Contract 56662 REL 142: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Project Number:
Title:
Upper Columbia Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 20.00%
Methow 40.00%
Wenatchee 40.00%
Contract Number:
56662 REL 142
Contract Title:
2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Contract Continuation:
Previous: Next:
n/a
  • 56662 REL 169: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
This contract will fund the Yakama Nation's Upper Columbia Habitat Restoration Project to seek, design and implement fish habitat restoration projects throughout the Methow, Entiat, and Wenatchee subbasins for the FY 2018 performance period.  Administrative tasks related to this SOW, such as reporting and inventory management, are provided under BPA Contract 56662 REL 111.
Account Type(s):
Expense
Contract Start Date:
10/01/2017
Contract End Date:
12/31/2018
Current Contract Value:
$2,620,683
Expenditures:
$2,620,683

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shannon Adams Yakama Confederated Tribes No Interested Party adas@yakamafish-nsn.gov (509) 945-0754
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Jason Breidert Yakama Confederated Tribes Yes Technical Contact brej@yakamafish-nsn.gov (509) 860-5351
Chris Butler Yakama Confederated Tribes Yes Technical Contact butlerc@yakamafish-nsn.gov (509) 449-8215
Christopher Clemons Yakama Confederated Tribes Yes Technical Contact clec@yakamafish-nsn.gov (509) 881-5746
Madeleine Eckmann Yakama Confederated Tribes Yes Technical Contact eckm@yakamafish-nsn.gov (509) 449-2091
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Tana Hoptowit Yakama Confederated Tribes No Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Jarred Johnson Yakama Confederated Tribes Yes Technical Contact johj@yakamafish-nsn.gov (509) 881-1462
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Timothy Ludington Bonneville Power Administration Yes COR tsludington@bpa.gov (503) 230-4988
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Steve Parker Yakama Confederated Tribes Yes Supervisor pars@yakamafish-nsn.gov (509) 865-6262x6342
Brandon Rogers Yakama Confederated Tribes Yes Contract Manager rogb@yakamafish-nsn.gov (509) 949-4109
Hans Smith Yakama Confederated Tribes Yes Contract Manager h.smith@methownet.com (509) 449-2750
Matt Wilberding Yakama Confederated Tribes Yes Technical Contact wilm@yakamafish-nsn.gov (509) 881-7091


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All administrative tasks fulfilled with timely quality products B: 119. Perform project management and administrative duties 12/31/2018 12/31/2018
USFS EC Support on Yakama Nation Fisheries Projects (BPA's EC covered in REL 111) D: 165. FY 18 USFS NEPA 2017-165 (BPA's EC covered in REL 111) 12/31/2018 12/31/2018
Conceptual Restoration Plan for Upper Stillwaters USFS Lands E: 175. Entiat Upper Stillwaters USFS Design 2017-167 12/31/2018 12/31/2018
Permit Level Restoration Plan for Stormy A Project Site F: 175. Stormy Area A - USFS Re-Design 2014-125 12/31/2018 12/31/2018
Restoration and Monitoring Plan for Tillicum Creek Fan G: 175. Tillicum Creek Fan Engineering 2016-161 12/31/2018 09/25/2018
Construction Management H: 100. Tillicum Creek Fan Construction Oversight 2016-161 12/31/2018 07/27/2018
Tillicum Fan Restoration I: 29. Tillicum Creek Fan Construction 2016-161 12/31/2018 07/27/2018
Mad River Reach Assessment Report J: 115. Mad River Reach Assessment 2017-172 12/31/2018 12/31/2018
Upper Nason Creek Reach Assessment Report N: 115. Upper Nason Habitat Assessment 2017-192 12/31/2018 12/31/2018
Final Restoration Designs and Monitoring Plan for the Upper Kahler Project O: 175. Upper Kahler - Design 2017-166 12/31/2018 12/31/2018
