Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Permits/Authorizations Acquired | A: 165. Obtain Permits and submit copies to BPA NEPA group | 09/30/2013 | 08/28/2013 | |
Maintain Springfield Fish Hatchery | B: 61. Maintenance of grounds and buildings at Springfield Hatchery | 09/30/2013 | 09/06/2013 | |
Provide documentation of construction activities | C: 100. Record and Document Construction Activities | 09/30/2013 | 09/05/2013 | |
Prepare Facility Maintenance Plan | D: 174. Prepare Written Building and Vehicle Maintenance Schedule | 01/21/2013 | 01/17/2013 | |
Attendance at program essential and SBSTOC meetings. | E: 189. Quarterly SBSTOC coordination meeting and program essential meetings. | 09/30/2013 | 09/10/2013 | |
Attach Progress Report in Pisces | F: 132. Submit Progress Report for the period (OCT 2011) to (SEP 2012) | 07/31/2013 | ||
Fulfill all administrative tasks with quality products and in a timely manner. | G: 119. Submit FY14 funding package to BPA | 09/30/2013 | 09/30/2013 | |
Test and Verify Water Supply Operational Procedures | I: 61. Verify Start-up, Shut down, and Operational Procedures | 09/30/2013 | 09/24/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Sockeye (O. nerka) - Snake River ESU (Endangered) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Obtain Permits and submit copies to BPA NEPA group | 10/01/2012 | ||||||
B | 61 | Maintenance of grounds and buildings at Springfield Hatchery | 06/13/2012 | ||||||
C | 100 | Record and Document Construction Activities | 10/01/2012 | ||||||
D | 174 | Prepare Written Building and Vehicle Maintenance Schedule | 10/01/2012 | ||||||
E | 189 | Quarterly SBSTOC coordination meeting and program essential meetings. | 10/01/2012 | ||||||
F | 132 | Submit Progress Report for the period (OCT 2011) to (SEP 2012) | 10/01/2012 | ||||||
G | 119 | Submit FY14 funding package to BPA | 10/01/2012 | ||||||
H | 185 | Periodic Status Reports for BPA | 10/01/2012 | ||||||
I | 61 | Verify Start-up, Shut down, and Operational Procedures | 06/13/2012 |