Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Provide EC documentation | A: 165. Provide EC documentation | 12/31/2013 | 12/31/2013 | |
New side channel on Lemhi River | B: 30. IDFG: Snyder Lemhi River sc: create new side channel | 12/20/2013 | 09/13/2013 | |
Increased habitat complexity in the Lemhi River side channel | C: 29. IDFG: Snyder Lemhi River sc: add structures to increase habitat complexity | 12/20/2013 | 08/30/2013 | |
completed riparian fence | D: 40. IDFG: Snyder Lemhi River sc: Install fence along new side channel | 12/31/2013 | 09/27/2013 | |
Revegetate all disturbed areas both riparian and upland | E: 47. IDFG: Snyder Lemhi River sc: revegetate disturbed areas with native vegetation | 12/31/2013 | 11/29/2013 | |
Upper Hawley Water Rights Point-of Use-Transfer: Install Irrigation Pipeline | F: 149. Upper Hawley Water Rights Point-of Use-Transfer: Install pipeline | 12/31/2013 | ||
Side Channel Engineering Plans | H: 175. Lemhi River Side Channel Project at Mabey Lane: Produce design or specifications | 08/30/2013 | 06/06/2013 | |
Create Side Channel and Reconnect Floodplain | I: 30. Lemhi River Side Channel Project at Mabey Lane: Create new channel | 11/29/2013 | ||
Install Jack Fence | J: 40. Lemhi River Side Channel Project at Mabey Lane: Install Fence | 11/29/2013 | ||
Riparian Vegetation Plantings on Side Channel | K: 47. Lemhi River Side Channel Project at Mabey Lane: Plant vegetation | 11/29/2013 | ||
Fulfill all administrative tasks with quality products and in a timely manner. | L: 119. Manage and Administer Project | 12/31/2013 | 12/31/2013 | |
Complete road paving and add guard rails | O: 38. Canyon Creek Bridge: Complete road paving and add guard rails | 06/30/2013 | 05/30/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Provide EC documentation | 01/01/2013 | ||||||
B | 30 | IDFG: Snyder Lemhi River sc: create new side channel | 06/20/2013 | ||||||
C | 29 | IDFG: Snyder Lemhi River sc: add structures to increase habitat complexity | 06/20/2013 | ||||||
D | 40 | IDFG: Snyder Lemhi River sc: Install fence along new side channel | 06/20/2013 | ||||||
E | 47 | IDFG: Snyder Lemhi River sc: revegetate disturbed areas with native vegetation | 06/20/2013 | ||||||
F | 149 | Upper Hawley Water Rights Point-of Use-Transfer: Install pipeline | |||||||
G | 150 | Carmen Creek SCC3 Flow Enhancement Project: Install Sprinkler (CANCELLED) | |||||||
H | 175 | Lemhi River Side Channel Project at Mabey Lane: Produce design or specifications | 01/01/2013 | ||||||
I | 30 | Lemhi River Side Channel Project at Mabey Lane: Create new channel | |||||||
J | 40 | Lemhi River Side Channel Project at Mabey Lane: Install Fence | 01/01/2013 | ||||||
K | 47 | Lemhi River Side Channel Project at Mabey Lane: Plant vegetation | |||||||
L | 119 | Manage and Administer Project | 01/01/2013 | ||||||
M | 185 | Periodic Status Reports for BPA | 01/01/2013 | ||||||
N | 132 | Submit Progress Report for the period (1/1/13) to (12/31/13) | 01/01/2013 | ||||||
O | 38 | Canyon Creek Bridge: Complete road paving and add guard rails | 01/01/2013 |