Restoration Plan for Peshastin RM 2.7 P: 175. Peshastin RM 2.7 - Design 2016-160 12/31/2018 07/03/2018
Construction Management Q: 100. Peshastin RM 2.7 - Construction Management 2016-160 12/31/2018 09/04/2018
Construct the Peshastin RM 2.7 Project R: 30. Peshastin RM 2.7 - Construction 2016-160 12/31/2018 08/15/2018
Skinney Creek Finalized Restoration Plan S: 175. Skinney Creek Design 2015-144 12/31/2018
Nason Confluence Finalized Restoration Plan T: 175. Nason Confluence - Design 2013-105 12/31/2018
Chiwawa Fan Finalized Restoration Plan U: 175. Chiwawa Fan - Design 2016-165 12/31/2018
Permit Level Restoration Plan for Chewuch RM 4.6 V: 175. Chewuch RM 4.6 Design 2017-176 12/31/2018 12/31/2018
Conceptual Restoration Plan for Chewuch RM 8 to 9 Project W: 175. Chewuch RM 8 to 9 Design 2017-177 12/31/2018 12/31/2018
Construction Management X: 100. Chewuch RM 17 to 20 Construction Oversight 2015-140 12/31/2018 12/31/2018
Construct the Chewuch RM17-20 Project Y: 29. Chewuch RM 17 to 20 Construction 2015-140 12/31/2018 07/27/2018
Upper Chewuch River Habitat Assessment Report Z: 115. Upper Chewuch Habitat Assessment 2017-180 12/31/2018 12/31/2018
Beaver Creek Reach 5 Finalized Restoration Plan AA: 175. Beaver Creek Reach 5 - Design 2017-171 12/31/2018 12/31/2018
Finalized Restoration Plan for the Fawn Creek Project Area AD: 175. Fawn Creek Project - Design 2015-147 12/31/2018
Concepts Level Restoration Plan for Poorman Creek Road Project Area AF: 175. Poorman Creek Road Side Channel Project - Design 2012-100 12/31/2018 12/31/2018
River Recreation Use Assessment Report AG: 174. Twisp to Carlton River Recreation Assessment 2017-174 12/31/2018 12/31/2018
Concepts Level Restoration Plan for the Upper Twisp River Assessment Area AH: 175. Upper Twisp River and Tributaries Project Design (USFS Projects) 2016-162 12/31/2018 12/31/2018
Finalized Restoration Plan for the Twisp River War Creek Area AI: 175. Twisp River - War Creek Area Restoration Design 2015-148 12/31/2018 12/31/2018
Concepts Level Restoration Plan for Little Bridge Creek USFS Lands AJ: 175. Little Bridge Creek Design (USFS Projects) 2017-182 12/31/2018 12/31/2018
Finalized Restoration Plan for Twisp Horseshoe USFS Lands AK: 175. Twisp Horseshoe Phase 2 (USFS) Restoration Engineering 2010-39 12/31/2018 12/31/2018
Construction Management AL: 100. Twisp Horseshoe Phase 1 Culvert Construction Oversight 2010-39 12/31/2018 12/31/2018
Side Channel Restored AM: 30. Twisp Horseshoe Phase 1 Culvert Construction 2010-39 12/31/2018 08/31/2018
Confidential Water Rights Evaluation AP: 154. Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 12/31/2018 12/31/2018
Alternative Water Delivery Feasibility Assessment AQ: 175. Methow Basin EWD Instream Flow Project - Eng. Feasibility Assessment 2015-152 12/31/2018
Permit Level Restoration Plan for the M2 Twisp to Carlton Project Sites AS: 175. M2 Twisp To Carlton Projects Design 2017-191 12/31/2018 12/31/2018
Finalized Restoration Plan for the Wolf Creek Ponds AT: 175. Wolf Creek Ponds Design 2017-188 12/31/2018 12/31/2018
Conceptual Restoration Plan for Upper Wenatchee Deadhorse Project AU: 175. NEW CCR 40108/Mod. 1 - Upper Wenatchee Deadhorse Tunnel Design 2012-103 12/31/2018
Restoration and Monitoring Plan for Beaver Creek DOT Project AV: 175. NEW CCR 40108/Mod. 1 - Beaver Creek DOT Design Replacement 2017-194 12/31/2018
Construction Management Complete AW: 100. NEW CCR 40108/Mod. 1 - Beaver Creek DOT Construction Management 2017-194 12/31/2018
Construct the Beaver Creek DOT Project AX: 29. NEW CCR 40108/Mod. 1 - Beaver Creek DOT Construction 2017-194 12/31/2018
