Environmental compliance documentation submitted to BPA |
A: 165. Environmental Compliance |
|
07/30/2009 |
07/30/2009 |
Design package for 8 land improvement projects |
B: 175. Prepare Engineering and Technical Designs |
|
03/31/2009 |
03/31/2009 |
Install 1,500 linear feet of fence along Lapwai Creek |
C: 40. Site 0522 Livestock Exclusion from Lapwai Creek |
|
08/22/2009 |
08/28/2009 |
Remove Herndon Bridge |
D: 184. Site 0522 Fish Passage Barrier Removal |
|
09/19/2008 |
08/31/2008 |
Reconnect Half Moon Draw with Lapwai Creek |
E: 30. Site 0522 Reconnect Half Moon Draw with Lapwai Creek |
|
08/31/2009 |
08/24/2009 |
Restore floodplain connectivity |
F: 180. Site 0522 Restore Floodplain Connectivity |
|
12/12/2008 |
08/06/2008 |
15 Acres of Invasive Plant Management |
G: 53. Site 0522 Treat 15 acres of Exotic Invasive Plant Species |
|
11/21/2008 |
08/07/2008 |
Install native tree, shrub and grass seed in riparian, upland and post construction areas |
H: 47. Site 0522 Plant Vegetation in Riparian and Construction Areas |
|
03/31/2009 |
03/31/2009 |
Install 1,000 linear feet of fence along Lapwai Creek |
I: 40. Site 0848 Install Fence |
|
08/27/2009 |
08/27/2009 |
Install native tree, shrub and grass seed in riparian and adjacent upland area |
J: 47. Site 0848 Plant Vegetation |
|
05/31/2009 |
05/21/2009 |
Install 800 linear feet of fence along Lapwai Creek |
K: 40. Site 0849 Install Fence |
|
06/30/2009 |
06/24/2009 |
Install 1,000 linear feet of fence along Lapwai Creek |
L: 40. Site 0850 Install Fence |
|
06/30/2009 |
06/24/2009 |
Alternative water source installed |
M: 34. Site 0850 Create Alternative Water Source for Livestock Along Lapwai Creek |
|
03/31/2009 |
03/31/2009 |
Plant native tree, shrub and grass in riparian and upland area |
N: 47. Site 0855 Plant 15 Acres with Native Trees and Shrubs |
|
03/31/2009 |
03/31/2009 |
30 Acres of Invasive Plant Management |
O: 53. Site 0852 Treat 30 Acres of Exotic Invasive Plant Species |
|
11/28/2008 |
11/28/2008 |
Road improvement completed |
P: 38. Site 0851 Improve Road to Reduce Sediment Delivery to Lapwai Creek |
|
06/30/2009 |
06/30/2009 |
80 acres seeded with direct seeding systems |
Q: 48. Site 0642 Reduce Sediment Delivery to Sweetwater Creek |
|
11/30/2008 |
10/30/2008 |
520 acres seeded with direct seeding systems |
R: 48. Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks |
|
11/30/2008 |
10/30/2008 |
Eight erosion control structures installed |
S: 55. Site 0853 Install Erosion Control Measures for Sheet, Rill, and Gully Erosion |
|
03/31/2009 |
03/31/2009 |
Alternative water source installed |
T: 34. Site 0524 Create Alternative Water Source for Livestock Along Lapwai Creek |
|
08/31/2009 |
08/24/2009 |
Remove fish passage barriers and restore landowner access over stream |
U: 184. Site 0854 Remove Passage Barrier |
|
07/31/2009 |
|
Raw temperature data |
V: 157. Stream Temperature Data Collection in the Lapwai Creek Watershed |
|
11/28/2008 |
11/21/2008 |
Analyzed stream temperature data |
W: 162. Stream Temperature Data Analysis |
|
02/27/2009 |
03/31/2009 |
Updated GIS database |
X: 160. Maintain GIS database |
|
03/31/2009 |
03/31/2009 |
Data Sent to Idaho StreamNet Project Leader |
Y: 161. Supply Publicly Available Data to Idaho StreamNet Project Leader |
|
01/30/2009 |
02/04/2009 |
Bio-logs and wetland sod planted and stored in holding tanks until 2009 installation |
Z: 47. Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2009 Planting |
|
03/27/2009 |
03/31/2009 |
Project designs for areas prioritized by the Lapwai Ecological Restoration Strategy document |
AA: 114. Select, Prioritize, and Obtain Permission for 2009 Projects |
|
03/31/2009 |
03/31/2009 |
Marketing plan implementation |
AB: 99. Implement Lapwai Watershed Marketing Plan |
|
03/31/2009 |
03/31/2009 |
FY 09 SOW Package and FY 08 Accrual Estimate |
AC: 119. Management, Coordination, and Communication |
|
02/20/2009 |
03/31/2009 |
Final FY 07 report attached to this contract |
AD: 132. Produce Progress Report for Period 4/1/07-4/30/08 |
|
10/15/2008 |
10/15/2008 |