Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 53025: 2010-001-00 EXP TYEE RANCH FLOODPLAIN ENHANCEMENT AND COMPLEXITY
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
53025
Contract Title:
2010-001-00 EXP TYEE RANCH FLOODPLAIN ENHANCEMENT AND COMPLEXITY
Contract Continuation:
Previous: Next:
n/a
  • 59682: 2010-001-00 EXP TYEE RANCH FLOODPLAIN ENHANCEMENT AND COMPLEXITY
Contract Status:
Closed
Contract Description:
This contract covers the Tyee Ranch Habitat Restoration proposal located between river mile 22 and 23 of the Entiat River.

The Entiat subbasin has been identified in the Upper Columbia Spring Chinook Salmon and Steelhead Recovery Plan, the WRIA 46 management plan and the WRIA 46 Detailed Implementation Plan as being ripe for habitat restoration projects which would serve to restore native salmon runs of listed species to a viable population level. The Upper Columbia Regional Technical Team (UCRTT) has rated the Middle Entiat River, in which this proposal is located, as a Category I (Protection/Restoration) assessment unit. The UCRTT describes these areas as representing "systems that most closely resemble natural, fully functional aquatic ecosystems. They comprise large, connected blocks of high-quality habitat that support more than two listed species. Exotic species may be present but are not dominant in abundance. Protecting these areas is a priority, although restoration in some areas is also needed."  The Tyee Ranch property, located within what is known as the Preston Reach is one of the areas where reach based restoration is necessary due to past natural and anthropogenic actions and feasible because of the ownership of the site by a single entity, the Mary Esther Fraser Family Trust.

The work being proposed under this contract is one of three restoration projects proposed for a reach based approach to habitat restoration in the Entiat Watershed being monitored as an Intensively Monitored Watershed (IMW). Restoration projects are also being proposed by the Yakama Nations on property to the north, river mile 25- 26 (Brennigan Creek) project and by the Chelan County Natural Resources Department to the south between river mile 19-20 (Dillwater). The intent of the IMW approach is to construct reach based, large scale projects in a single calendar year and then monitor those projects and their effects for the following two years. A second round of reach scale projects will occur in 2014 in the lower Entiat and the final round will occur in 2017 in the middle river area.

Historically, the property has been used as pasture with unrestricted livestock access to the river. Levees were constructed on the site in the 1960's and 1970's . During the 1970's, the Army Corps of Engineers, in response to a massive slide north of the site, "cleaned up" the river. As a result, dredged spoils cutoff flow to a historic side channel in the northernmost reach of property ownership, natural floodplain connectivity and processes have been reduced and eliminated, there is a lack of large woody debris and there is streambank erosion. Limiting factors to be addressed with this project include restoration of natural floodplain processes, lack of woody debris, side channel habitat for offstream refugia, bank roughening and elimination of livestock access to the river.

The Tyee Ranch habitat restoration is the first targeted solicitation proposal under the Upper Columbia Salmon Recovery Board' s program adopted in 2010 utilizing  BPA programmatic non-accord funds. The objective of the Tyee Ranch restoration project is to increase habitat diversity and the abundance of spring Chinook salmon and steelhead between river mile (RM) 21.8 to RM 22.5. As proposed, Phase I of the contract would result in the installation of four floodplain connection channel engineered log jams (ELJ), two mid-channel ELJs, one bank ELJ and two areas of wood enhancement of Large Woody Debris (LWD). Excavation to restore side channel connection would occur between RM 22.9 and 23.0 and between RM 22.3 to below RM 22.1. The upper levee, constructed in the 1970's would be modified by the removal of the southern one-third and the selective breaching at the northern end.   Upon completion of the instream work, all access roads, haul routes and temporary river crossings would be removed, the area restored to its pre-construction condition and the area replanted with native riparian vegetation. The final action would be to construct pasture fencing around the perimeter of existing pasture areas and construction of an off-stream self-water facility to eliminate livestock intrusion.

Engineered log jam structures, side channel reconnection and northern levee modification is slated to be completed between July 15 and September 15, 2011. Fence construction and the off-stream watering facility are scheduled to be complete by October 31, 2011. Riparian planting would likely occur during spring planting season of 2012.

In a potential future contract pending BPA review, Phase II of the contract would entail the removal and restoration of the entire lower levee, constructed sometime in the 1960's and located approximately between RM 21.8 and 21.9. This work is slated to be completed during the summer work window of 2012 with riparian planting occurring either fall of 2012 or spring 2013. The proposal for this portion of the project would entail the excavation of the entire length of the levee. It is likely that there would also be placement of large woody debris and possibly some side channel excavation if necessary to restore floodplain processes and increase complexity and habitat. More detailed designs will be developed in concert with the landowner and downstream property owner whose property could be affected by this levee removal.

