Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 300: 2009-003-00 EXP YN - UC HABITAT RESTORATION
Project Number:
Title:
Upper Columbia Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 20.00%
Methow 40.00%
Wenatchee 40.00%
Contract Number:
56662 REL 300
Contract Title:
2009-003-00 EXP YN - UC HABITAT RESTORATION
Contract Continuation:
Previous: Next:
91619: 2009-003-00 EXP YN - UC HABITAT RESTORATION
  • 96143: 2009-003-00 EXP UC HABITAT PROJECTS - DESIGN & CONSTRUCT
Contract Status:
Issued
Contract Description:
This contract will fund the Yakama Nation Fisheries Upper Columbia Habitat Restoration Project to seek, design and implement fish habitat restoration projects throughout the Methow, Entiat, and Wenatchee subbasins for the Calendar Year 2024 performance period.  Administrative tasks related to this SOW, such as reporting and inventory management, are provided under BPA Contract 56662 REL 289 (through 5/31/24, then tasks will transfer to the subsequent FY24 release).

This contract details salmon habitat restoration work being designed or implemented in the Upper Columbia Spring Chinook Salmon and Steelhead recovery area under the guidance of the Upper Columbia Spring Chinook Salmon and Steelhead Recovery Plan and the 2021 Habitat Restoration Prioritization.  Yakama Nation Fisheries uses project and ecological concern prioritizations contained within the 2021 Habitat Restoration Prioritization and within Habitat and Geomorphic Reach Assessments reviewed by the Upper Columbia Regional Technical Team to determine which project action types and locations to pursue.  At the project level, Yakama Nation Fisheries subcontracts with technical consultants to develop salmon habitat restoration actions that best address prioritized ecological concerns limiting salmon and steelhead productivity and abundance.  

Work Element actions in 2024 include:

REACH ASSESSMENT PROJECTS (2024 HABITAT ASSESSMENTS)

Methow Subbasin:
Methow River-Thompson Creek and Methow River-Fawn Creek Assessment Units - Methow River Reach Assessment Update (Weeman Bridge to Twisp)

Wenatchee Subbasin:
Middle and Lower Icicle Assessment Units - Icicle River Reach Assessment
Lower Nason Creek Assessment Unit - Nason Creek Reach Assessment Update
Chiwaukum Creek Assessment Unit - Chiwaukum Creek Reach Assessment
Lower White River Assessment Unit - Lower White River Reach Assessment

Entiat Subbasin:
Entiat River-Preston Creek and Entiat River-Potato Creek Assessment Units - Middle Entiat Reach Assessment Update

DESIGN PROJECTS (2024 ENGINEERING AND DESIGN PROJECTS)

Methow Subbasin:
Chewuch River-Doe Creek Assessment Unit - Chewuch USFS
Wolf Creek Assessment Unit - Wolf Creek USFS
Methow River-Fawn Creek Assessment Unit - Methow Basin EWD Instream Flow Project
Early Winters Creek Assessment Unit - Early Winters Creek USFS
Methow River-Rattlesnake Creek Assessment Unit - Upper Methow USFS
Methow River-Thompson Creek Assessment Unit - W2 Foghorn Reach, 1890s Outlet, and Two Channels Project

Wenatchee Subbasin:
Lower Nason Creek Assessment Unit - Nason Creek N1 DOT Project and Upper Nason Phase 3
Lower Chiwawa River Assessment Unit - Lower Chiwawa Big Meadow
Wenatchee River-Nahahum Canyon Assessment Unit - Lower Wenatchee River Reach 3 Restoration

Entiat Subbasin:
Entiat River-Lake Creek Assessment Unit - Entiat Stillwaters USFS
Mad River Assessment Unit - Mad River (USFS) Projects, Mad River Outlet, MRO Instream Flow Project

RESTORATION ACTIONS (2024 CONSTRUCTION ACTIONS)

Methow Subbasin:
Lower Twisp Assessment Unit - Newby Narrows Phase 2

Entiat Subbasin:
Mad River Assessment Unit - Mad River USFS

Wenatchee Subbasin:
Lower Nason Creek Assessment Unit - Upper Nason Creek Restoration Phase 2
Lower Chiwawa River Assessment Unit - Lower Chiwawa USFS and Chiwawa Outlet

For all three subbasins, this contract also details a scope of work for continuing to partner with the United States Forest Service to implement salmon recovery actions on USFS managed lands.  Through a cooperative agreement with the USFS, the Yakama Nation provides some cost reimbursement coverage to the USFS for federal staff costs on conducting NEPA and environmental compliance review on Yakama Nation sponsored projects.
Account Type(s):
Expense
Contract Start Date:
01/01/2024
Contract End Date:
12/31/2024
Current Contract Value:
$5,047,922
Expenditures:
$3,695,356

