery to Lapwai Creek 06/30/2009 06/30/2009
80 acres seeded with direct seeding systems Q: 48. Site 0642 Reduce Sediment Delivery to Sweetwater Creek 11/30/2008 10/30/2008
520 acres seeded with direct seeding systems R: 48. Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks 11/30/2008 10/30/2008
Eight erosion control structures installed S: 55. Site 0853 Install Erosion Control Measures for Sheet, Rill, and Gully Erosion 03/31/2009 03/31/2009
Alternative water source installed T: 34. Site 0524 Create Alternative Water Source for Livestock Along Lapwai Creek 08/31/2009 08/24/2009
Remove fish passage barriers and restore landowner access over stream U: 184. Site 0854 Remove Passage Barrier 07/31/2009
Raw temperature data V: 157. Stream Temperature Data Collection in the Lapwai Creek Watershed 11/28/2008 11/21/2008
Analyzed stream temperature data W: 162. Stream Temperature Data Analysis 02/27/2009 03/31/2009
Updated GIS database X: 160. Maintain GIS database 03/31/2009 03/31/2009
Data Sent to Idaho StreamNet Project Leader Y: 161. Supply Publicly Available Data to Idaho StreamNet Project Leader 01/30/2009 02/04/2009
Bio-logs and wetland sod planted and stored in holding tanks until 2009 installation Z: 47. Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2009 Planting 03/27/2009 03/31/2009
Project designs for areas prioritized by the Lapwai Ecological Restoration Strategy document AA: 114. Select, Prioritize, and Obtain Permission for 2009 Projects 03/31/2009 03/31/2009
Marketing plan implementation AB: 99. Implement Lapwai Watershed Marketing Plan 03/31/2009 03/31/2009
FY 09 SOW Package and FY 08 Accrual Estimate AC: 119. Management, Coordination, and Communication 02/20/2009 03/31/2009
Final FY 07 report attached to this contract AD: 132. Produce Progress Report for Period 4/1/07-4/30/08 10/15/2008 10/15/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 34 Develop Alternative Water Source
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 4 instances of WE 40 Install Fence
  • 4 instances of WE 47 Plant Vegetation
  • 2 instances of WE 48 Practice No-till and Conservation Tillage Systems
  • 2 instances of WE 53 Remove Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 02/09/2007
B 175 Prepare Engineering and Technical Designs 02/09/2007
C 40 Site 0522 Livestock Exclusion from Lapwai Creek
D 184 Site 0522 Fish Passage Barrier Removal 07/28/2008
E 30 Site 0522 Reconnect Half Moon Draw with Lapwai Creek
F 180 Site 0522 Restore Floodplain Connectivity
G 53 Site 0522 Treat 15 acres of Exotic Invasive Plant Species
H 47 Site 0522 Plant Vegetation in Riparian and Construction Areas
I 40 Site 0848 Install Fence
J 47 Site 0848 Plant Vegetation
K 40 Site 0849 Install Fence
L 40 Site 0850 Install Fence
M 34 Site 0850 Create Alternative Water Source for Livestock Along Lapwai Creek
N 47 Site 0855 Plant 15 Acres with Native Trees and Shrubs
O 53 Site 0852 Treat 30 Acres of Exotic Invasive Plant Species
P 38 Site 0851 Improve Road to Reduce Sediment Delivery to Lapwai Creek
Q 48 Site 0642 Reduce Sediment Delivery to Sweetwater Creek
R 48 Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks
S 55 Site 0853 Install Erosion Control Measures for Sheet, Rill, and Gully Erosion
T 34 Site 0524 Create Alternative Water Source for Livestock Along Lapwai Creek
U 184 Site 0854 Remove Passage Barrier
V 157 Stream Temperature Data Collection in the Lapwai Creek Watershed
W 162 Stream Temperature Data Analysis 02/09/2007
X 160 Maintain GIS database 02/09/2007
Y 161 Supply Publicly Available Data to Idaho StreamNet Project Leader 02/09/2007
Z 47 Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2009 Planting 02/09/2007
AA 114 Select, Prioritize, and Obtain Permission for 2009 Projects 02/09/2007
AB 99 Implement Lapwai Watershed Marketing Plan 02/09/2007
AC 119 Management, Coordination, and Communication 02/09/2007
AD 132 Produce Progress Report for Period 4/1/07-4/30/08 02/09/2007
AE 185 Periodic Status Reports for BPA 02/09/2007