Province | Subbasin | % |
---|---|---|
Intermountain | Pend Oreille | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Sep-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Matthew Berger | Kalispel Tribe | Yes | Technical Contact | mberger@knrd.org | (509) 447-7244 |
Jason Connor | Kalispel Tribe | Yes | Interested Party | jconnor@knrd.org | (509) 447-7285 |
Ray Entz | Kalispel Tribe | Yes | Supervisor | rentz@knrd.org | (509) 445-1147 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Joe Maroney | Kalispel Tribe | Yes | Supervisor | jmaroney@knrd.org | (509) 447-7272 |
Jason Olson | Kalispel Tribe | No | Contract Manager | jolson@knrd.org | (509) 447-7290 |
Jolene Seymour | Kalispel Tribe | Yes | Administrative Contact | jseymour@kalispeltribe.com | (509) 445-1147 |
Jennifer Snyder | Bonneville Power Administration | Yes | Env. Compliance Lead | jasnyder@bpa.gov | (503) 230-4187 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Virgil Watts III | Bonneville Power Administration | Yes | COR | vlwatts@bpa.gov | (503) 230-4625 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Obtain Required Permits | B: 165. Obtain Required Permits | 07/21/2014 | 07/21/2014 | |
Fulfill all administrative tasks with quality products and in a timely manner. | C: 119. Manage and fulfill all administrative tasks | 07/31/2014 | 07/31/2014 | |
Replace East Branch LeClerc Creek culverts sites No. 1520386 and 1520387 | D: 184. Replace East Branch LeClerc Creek culverts sites No. 1520386 and 1520387 | 07/31/2014 | ||
Replace West Branch LeClerc Creek Culvert site No. 1520372 | E: 184. Replace West Branch LeClerc Creek Culvert site No. 1520372 | 07/31/2014 | ||
Attach Progress Report in Pisces | F: 132. Submit Progress Report for the period Aug 1,2013 to July 31,2014 | 07/31/2014 | 07/31/2014 | |
Temperature model of the Priest River | G: 34. Temperature model of the Priest River | 04/24/2014 | 04/01/2014 | |
Project coordination among all stakeholders | H: 189. Coordination with other entities on restoration efforts | 07/31/2014 | 07/31/2014 | |
Install fence around Indian Creek Ponds | I: 40. Install fence around Indian Creek Ponds | 06/27/2014 |
Primary Focal Species | Work Statement Elements |
---|---|
Cutthroat Trout, Westslope (O. c. lewisi) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 08/01/2013 | ||||||
B | 165 | Obtain Required Permits | 08/01/2013 | ||||||
C | 119 | Manage and fulfill all administrative tasks | 08/01/2013 | ||||||
D | 184 | Replace East Branch LeClerc Creek culverts sites No. 1520386 and 1520387 | 05/05/2014 | ||||||
E | 184 | Replace West Branch LeClerc Creek Culvert site No. 1520372 | 05/05/2014 | ||||||
F | 132 | Submit Progress Report for the period Aug 1,2013 to July 31,2014 | 08/01/2013 | ||||||
G | 34 | Temperature model of the Priest River | 08/01/2013 | ||||||
H | 189 | Coordination with other entities on restoration efforts | 08/01/2013 | ||||||
I | 40 | Install fence around Indian Creek Ponds | 09/08/2014 |