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shannon Adams Yakama Confederated Tribes No Interested Party adas@yakamafish-nsn.gov (509) 945-0754
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
James Albani Yakama Confederated Tribes Yes Technical Contact albj@yakamafish-nsn.gov (651) 341-3211
Victoria Bohlen Bonneville Power Administration Yes COR vlbohlen@bpa.gov (503) 230-3506
Chris Butler Yakama Confederated Tribes Yes Technical Contact butlerc@yakamafish-nsn.gov (509) 449-8215
Annet Dillman Yakama Confederated Tribes Yes Administrative Contact dila@yakamafish-nsn.gov (509) 865-2255
Madeleine Eckmann Yakama Confederated Tribes Yes Technical Contact eckm@yakamafish-nsn.gov (509) 449-2091
Lindsay Henning Yakama Confederated Tribes Yes Technical Contact henl@yakamafish-nsn.gov (509) 860-5351
Tamera Hoptowit Yakama Confederated Tribes No Administrative Contact Hopta@yakamafish-nsn.gov (509) 865-5121x6354
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
James Hudson Yakama Confederated Tribes Yes Technical Contact hudj@yakamafish-nsn.gov (509) 907-0538
Jarred Johnson Yakama Confederated Tribes Yes Technical Contact johj@yakamafish-nsn.gov (509) 881-1462
Michelle O'Malley Bonneville Power Administration Yes F&W Approver mmomalley@bpa.gov (503) 230-5138
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023
Brandon Rogers Yakama Confederated Tribes Yes Supervisor rogb@yakamafish-nsn.gov (509) 949-4109
Hans Smith Yakama Confederated Tribes Yes Contract Manager h.smith@methownet.com (509) 449-2750
Elizabeth Witkowski Yakama Confederated Tribes Yes Technical Contact wite@yakamafish-nsn.gov (509) 881-7091
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Benjamin Woodworth Yakama Confederated Tribes No Technical Contact woob@yakamafish-nsn.gov (360) 920-9544