As a separate action, a Conservation Easement would be recorded on the property to provide protection and maintenance, if necessary, of the completed restoration.
Account Type(s):
Expense
Contract Start Date:
06/01/2011
Contract End Date:
12/14/2012
Current Contract Value:
$872,793
Expenditures:
$872,793

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain required permits prior to 2011 construction of project. A: 165. Complete EC permitting processes 07/08/2011 08/06/2011
Complete all project management and administrative activities for the project B: 119. Lead coordination efforts for project implementation 10/31/2012 12/14/2012
Stakeholder Coordination C: 191. Lead coordination efforts for watershed wide restoration 10/31/2012 12/14/2012
Floodplain connection engineered log jam D: 29. Floodplain Connection Engineered Log Jam 10/31/2012 09/15/2012
Large Woody Debris Installation E: 29. Large Woody Debris Recruitment 10/31/2012 09/30/2012
Large Woody Debris Installation F: 29. Side Channel Structures 10/31/2012 09/30/2012
Buried Diffuser G: 29. Buried Engineered Log Jam diffuser 10/31/2012 09/30/2012
Mid-channel elj H: 29. Mid-channel Engineered Log Jam 10/31/2012 09/30/2012
Large Woody Debris Installation I: 29. Side Channel Large Woody Debris 10/31/2012 09/30/2012
% Floodplain connection elj J: 29. % Floodplain Connection Engineered Log Jam 12/14/2012 09/30/2012
% Large Woody Debris Installation K: 29. % Bank Large Wood Debris 12/14/2012 11/15/2012
Large Woody Debris Installation L: 29. Mid-channel Engineered Log Jam 10/31/2012 09/30/2012
Large Woody Debris Installation M: 29. Large Woody Debris Enhancement 10/31/2012 09/30/2012
Large Woody Debris Installation N: 29. Floodplain connection Engineered Log Jam 10/31/2012 09/30/2012
New side channel through existing beaver ponds O: 30. Excavated side channel 10/31/2012 11/15/2012
% New inlet breach in upper levee P: 30. % Inlet levee breach 12/14/2012 11/15/2012
% Levee inlet and side channel excavation Q: 30. % %Inlet and side channel excavation 12/14/2012 11/15/2012
Side channel excavation R: 30. Side channel excavation 10/31/2012 11/15/2012
Inlet breach S: 30. Inlet at streambank breach 10/31/2012 09/20/2012
Levee and riprap removal T: 180. Levee and riprap removal 10/31/2012 11/15/2012
Installation of riparian vegetation U: 47. Riparian Planting 10/31/2012
Installation of riparian vegetation V: 47. Floodplain Planting 10/31/2012
Monitoring plan W: 174. Prepare monitoring plan for post construction plan mortality 10/31/2012
Fence Installation X: 40. Riparian and pasture fencing installation 10/31/2012
Water Facility Y: 34. Construct water facility 10/31/2012
Attach Progress Report in Pisces AA: 132. Submit Progress Report for the period June 2011 to Oct 2012 12/14/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 11 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 5 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 174 Produce Plan
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 11 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 5 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 174 Produce Plan
Trout, Bull (S. confluentus) (Threatened)
  • 11 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 5 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete EC permitting processes 06/01/2011
B 119 Lead coordination efforts for project implementation 06/01/2011
C 191 Lead coordination efforts for watershed wide restoration 06/01/2011
D 29 Floodplain Connection Engineered Log Jam 06/28/2011
E 29 Large Woody Debris Recruitment 06/28/2011
F 29 Side Channel Structures 06/28/2011
G 29 Buried Engineered Log Jam diffuser 06/28/2011
H 29 Mid-channel Engineered Log Jam 06/28/2011
I 29 Side Channel Large Woody Debris 06/28/2011
J 29 % Floodplain Connection Engineered Log Jam 06/28/2011
K 29 % Bank Large Wood Debris 06/28/2011
L 29 Mid-channel Engineered Log Jam 06/28/2011
M 29 Large Woody Debris Enhancement 06/28/2011
N 29 Floodplain connection Engineered Log Jam 06/28/2011
O 30 Excavated side channel 06/28/2011
P 30 % Inlet levee breach 06/28/2011
Q 30 % %Inlet and side channel excavation 06/28/2011
R 30 Side channel excavation 06/28/2011
S 30 Inlet at streambank breach 06/28/2011
T 180 Levee and riprap removal 06/28/2011
U 47 Riparian Planting 06/28/2011
V 47 Floodplain Planting 06/28/2011
W 174 Prepare monitoring plan for post construction plan mortality 06/01/2011
X 40 Riparian and pasture fencing installation 06/28/2011
Y 34 Construct water facility 06/28/2011
Z 185 Periodic Status Reports for BPA 06/01/2011
AA 132 Submit Progress Report for the period June 2011 to Oct 2012 06/01/2011