Environmental Compliance Requirements Completed |
A: 165. Environmental Compliance |
|
02/03/2011 |
02/03/2011 |
Design package for 8 land improvement projects |
B: 175. Prepare Engineering and Technical Designs |
|
04/15/2010 |
12/14/2009 |
Install 800 linear feet of fence along Lapwai Creek |
C: 40. Site 0975 Livestock Exclusion from Lapwai Creek |
|
03/25/2011 |
02/16/2011 |
Plant native tree, shrub and grass in riparian and upland area |
D: 47. Site 0975 Plant Spring/Wetland Area with Native Trees and Shrubs |
|
04/30/2011 |
04/30/2011 |
Alternative water source installed |
E: 34. Site 0975 Create Alternative Water Source for Livestock |
|
04/28/2011 |
04/28/2011 |
Remove Culvert |
F: 184. Site 0972 Fish Passage Barrier Removal |
|
11/30/2010 |
09/18/2009 |
Install native tree, shrub and grass seed in riparian and post construction areas |
G: 47. Site 0972 Plant Vegetation in Riparian and Construction Areas |
|
03/31/2011 |
03/29/2011 |
Install 1,600 linear feet of fence along Lapwai Creek |
H: 40. Site 0972 Install Fence |
|
04/05/2011 |
11/17/2010 |
80 Acres of Invasive Plant Management |
I: 53. Treat 80 Acres of Exotic Invasive Plant Species |
|
04/16/2010 |
04/16/2010 |
Install 800 linear feet of fence along Lapwai Creek |
J: 40. Site 0974 Install Fence |
|
04/05/2011 |
11/17/2010 |
Road improvement completed |
K: 38. Site 0974 Improve Road to Reduce Sediment Delivery to Lapwai Creek |
|
08/24/2010 |
09/22/2010 |
80 acres seeded with direct seeding systems |
L: 48. Site 0642 Reduce Sediment Delivery to Sweetwater Creek |
|
11/30/2009 |
10/22/2009 |
520 acres seeded with direct seeding systems |
M: 48. Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks |
|
11/30/2009 |
10/30/2009 |
six erosion control structures installed |
N: 55. Site 0973 Install Erosion Control Measures for Sheet, Rill, and Gully Erosion |
|
04/30/2011 |
04/30/2011 |
150 acres of vegetation maintained at 33 sites |
O: 22. Maintain Vegetation at Previously Planted Sites in Contract Years 2005 through 2009 |
|
04/21/2010 |
04/21/2010 |
Raw temperature data |
P: 157. Stream Temperature Data Collection in the Lapwai Creek Watershed |
|
11/28/2009 |
11/19/2009 |
Updated GIS database |
Q: 160. Maintain GIS database |
|
03/31/2011 |
03/30/2011 |
Data Sent to Idaho StreamNet Project Leader |
R: 161. Supply Publicly Available Data to Idaho StreamNet Project Leader |
|
03/14/2011 |
03/22/2011 |
Bio-logs and wetland sod planted and stored in holding tanks until 2010 installation |
S: 47. Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2010 Planting |
|
03/27/2010 |
03/30/2010 |
Project selected for areas prioritized by the Lapwai Ecological Restoration Strategy document |
T: 114. Select, Prioritize, and Obtain Permission for 2010 Projects |
|
03/31/2010 |
03/31/2010 |
Marketing plan implementation |
U: 99. Implement Lapwai Watershed Marketing Plan |
|
03/31/2010 |
03/31/2010 |
FY 10 SOW Package and FY 09 Accrual Estimate |
V: 119. Management, Coordination, and Communication |
|
02/19/2011 |
03/01/2011 |
Final FY 08 report attached to this contract |
W: 132. Produce Progress Report for Period 4/1/08-4/30/09 |
|
10/15/2009 |
10/15/2009 |
Completed RIPP Step 1 on 10 non-tribal Properties |
Y: 115. Complete 10 Habitat Restoration Plans |
|
11/30/2009 |
12/15/2009 |
Install 3600 linear feet of fence along Rock Creek |
Z: 40. Site 1092 Livestock Exclusion from Lapwai Creek |
|
01/16/2011 |
03/24/2011 |
