Contract 62932: 2007-402-00 EXP IDFG SPRINGFIELD HATCHERY SOCKEYE PRODUCTION
Project Number:
Title:
Snake River Sockeye Captive Propagation
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
62932
Contract Title:
2007-402-00 EXP IDFG SPRINGFIELD HATCHERY SOCKEYE PRODUCTION
Contract Continuation:
Previous: Next:
58452: 2007-402-00 EXP IDFG SPRINGFIELD HATCHERY SOCKEYE PRODUCTION
  • 66636: 2007-402-00 EXP IDFG SPRINGFIELD HATCHERY SOCKEYE PRODUCTION
Contract Status:
Closed
Contract Description:
2014 begins the first production cycle of sockeye smolts at the new Springfield Hatchery.   This contract includes procurement and installation of necessary equipment and related supplies for production of sockeye salmon smolts at Springfield Hatchery, as well as necessary supporting infrastructure such as hatchery dormitory, grounds, residences, shop, and administration wing.   Hatchery staff will update inventory as equipment is received.  Care and maintenance of new buildings, fish rearing units, associated/support tools and equipment and vehicles  will be a major work element during this contract period.

The existing construction contract (BPA Contract 57306 - Capital funded)  will be in force during the first three months of this contract.  Hatchery personnel will continue to photograph and document activities as needed. A Springfield Hatchery Operations and Maintenance manual is a deliverable under the construction contract, and hatchery personnel will attend and participate in development of this product.

Water delivery systems include fixed speed and variable speed pumps, head-boxes with aeration equipment, and chiller.  Testing of these water delivery systems to be an ongoing part of the project, and especially intensive during this contract period.   Sentinel fish are scheduled to be cultured during the previous contract period, and may still be cultured to observe system for signs of problems prior to receipt of sockeye salmon eggs.  On-site training covering all hatchery components will be conducted prior to contractor demobilization, and all hatchery staff will attend and participate in the training.  

Approximately 200,000-250,000 sockeye salmon are to be cultured during the first production year at Springfield Hatchery.   Eyed sockeye eggs are scheduled for receipt during December, 2013.  The resulting fry are to be incubated to the swim-up stage, then transferred to early rearing tanks until approximately 90-120 fpp.  The fingerlings will be marked and transferred to secondary rearing units for rearing to a project release size of 9-10  fpp.  Baseline data including survival, growth (monthly, growth units per temperature unit), feed conversion, etc.  will be collected, reported monthly, and used to set-up future brood year's projections.

Hatchery personnel will attend and participate in Stanley Basis Sockeye Technical Oversight Committee (SBSTOC) and program specific meetings as  program needs necessitate and time allows.
Account Type(s):
Expense
Contract Start Date:
10/01/2013
Contract End Date:
09/30/2014
Current Contract Value:
$769,280
Expenditures:
$769,280

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Permits/Authorizations Acquired A: 165. Obtain Permits and submit copies to BPA NEPA group 11/29/2013 10/31/2013
Construction Management Complete B: 100. Record and Document Construction Activities 12/31/2013 12/31/2013
Maintain Springfield Fish Hatchery C: 61. Maintenance of grounds and buildings at Springfield Hatchery 09/30/2014 09/30/2014
Procure needed equipment and supplies for sockeye production at Springfield D: 61. Procurement of Hatchery Equipment and Supplies 09/30/2014 09/30/2014
Test and Verify Water Supply Operational Procedures E: 61. Verify Start-up, Shut down, and Operational Procedures 05/30/2014 06/27/2014
Rear BY 13 juvenile sockeye salmon at Springfield FH F: 176. Rear BY 2013 Springfield sockeye production group 09/30/2014 09/30/2014
Mark BYR 2013 Springfield sockeye production group G: 158. Mark BY 2013 Springfield sockeye production group 07/31/2014 06/26/2014
2014 Salmon River AOP H: 174. Salmon River Annual Operating Plan 06/30/2014 06/02/2014
Attendance at program essential and SBSTOC meetings. I: 189. Quarterly SBSTOC coordination meeting and program essential meetings. 09/30/2014 07/24/2014
Attach FY12 Progress Report in Pisces J: 132. Submit Progress Report for the period (OCT 2011) to (SEP 2012) 10/01/2013 09/25/2013
Attach FY13 Progress Report in Pisces K: 132. Submit Progress Report for the period (OCT 2012) to (SEP 2013) 04/10/2014 04/09/2014
All administrative tasks fulfilled with timely quality products L: 119. Submit FY15 funding package to BPA 09/30/2014 09/30/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 3 instances of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Permits and submit copies to BPA NEPA group 10/01/2013
B 100 Record and Document Construction Activities 10/01/2013
C 61 Maintenance of grounds and buildings at Springfield Hatchery 08/23/2013
D 61 Procurement of Hatchery Equipment and Supplies 08/23/2013
E 61 Verify Start-up, Shut down, and Operational Procedures 08/23/2013
F 176 Rear BY 2013 Springfield sockeye production group 09/27/2013
G 158 Mark BY 2013 Springfield sockeye production group 09/27/2013
H 174 Salmon River Annual Operating Plan 08/23/2013
I 189 Quarterly SBSTOC coordination meeting and program essential meetings. 10/01/2013
J 132 Submit Progress Report for the period (OCT 2011) to (SEP 2012) 10/01/2013
K 132 Submit Progress Report for the period (OCT 2012) to (SEP 2013) 10/01/2013
L 119 Submit FY15 funding package to BPA 10/01/2013
M 185 Periodic Status Reports for BPA 10/01/2013