Contract 56662 REL 50: 1996-035-01 EXP YAKIMA RESERVATION WATERSHED PROJECT (YRWP)
Project Number:
Title:
Yakama Reservation Watershed Project
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
56662 REL 50
Contract Title:
1996-035-01 EXP YAKIMA RESERVATION WATERSHED PROJECT (YRWP)
Contract Continuation:
Previous: Next:
56662 REL 15: 1996-035-01 EXP YAKIMA RESERVATION WATERSHED PROJECT (YRWP)
  • 56662 REL 77: 1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Contract Status:
Closed
Contract Description:
The YRWP works to restore natural function to the Satus, Toppenish and Ahtanum Watersheds. Our restoration and monitoring efforts take a comprehensive approach to the restoration of habitat for fisheries resources including steelhead and bull trout.
Account Type(s):
Expense
Contract Start Date:
03/01/2014
Contract End Date:
02/28/2015
Current Contract Value:
$1,091,108
Expenditures:
$1,091,108

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shannon Adams Yakama Confederated Tribes Yes Contract Manager adas@yakamafish-nsn.gov (509) 945-0754
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Kelly Clayton Yakama Confederated Tribes Yes Interested Party clak@yakamafish-nsn.gov (509) 945-7195
Ryan DeKnikker Yakama Confederated Tribes Yes Contract Manager dekr@yakamafish-nsn.gov (509) 945-5389
Loverne George Yakama Confederated Tribes Yes Administrative Contact geol@yakamafish-nsn.gov (509) 865-5121x6364
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Michelle O'Malley Bonneville Power Administration Yes COR mmomalley@bpa.gov (503) 230-5138
Tim Resseguie Yakama Confederated Tribes Yes Technical Contact rest@yakamafish-nsn.gov (509) 945-7409
Brandon Rogers Yakama Confederated Tribes Yes Interested Party rogb@yakamafish-nsn.gov (509) 949-4109
Paul Ward Yakama Confederated Tribes No Supervisor warp@yakamafish-nsn.gov (509) 949-4129


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
SOW and LIB submitted A: 119. Manage Restoration Projects 10/31/2014 11/14/2014
List of Selected Projects (and contingency projects) to be implemented B: 114. Select habitat improvement actions and identify possible projects for next fiscal year 09/30/2014 09/30/2014
Project databases that are maintained and up to date. C: 160. Update Project Database 02/28/2015 12/31/2014
Disseminated data D: 161. Create informal summary reports and maps 02/28/2015 12/31/2014
5 outreach sessions completed E: 99. Conduct field and classroom education at local schools 02/28/2015 12/31/2014
Technical review and input provided to various policy and planning efforts F: 122. Input to various Tribal planning and policy efforts 02/28/2015 12/31/2014
Completed environmental documentation G: 165. Environmental Compliance 02/28/2015 12/31/2014
Completed Annual Report submitted to BPA H: 132. Produce Project Annual Report for FY14 02/28/2015 02/25/2015
Outmigration estimate and other data from screw traps I: 157. Operate rotary screw traps 02/28/2015 02/28/2015
Complete three pass surveys in Satus and Ahtanum Creeks J: 157. Conduct spawner surveys 02/28/2015 02/28/2015
functioning PIT tag antenna array K: 70. Instal a portable PIT tag antenna array at Ahtanum Creek 02/28/2015 12/18/2014
PIT tag detections L: 157. Collect PIT tag detection data from antenna array on Ahtanum Creek 02/28/2015 02/28/2015
Water temperature record M: 157. Collect water temperature data 12/31/2014 11/23/2014
Weekly manual discharge measurements N: 157. Collect discharge measurements 02/28/2015 02/28/2015
Monitor water level in monitoring wells O: 157. Collect data from monitoring wells 02/28/2015 02/28/2015
Wapato Irrigation Project diversions managed for minimum instream flow. P: 186. Assist with the operation of diversions and screens on Ahtanum Creek 02/28/2015 02/27/2015
water diversion managed at 6 diversions to provide minimum streamflow Q: 186. Assist with operation of diversions and screens on Toppenish Creek 02/28/2015 02/27/2015
Functioning fences, wells, stock tanks, and habitat improvements R: 186. Maintain livestock wells/stock tanks/livestock fences/improved springs 10/31/2014 10/31/2014
Install Barb Wire and Buck & Pole Fence S: 40. Install Riparian/Meadow Barb Wire and Buck & Pole Fence 02/28/2015 02/27/2015
Maintain vegetation T: 198. Maintain pre-existing vegetation 11/30/2014 11/30/2014
Plant vegetation U: 47. First year vegetation planting 11/30/2014 11/01/2014
Remove fish passage barriers W: 85. North Fork Toppenish Creek Fish Barrier Removal and Floodplain Reconnection 09/30/2014 09/30/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 3 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage Restoration Projects 03/01/2014
B 114 Select habitat improvement actions and identify possible projects for next fiscal year 03/01/2014
C 160 Update Project Database 03/01/2014
D 161 Create informal summary reports and maps 03/01/2014
E 99 Conduct field and classroom education at local schools 03/01/2014
F 122 Input to various Tribal planning and policy efforts 03/01/2014
G 165 Environmental Compliance 03/01/2014
H 132 Produce Project Annual Report for FY14 03/01/2014
I 157 Operate rotary screw traps 12/30/2013
J 157 Conduct spawner surveys 12/18/2013
K 70 Instal a portable PIT tag antenna array at Ahtanum Creek 07/08/2014
L 157 Collect PIT tag detection data from antenna array on Ahtanum Creek 03/01/2014
M 157 Collect water temperature data 12/30/2013
N 157 Collect discharge measurements 12/18/2013
O 157 Collect data from monitoring wells 12/18/2013
P 186 Assist with the operation of diversions and screens on Ahtanum Creek 12/18/2013
Q 186 Assist with operation of diversions and screens on Toppenish Creek 12/18/2013
R 186 Maintain livestock wells/stock tanks/livestock fences/improved springs 12/18/2013
S 40 Install Riparian/Meadow Barb Wire and Buck & Pole Fence 12/18/2013
T 198 Maintain pre-existing vegetation 03/01/2014
U 47 First year vegetation planting 03/01/2014
V 29 Place large wood to increase habitat complexity
W 85 North Fork Toppenish Creek Fish Barrier Removal and Floodplain Reconnection 08/20/2014
X 185 Periodic Status Reports for BPA 03/01/2014