Obtain or complete Environmental consultation documents and provide to BPA |
A: 165. Produce EC documents on identified projects |
|
08/31/2015 |
08/31/2015 |
Produce Design and/or Specifications |
B: 175. Produce Design and/or Specifications |
|
07/31/2015 |
07/31/2015 |
Install Pipeline and infrastructure to allow the closure of P-15 Diversion and water conservation. |
C: 149. Install pipeline near Furey Lane from the Cross Ditch |
|
08/28/2015 |
08/28/2015 |
Remove and replace P-16 Fish Barrier on Pahsimeroi with fish friendly structure and pipeline. |
D: 84. Replace Furey Push Up Dam with Fish Passable Structure at Furey -P-16 |
|
08/28/2015 |
08/28/2015 |
Install pipeline to provide water conservation on Pahsimeroi |
E: 149. Furey Lane Pipeline - P-16 |
|
09/25/2015 |
09/25/2015 |
Install irrigation systems to replace current flood irrigation to water conservation for P-17 |
F: 150. Install Sprinkler Irrigation to Replace Flood on P-16 properties from Furey P-16 |
|
09/25/2015 |
09/25/2015 |
Provide materials for approximately 3750 feet of Riparian Jack Post and Pole Fence |
G: 40. Install Jack Fence on Easement Property on Furey Lane |
|
08/28/2015 |
12/26/2014 |
Remove partial barrier on Spring Creek/Pahsimeroi near McCoy Lane |
H: 85. Remove Fish Barrier near McCoy Lane #1 |
|
09/25/2015 |
|
Install Bridge or/bottomless arch culvert to replace undersized existing culvert. |
I: 184. Install bridges near McCoy Lane #1 |
|
09/25/2015 |
|
Remove fish barrier culvert on McCoy Lane on the County Road |
J: 85. Remove Fish Barrier near McCoy Lane #2 |
|
09/25/2015 |
|
Install Bridge/bottomless culvert on McCoy Lane on the County Road |
K: 184. Install bridges near McCoy Lane #2 |
|
09/25/2015 |
|
Install stock-water wells, pipeline & stock tanks to replace in-stream stock water from Pahsimeroi |
L: 34. Install off Stream Stockwater at McCoy Lane |
|
09/25/2015 |
|
Install pipeline and infrastructure to allow for the removal of P-13 diversion, ditch & fish b |
M: 149. Install pipeline to provide infrastructure to remove P-13 Diversion and consolidate into P-12 |
|
09/25/2015 |
06/01/2015 |
Remove P-13 Fish Barrier on Pahsimeroi |
N: 85. Remove P-13 Fish Barrier on Pahsimeroi |
|
09/04/2015 |
09/01/2015 |
Install pipeline and infrastructure to allow for the removal of P-13 diversion, ditch & fish barrier |
O: 149. Install pipeline to provide infrastructure to remove P-13 Diversion and consolidate in new POD |
|
08/28/2015 |
08/03/2015 |
Install stock-water wells, pipeline & stock tanks to replace in-stream stock water from Pahsimeroi. |
P: 34. Install off Stream Stockwater at P13 Project |
|
05/29/2015 |
05/29/2015 |
Remove partial barrier on Sulphur Creek |
Q: 85. Remove Fish Barrier on Sulphur Creek |
|
09/25/2015 |
08/15/2015 |
Install bottomless arch culvert to replace culvert in lower Sulphur Creek |
R: 184. Remove Sulphur Creek Culvert and Replace with Fish Passable Structure |
|
09/25/2015 |
09/25/2015 |
Install stock-water wells, pipeline & stock tanks to replace in-stream stock water from Hamilton |
S: 34. Install Off Stream Stockwater at P16 to replace Hamilton/P16/Pahsimeroi Stockwater |
|
09/25/2015 |
|
All administrative tasks fulfilled with timely quality products |
T: 119. Manage and administer projects within this contract for FY 13/14 |
|
09/25/2015 |
09/25/2015 |
Attach Pahsimeroi Contract 2008-603 Progress Report in Pisces |
V: 132. Submit Progress Report for the period May 1, 2013 thru September 30, 2014 |
|
11/30/2014 |
12/08/2014 |