Partial completion of BPA's land acquisition process AY: 172. NEW CCR 40108/Mod. 1 - Western Rivers Methow Acquisition Support 2018-200 12/31/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 4 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 3 instances of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 174 Produce Plan
  • 27 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 6 instances of WE 100 Construction Management
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 115 Produce Inventory or Assessment
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 4 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 3 instances of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 174 Produce Plan
  • 27 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 6 instances of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 6 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2017
B 119 Perform project management and administrative duties 10/01/2017
C 132 (No annual report required for this contract) 10/01/2017
D 165 FY 18 USFS NEPA 2017-165 (BPA's EC covered in REL 111) 10/01/2017
E 175 Entiat Upper Stillwaters USFS Design 2017-167
F 175 Stormy Area A - USFS Re-Design 2014-125
G 175 Tillicum Creek Fan Engineering 2016-161
H 100 Tillicum Creek Fan Construction Oversight 2016-161 10/01/2017
I 29 Tillicum Creek Fan Construction 2016-161
J 115 Mad River Reach Assessment 2017-172
K 174 Lower Icicle River Recreation Assessment 2017-170
L 175 Leavenworth Area Design 2017-185
M 175 Lower Wenatchee River Reach 3 Design 2017-186
N 115 Upper Nason Habitat Assessment 2017-192
O 175 Upper Kahler - Design 2017-166
P 175 Peshastin RM 2.7 - Design 2016-160
Q 100 Peshastin RM 2.7 - Construction Management 2016-160 10/01/2017
R 30 Peshastin RM 2.7 - Construction 2016-160 06/05/2018
S 175 Skinney Creek Design 2015-144
T 175 Nason Confluence - Design 2013-105
U 175 Chiwawa Fan - Design 2016-165
V 175 Chewuch RM 4.6 Design 2017-176
W 175 Chewuch RM 8 to 9 Design 2017-177
X 100 Chewuch RM 17 to 20 Construction Oversight 2015-140 10/01/2017
Y 29 Chewuch RM 17 to 20 Construction 2015-140 08/31/2017
Z 115 Upper Chewuch Habitat Assessment 2017-180
AA 175 Beaver Creek Reach 5 - Design 2017-171
AB 175 Beaver Creek Fan Design 2017-193
AC 175 Beaver Creek DOT Design 2017-194
AD 175 Fawn Creek Project - Design 2015-147
AE 175 Hancock Springs - Lower Creek - Design 2009-14
AF 175 Poorman Creek Road Side Channel Project - Design 2012-100
AG 174 Twisp to Carlton River Recreation Assessment 2017-174
AH 175 Upper Twisp River and Tributaries Project Design (USFS Projects) 2016-162
AI 175 Twisp River - War Creek Area Restoration Design 2015-148
AJ 175 Little Bridge Creek Design (USFS Projects) 2017-182
AK 175 Twisp Horseshoe Phase 2 (USFS) Restoration Engineering 2010-39
AL 100 Twisp Horseshoe Phase 1 Culvert Construction Oversight 2010-39 10/01/2017
AM 30 Twisp Horseshoe Phase 1 Culvert Construction 2010-39 10/01/2017
AN 100 Early Winters Creek – Twenty Below Construction Management 2014-117 10/01/2017
AO 29 Early Winters Creek – Twenty Below Construction 2014-117
AP 154 Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 10/01/2017
AQ 175 Methow Basin EWD Instream Flow Project - Eng. Feasibility Assessment 2015-152
AR 175 Methow Weeman Side Channel Design 2017-189
AS 175 M2 Twisp To Carlton Projects Design 2017-191
AT 175 Wolf Creek Ponds Design 2017-188
AU 175 NEW CCR 40108/Mod. 1 - Upper Wenatchee Deadhorse Tunnel Design 2012-103
AV 175 NEW CCR 40108/Mod. 1 - Beaver Creek DOT Design Replacement 2017-194
AW 100 NEW CCR 40108/Mod. 1 - Beaver Creek DOT Construction Management 2017-194 10/01/2017
AX 29 NEW CCR 40108/Mod. 1 - Beaver Creek DOT Construction 2017-194 08/31/2018
AY 172 NEW CCR 40108/Mod. 1 - Western Rivers Methow Acquisition Support 2018-200 10/01/2017