Province | Subbasin | % |
---|---|---|
Intermountain | Pend Oreille | 100.00% |
Previous: | Next: |
---|---|
n/a |
|
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Matthew Berger | Kalispel Tribe | Yes | Technical Contact | mberger@knrd.org | (509) 447-7244 |
Jason Connor | Kalispel Tribe | No | Interested Party | jconnor@knrd.org | (509) 447-7285 |
Ray Entz | Kalispel Tribe | Yes | Administrative Contact | rentz@knrd.org | (509) 445-1147 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Joe Maroney | Kalispel Tribe | Yes | Supervisor | jmaroney@knrd.org | (509) 447-7272 |
Jason Olson | Kalispel Tribe | No | Interested Party | jolson@knrd.org | (509) 447-7290 |
Donald Rose | Bonneville Power Administration | Yes | Env. Compliance Lead | dlrose@bpa.gov | (503) 230-3796 |
Jolene Seymour | Kalispel Tribe | No | Administrative Contact | jseymour@kalispeltribe.com | (509) 445-1147 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Virgil Watts III | Bonneville Power Administration | Yes | COR | vlwatts@bpa.gov | (503) 230-4625 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Obtain Required Permits | B: 165. Obtain Required Permits | 07/30/2013 | 07/30/2013 | |
Fulfill all administrative tasks with quality products and in a timely manner. | C: 119. Manage and fulfill all administrative tasks | 07/30/2013 | 07/30/2013 | |
Replace Cee Cee Ah Creek culvert site #1. | D: 184. Replace Cee Cee Ah Creek Culvert Site #1 | 11/01/2012 | 11/01/2012 | |
Replace Cee Cee Ah Culvert Site #2 | E: 184. Replace Cee Cee Ah Creek Culvert Site #2 | 11/01/2012 | 11/01/2012 | |
Replace Cee Cee Ah Culvert Site #3 | F: 184. Replace Cee Cee Ah Creek Culvert Site #3 | 11/01/2012 | 11/01/2012 | |
Attach Progress Report in Pisces | G: 132. Submit Progress Report for the period Aug 1,2012 to July 31,2013 | 07/31/2013 | 07/31/2013 | |
Project coordination among all stakeholders | H: 189. Coordination with other entities on restoration efforts | 07/30/2013 | 07/30/2013 | |
Investigate needs for conservation hatchery | I: 174. Investigate needs for conservation hatchery | 07/30/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Cutthroat Trout, Westslope (O. c. lewisi) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 05/01/2012 | ||||||
B | 165 | Obtain Required Permits | 08/15/2012 | ||||||
C | 119 | Manage and fulfill all administrative tasks | 08/15/2012 | ||||||
D | 184 | Replace Cee Cee Ah Creek Culvert Site #1 | 08/20/2012 | ||||||
E | 184 | Replace Cee Cee Ah Creek Culvert Site #2 | 08/20/2012 | ||||||
F | 184 | Replace Cee Cee Ah Creek Culvert Site #3 | 08/20/2012 | ||||||
G | 132 | Submit Progress Report for the period Aug 1,2012 to July 31,2013 | 08/15/2012 | ||||||
H | 189 | Coordination with other entities on restoration efforts | 08/15/2012 | ||||||
I | 174 | Investigate needs for conservation hatchery | 08/01/2012 |