Province | Subbasin | % |
---|---|---|
Columbia Cascade | Okanogan | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Permit received | A: 165. Permit approval received | 08/25/2008 | 10/31/2008 | |
Low flow channel constructed | B: 30. Construct a low flow channel and increase bank stability in lower Salmon Creek | 10/31/2008 | 12/08/2008 | |
Provide on the ground and oversight direction for contractor | C: 100. Oversee construction of low flow channel | 10/17/2008 | 12/08/2008 | |
Funding Package - Submit draft to COTR | D: 119. Develop SOW, Budget for 2009 | 05/01/2009 | 07/15/2009 | |
Watershed Coordination | E: 191. Coordinate with landowners, local governments, irrigation district and WDFW with annual activities | 07/31/2009 | 05/31/2009 | |
Conduct surveys for adequate fish passage | F: 157. Evaluate fish passage conditions during controlled releases | 07/31/2009 | 06/01/2009 | |
Attach Progress Report in Pisces | H: 132. Submit Progress Report for the period (8/1/2008) to (7/31/2009) | 07/15/2009 | 07/31/2009 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Permit approval received | 02/09/2007 | ||||||
B | 30 | Construct a low flow channel and increase bank stability in lower Salmon Creek | 08/28/2008 | ||||||
C | 100 | Oversee construction of low flow channel | 02/09/2007 | ||||||
D | 119 | Develop SOW, Budget for 2009 | 02/09/2007 | ||||||
E | 191 | Coordinate with landowners, local governments, irrigation district and WDFW with annual activities | 02/09/2007 | ||||||
F | 157 | Evaluate fish passage conditions during controlled releases | 08/14/2008 | ||||||
G | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
H | 132 | Submit Progress Report for the period (8/1/2008) to (7/31/2009) | 02/09/2007 |