Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Permits/Authorizations Acquired | A: 165. Obtain Permits and submit copies to BPA NEPA group | 09/30/2015 | 09/29/2015 | |
Snake River sockeye RPA/BiOp data submission to IDFG project leader | B: 202. Snake River sockeye RPA/BiOp Data | 02/28/2015 | 01/19/2015 | |
Maintain Springfield Fish Hatchery | E: 61. Maintenance of grounds and buildings at Springfield Hatchery | 09/30/2015 | 09/29/2015 | |
Procure needed equipment and supplies for sockeye production at Springfield | F: 61. Procurement of Hatchery Equipment and Supplies | 09/30/2015 | 09/29/2015 | |
Rear BY 13 juvenile sockeye salmon at Springfield FH | G: 176. Rear BY 2013 Springfield sockeye production group | 09/30/2015 | 05/08/2015 | |
PIT tag BY 2013 Springfield sockeye production group with 50K PIT tags | H: 158. Tag BY 2013 Springfield sockeye production group | 04/17/2015 | 01/22/2015 | |
Mark BYR 2014 Springfield sockeye production group | I: 158. Tag BY 2014 Springfield sockeye production group | 07/30/2015 | 07/03/2015 | |
Rear BY 2014 juvenile sockeye salmon at Springfield FH | J: 176. Rear BY 2014 Springfield sockeye production group | 09/30/2015 | 09/29/2015 | |
2015 Salmon River AOP | K: 174. Salmon River Annual Operating Plan | 04/30/2015 | 03/27/2015 | |
Attendance at program essential and SBSTOC meetings. | L: 189. Quarterly SBSTOC coordination meeting and program essential meetings. | 09/30/2015 | 08/25/2015 | |
Attach FY14 Progress Report in Pisces | M: 132. Submit Progress Report for the period (OCT 2013) to (SEP 2014) | 12/31/2014 | 12/31/2014 | |
All administrative tasks fulfilled with timely quality products | N: 119. Submit FY16 funding package to BPA | 09/30/2015 | 09/30/2015 |
Primary Focal Species | Work Statement Elements |
---|---|
Sockeye (O. nerka) - Snake River ESU (Endangered) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Obtain Permits and submit copies to BPA NEPA group | 10/01/2014 | ||||||
B | 202 | Snake River sockeye RPA/BiOp Data | |||||||
C | 61 | Install chilled water supply temperature buffering system at Eagle Hatchery | 10/15/2014 | ||||||
D | 34 | Minor modification to artesian well | |||||||
E | 61 | Maintenance of grounds and buildings at Springfield Hatchery | 10/01/2014 | ||||||
F | 61 | Procurement of Hatchery Equipment and Supplies | 10/01/2014 | ||||||
G | 176 | Rear BY 2013 Springfield sockeye production group | 10/01/2014 | ||||||
H | 158 | Tag BY 2013 Springfield sockeye production group | 10/01/2014 | ||||||
I | 158 | Tag BY 2014 Springfield sockeye production group | 10/01/2014 | ||||||
J | 176 | Rear BY 2014 Springfield sockeye production group | 10/01/2014 | ||||||
K | 174 | Salmon River Annual Operating Plan | 10/01/2014 | ||||||
L | 189 | Quarterly SBSTOC coordination meeting and program essential meetings. | 10/01/2014 | ||||||
M | 132 | Submit Progress Report for the period (OCT 2013) to (SEP 2014) | 10/01/2014 | ||||||
N | 119 | Submit FY16 funding package to BPA | 10/01/2014 | ||||||
O | 185 | Periodic Status Reports for BPA | 10/01/2014 |