Province | Subbasin | % |
---|---|---|
Columbia Cascade | Entiat | 25.00% |
Methow | 25.00% | |
Okanogan | 25.00% | |
Wenatchee | 25.00% |
Previous: | Next: |
---|---|
n/a |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Obtain required permits prior to 2011 construction of project. | A: 165. Complete EC permitting processes | 07/08/2011 | 08/06/2011 | |
Complete all project management and administrative activities for the project | B: 119. Lead coordination efforts for project implementation | 10/31/2012 | 12/14/2012 | |
Stakeholder Coordination | C: 191. Lead coordination efforts for watershed wide restoration | 10/31/2012 | 12/14/2012 | |
Floodplain connection engineered log jam | D: 29. Floodplain Connection Engineered Log Jam | 10/31/2012 | 09/15/2012 | |
Large Woody Debris Installation | E: 29. Large Woody Debris Recruitment | 10/31/2012 | 09/30/2012 | |
Large Woody Debris Installation | F: 29. Side Channel Structures | 10/31/2012 | 09/30/2012 | |
Buried Diffuser | G: 29. Buried Engineered Log Jam diffuser | 10/31/2012 | 09/30/2012 | |
Mid-channel elj | H: 29. Mid-channel Engineered Log Jam | 10/31/2012 | 09/30/2012 | |
Large Woody Debris Installation | I: 29. Side Channel Large Woody Debris | 10/31/2012 | 09/30/2012 | |
% Floodplain connection elj | J: 29. % Floodplain Connection Engineered Log Jam | 12/14/2012 | 09/30/2012 | |
% Large Woody Debris Installation | K: 29. % Bank Large Wood Debris | 12/14/2012 | 11/15/2012 | |
Large Woody Debris Installation | L: 29. Mid-channel Engineered Log Jam | 10/31/2012 | 09/30/2012 | |
Large Woody Debris Installation | M: 29. Large Woody Debris Enhancement | 10/31/2012 | 09/30/2012 | |
Large Woody Debris Installation | N: 29. Floodplain connection Engineered Log Jam | 10/31/2012 | 09/30/2012 | |
New side channel through existing beaver ponds | O: 30. Excavated side channel | 10/31/2012 | 11/15/2012 | |
% New inlet breach in upper levee | P: 30. % Inlet levee breach | 12/14/2012 | 11/15/2012 | |
% Levee inlet and side channel excavation | Q: 30. % %Inlet and side channel excavation | 12/14/2012 | 11/15/2012 | |
Side channel excavation | R: 30. Side channel excavation | 10/31/2012 | 11/15/2012 | |
Inlet breach | S: 30. Inlet at streambank breach | 10/31/2012 | 09/20/2012 | |
Levee and riprap removal | T: 180. Levee and riprap removal | 10/31/2012 | 11/15/2012 | |
Installation of riparian vegetation | U: 47. Riparian Planting | 10/31/2012 | ||
Installation of riparian vegetation | V: 47. Floodplain Planting | 10/31/2012 | ||
Monitoring plan | W: 174. Prepare monitoring plan for post construction plan mortality | 10/31/2012 | ||
Fence Installation | X: 40. Riparian and pasture fencing installation | 10/31/2012 | ||
Water Facility | Y: 34. Construct water facility | 10/31/2012 | ||
Attach Progress Report in Pisces | AA: 132. Submit Progress Report for the period June 2011 to Oct 2012 | 12/14/2012 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Complete EC permitting processes | 06/01/2011 | ||||||
B | 119 | Lead coordination efforts for project implementation | 06/01/2011 | ||||||
C | 191 | Lead coordination efforts for watershed wide restoration | 06/01/2011 | ||||||
D | 29 | Floodplain Connection Engineered Log Jam | 06/28/2011 | ||||||
E | 29 | Large Woody Debris Recruitment | 06/28/2011 | ||||||
F | 29 | Side Channel Structures | 06/28/2011 | ||||||
G | 29 | Buried Engineered Log Jam diffuser | 06/28/2011 | ||||||
H | 29 | Mid-channel Engineered Log Jam | 06/28/2011 | ||||||
I | 29 | Side Channel Large Woody Debris | 06/28/2011 | ||||||
J | 29 | % Floodplain Connection Engineered Log Jam | 06/28/2011 | ||||||
K | 29 | % Bank Large Wood Debris | 06/28/2011 | ||||||
L | 29 | Mid-channel Engineered Log Jam | 06/28/2011 | ||||||
M | 29 | Large Woody Debris Enhancement | 06/28/2011 | ||||||
N | 29 | Floodplain connection Engineered Log Jam | 06/28/2011 | ||||||
O | 30 | Excavated side channel | 06/28/2011 | ||||||
P | 30 | % Inlet levee breach | 06/28/2011 | ||||||
Q | 30 | % %Inlet and side channel excavation | 06/28/2011 | ||||||
R | 30 | Side channel excavation | 06/28/2011 | ||||||
S | 30 | Inlet at streambank breach | 06/28/2011 | ||||||
T | 180 | Levee and riprap removal | 06/28/2011 | ||||||
U | 47 | Riparian Planting | 06/28/2011 | ||||||
V | 47 | Floodplain Planting | 06/28/2011 | ||||||
W | 174 | Prepare monitoring plan for post construction plan mortality | 06/01/2011 | ||||||
X | 40 | Riparian and pasture fencing installation | 06/28/2011 | ||||||
Y | 34 | Construct water facility | 06/28/2011 | ||||||
Z | 185 | Periodic Status Reports for BPA | 06/01/2011 | ||||||
AA | 132 | Submit Progress Report for the period June 2011 to Oct 2012 | 06/01/2011 |