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Perform project management and administrative duties 12/31/2024
USFS Environmental Compliance on Yakama Nation Fisheries Projects D: 165. FY24 USFS NEPA 2017-164 12/31/2024
Final Construction Plan for the Chewuch USFS Project Area E: 175. Chewuch USFS Designs Phase 3 & 4 - 2019-208 12/31/2024
Permit Level and Final Designs and Report for the Wolf Creek USFS Project Area F: 175. Wolf Creek USFS Design Phase 3 & 4 - 2021-213 12/01/2024
Confidential Water Rights Evaluation G: 154. Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 12/31/2024
Permit Level and Final Designs for the Methow Basin EWD Instream Flow Project H: 175. Methow Basin EWD Instream Flow Project - Eng. and Design Phase 3 & 4 - 2015-152 12/31/2024
Conceptual Designs and Report for the Early Winters USFS Project Area I: 175. Early Winters Creek USFS Conceptual Designs - 2014-117 12/31/2024
Conceptual Designs and Report for the Upper Methow Project Area J: 175. Upper Methow Conceptual Designs - 2023-218 12/31/2024
Conceptual Designs and Report for the W2 Foghorn Project Area K: 175. W2 Foghorn Reach Conceptual Designs - 2023-219 12/31/2024
Conceptual Designs and Report for the 1890s Outlet Project L: 175. 1890s Outlet Conceptual Design - 2011-65 12/31/2024
Conceptual Designs and Report for the Two Channels Area M: 175. Two Channels Conceptual Design - 2011-89 12/31/2024
Report drafted and submitted for review N: 115. Methow River Reach Assessment Updates (Big Valley & M2) - 2023-220 12/31/2024
Nason Creek N1 DOT Permit and Construction Level Designs O: 175. Nason Creek N1 DOT Design Phase 3 and 4 - 2018-198 12/31/2024
Draft Construction Plan for the Upper Nason Phase 3 Project P: 175. Upper Nason Creek Side Channel Redesign Phase 3 2020-207 12/31/2024
Final Construction Plan for the Lower Chiwawa Big Meadow Project Q: 175. Lower Chiwawa Big Meadow Phases 3 and 4 - 2021-214 12/31/2024
Final Construction Plan for the Lower Wenatchee Reach 3 Project Area R: 175. Lower Wenatchee River Reach 3 Design Phases 3 and 4 - 2017-186 12/31/2024
Nason Creek, Icicle Creek, Chiwaukum Creek, and White River reports drafted and submitted for review S: 115. Wenatchee Subbasin Reach Assessments (Nason Creek, Icicle, White River, Chiwaukum) - 2023-221 12/31/2024
Draft Construction Plan for the Mad River Outlet Project Area T: 175. Mad River Outlet Design Phase 3 - 2021-215 12/31/2024
Confidential Water Rights Evaluation U: 154. Entiat Basin MRO Instream Flow Project - Water Rights Consulting 2022-217 12/31/2024
Alternative Water Delivery Feasibility Assessment V: 175. Entiat Basin MRO Instream Flow Project - Eng. Feasibility Assessment 2022-217 12/31/2024
Conceptual Designs and Report for the Entiat Stillwaters USFS Project Area W: 175. Entiat Stillwaters Design Phase 2 - 2019-210 12/31/2024
Report drafted and submitted for review X: 115. Middle Entiat Reach Assessment Updates (Grey, Stormy, Preston Reaches) - 2023-222 12/31/2024
Construction Management Complete Y: 100. Newby Narrows Oversight 2015-153 12/31/2024
Side Channel Restoration and Large Wood Habitat added into 0.3 miles of the Twisp River. Z: 30. Newby Narrows Construction 2015-153 12/31/2024
Construction Management Complete AA: 100. Mad River USFS Oversight 2017-172 12/31/2024
Large wood habitat and side channel elements added into three miles of the Mad River AB: 29. Mad River USFS Construction 2017-172 12/31/2024
Construction Management Complete AC: 100. Upper Nason Creek Yr 2 Oversight 2020-207 12/31/2024
Large wood habitat elements added into 1 mile of Nason Creek AD: 29. Upper Nason Creek Yr 2 Construction 2020-207 12/31/2024
Construction Management Complete AE: 100. Chiwawa Outlet Oversight 2019-205 12/31/2024
Large wood habitat elements added into 0.5 miles of the Chiwawa River AF: 29. Chiwawa Outlet Construction 2019-205 12/31/2024
Construction Management Complete AG: 100. Lower Chiwawa USFS Oversight 2021-214 12/31/2024
Side Channel Restoration and Large Wood Habitat added into 0.7 miles of the Chiwawa River AH: 30. Lower Chiwawa USFS Construction 2021-214 12/31/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 3 instances of WE 115 Produce Inventory or Assessment
  • 15 instances of WE 175 Produce Design
  • 2 instances of WE 154 Develop and Negotiate Water Right Transaction
  • 5 instances of WE 100 Construction Management
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 3 instances of WE 115 Produce Inventory or Assessment
  • 14 instances of WE 175 Produce Design
  • 2 instances of WE 154 Develop and Negotiate Water Right Transaction
  • 5 instances of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Perform project management and administrative duties
C 132 No deliverable - Annual report is provided under partner contract
D 165 FY24 USFS NEPA 2017-164
E 175 Chewuch USFS Designs Phase 3 & 4 - 2019-208 09/13/2024
F 175 Wolf Creek USFS Design Phase 3 & 4 - 2021-213 09/13/2024
G 154 Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152
H 175 Methow Basin EWD Instream Flow Project - Eng. and Design Phase 3 & 4 - 2015-152 09/13/2024
I 175 Early Winters Creek USFS Conceptual Designs - 2014-117 09/13/2024
J 175 Upper Methow Conceptual Designs - 2023-218 09/13/2024
K 175 W2 Foghorn Reach Conceptual Designs - 2023-219 09/13/2024
L 175 1890s Outlet Conceptual Design - 2011-65 09/13/2024
M 175 Two Channels Conceptual Design - 2011-89 09/13/2024
N 115 Methow River Reach Assessment Updates (Big Valley & M2) - 2023-220 04/22/2024
O 175 Nason Creek N1 DOT Design Phase 3 and 4 - 2018-198 09/13/2024
P 175 Upper Nason Creek Side Channel Redesign Phase 3 2020-207 06/28/2024
Q 175 Lower Chiwawa Big Meadow Phases 3 and 4 - 2021-214 09/13/2024
R 175 Lower Wenatchee River Reach 3 Design Phases 3 and 4 - 2017-186 09/13/2024
S 115 Wenatchee Subbasin Reach Assessments (Nason Creek, Icicle, White River, Chiwaukum) - 2023-221 04/22/2024
T 175 Mad River Outlet Design Phase 3 - 2021-215 09/13/2024
U 154 Entiat Basin MRO Instream Flow Project - Water Rights Consulting 2022-217
V 175 Entiat Basin MRO Instream Flow Project - Eng. Feasibility Assessment 2022-217 09/13/2024
W 175 Entiat Stillwaters Design Phase 2 - 2019-210 09/13/2024
X 115 Middle Entiat Reach Assessment Updates (Grey, Stormy, Preston Reaches) - 2023-222 04/22/2024
Y 100 Newby Narrows Oversight 2015-153
Z 30 Newby Narrows Construction 2015-153 04/09/2024
AA 100 Mad River USFS Oversight 2017-172
AB 29 Mad River USFS Construction 2017-172 06/11/2024
AC 100 Upper Nason Creek Yr 2 Oversight 2020-207
AD 29 Upper Nason Creek Yr 2 Construction 2020-207 02/29/2024
AE 100 Chiwawa Outlet Oversight 2019-205
AF 29 Chiwawa Outlet Construction 2019-205 01/01/2024
AG 100 Lower Chiwawa USFS Oversight 2021-214
AH 30 Lower Chiwawa USFS Construction 2021-214 05/20/2024