Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56065 REL 18: 2007-246-00 EXP PNNL RESTORATION OF BULL TROUT PASS
Project Number:
Title:
Restoration of Bull Trout Passage at Albeni Falls Dam
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
56065 REL 18
Contract Title:
2007-246-00 EXP PNNL RESTORATION OF BULL TROUT PASS
Contract Continuation:
Previous: Next:
56065 REL 14: 2007-246-00 EXP PNNL RESTORATION OF BULL TROUT PASS
  • 56065 REL 21: 2007-246-00 EXP RESTORATION OF BULL TROUT PASS
Contract Status:
Closed
Contract Description:
The primary goal of the proposed project is to monitor and evaluate the effectiveness of a fish trap installed in the tailrace of Albeni Falls Dam by the Kalispel Tribe of Indians (herein ‘Tribe’).  The Tribe requested the assistance of PNNL to evaluate the trap based on their experience with telemetry monitoring technologies and over a decade of experience studying migratory fishes at Albeni Falls Dam.  The trap will be primarily designed to capture migrating bull trout Salvelinus confluentus and westslope cutthroat trout Oncorhynchus clarki lewisi, which will then be manually transported above Albeni Falls Dam by the Tribe as a means of temporary passage until a more permanent fish passage structure is built.  
A secondary goal is to continue operation of previously installed telemetry equipment downstream of Albeni Falls Dam that are being used to evaluate use of coldwater refuges of bull trout; refuges that are necessary for fish entrained downstream of AFD to survive high summer water temperatures.

PNNL has two objectives for the May 2016 - April 2017 contract period:

1) Determine the movement behavior of tagged fish within the tailrace of Albeni Falls Dam and whether they enter the fish trap, or come in close proximity of the trap but do not enter it.
2) Continue radio telemetry system monitoring downstream of Albeni Falls Dam in the Pend Oreille River to identify bull trout use of coldwater refuge habitat.
Account Type(s):
Expense
Contract Start Date:
05/01/2016
Contract End Date:
04/30/2017
Current Contract Value:
$77,682
Expenditures:
$77,682

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Ensure environmental compliance requirements are complete B: 165. Complete environmental compliance requirements 04/30/2017 04/30/2017
Functioning monitoring station on fish trap C: 70. Re-Install monitoring station on fish trap 09/01/2016 05/23/2016
Functioning radio monitoring stations throughout study period D: 157. Maintain and download radio receiving stations 04/30/2017 04/30/2017
Develop a profile of each fish tracked E: 162. Data reduction and analysis 04/30/2017 01/02/2017
Completed Annual Report F: 132. Submit Progress Report for the period 15 Nov 2015 through 31 Dec 2016 04/30/2017 04/30/2017
All administrative tasks fulfilled with timely quality products G: 119. Manage Project 04/30/2017 04/30/2017
Testing and calibration of all monitoring stations H: 70. Test all stations prior to next monitoring season, if applicable 04/30/2017 04/30/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Bull (S. confluentus) (Threatened)
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 05/01/2016
B 165 Complete environmental compliance requirements 05/01/2016
C 70 Re-Install monitoring station on fish trap 05/01/2016
D 157 Maintain and download radio receiving stations 05/01/2016
E 162 Data reduction and analysis 05/01/2016
F 132 Submit Progress Report for the period 15 Nov 2015 through 31 Dec 2016 05/01/2016
G 119 Manage Project 05/01/2016
H 70 Test all stations prior to next monitoring season, if applicable 05/01/2016