Plant native tree, shrub and grass in riparian and upland area |
AA: 47. Site 1092 Plant Spring/Wetland Area with Native Trees and Shrubs |
|
04/20/2011 |
04/20/2011 |
Alternative water source installed |
AB: 34. Site 1092 Create Alternative Water Source for Livestock |
|
04/15/2011 |
04/15/2011 |
Provide livestock access to pasture |
AC: 38. Site 1092 Livestock Crossing |
|
04/14/2011 |
04/14/2011 |
First work period progress report attached to this contract |
AD: 132. Produce Progress Report for Period 5/1/09-4/30/10 |
|
07/30/2010 |
07/30/2010 |
Completed RIPP Step 1 on 8 non-tribal Properties |
AE: 115. Complete 8 Habitat Restoration Plans for second work period |
|
12/30/2010 |
11/05/2010 |
Marketing plan implementation |
AF: 99. Implement Lapwai Watershed Marketing Plan for second work period |
|
04/22/2011 |
04/22/2011 |
Project selected for areas prioritized by the Lapwai Ecological Restoration Strategy document |
AG: 114. Select, Prioritize, and Obtain Permission for 2011 Projects |
|
12/17/2010 |
12/09/2010 |
Bio-logs and wetland sod planted and stored in holding tanks until 2011 installation |
AH: 47. Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2011 Planting |
|
04/29/2011 |
04/29/2011 |
Raw temperature data |
AI: 157. Stream Temperature Data Collection in the Lapwai Creek Watershed |
|
12/09/2010 |
12/27/2010 |
150 acres of vegetation maintained at 33 sites |
AJ: 22. Second Performanc Period Planted Sites Maintenance |
|
11/11/2010 |
11/04/2010 |
Alternative water source installed |
AK: 34. Site 1097 Create Alternative Water Source for Livestock |
|
04/07/2011 |
04/30/2011 |
Install 1000 linear feet of fence along Mission Creek |
AL: 40. Site 1097 Install Fence |
|
04/07/2011 |
04/26/2011 |
Install 1400 linear feet of fence along Lapwai Creek |
AM: 40. Site 1096 Install Fence |
|
10/30/2010 |
11/17/2010 |
Installation of 3,000 lf of grassed waterways |
AN: 55. Site 0992 Grass Waterway |
|
12/17/2010 |
11/30/2010 |
520 acres seeded with direct seeding systems |
AO: 48. Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks |
|
11/30/2010 |
11/05/2010 |
80 acres seeded with direct seeding systems |
AP: 48. Site 0642 Reduce Sediment Delivery to Sweetwater Creek |
|
11/30/2010 |
10/27/2010 |
Alternative water source installed |
AQ: 34. Site 1095 Create Alternative Water Source for Livestock |
|
04/14/2011 |
04/30/2011 |
Road improvement completed |
AR: 38. Site 1095 Improve Road to Reduce Sediment Delivery to Lapwai Creek |
|
12/08/2010 |
12/16/2010 |
Plant native tree, shrub and grass in riparian and upland area |
AS: 47. Site 1095 Plant Riparian Area with Native Trees and Shrubs |
|
04/20/2011 |
04/30/2011 |
Install 2050 linear feet of fence along Tom Beall Creek |
AT: 40. Site 1095 Install Fence |
|
04/14/2011 |
04/30/2011 |
50 Acres of Invasive Plant Management |
AU: 53. Release biocontrol agents for yellow star thistle and spotted knapweed control. |
|
07/30/2010 |
07/09/2010 |
11 miles Stream Treated for Hybrid Knotweed |
AV: 53. Control Hybrid Knotweed in second contract period |
|
10/29/2010 |
10/10/2010 |
15 Acres of Invasive Plant Management |
AW: 53. Treat 15 Acres of Exotic Invasive Plant Species |
|
11/30/2010 |
10/10/2010 |
Install 1,500 linear feet of fence along Rock Creek |
AX: 40. Site 1094 Install Fence |
|
03/24/2011 |
03/24/2011 |
Install native tree, shrub and grass seed in riparian areas |
AY: 47. Site 1094 Plant Vegetation in Riparian Zone |
|
04/23/2011 |
04/30/2011 |