Contract 66757: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
Project Number:
Title:
Pahsimeroi River Habitat
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
66757
Contract Title:
2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
Contract Continuation:
Previous: Next:
57289: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-CUSTER
  • 70409: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
Contract Status:
Closed
Contract Description:
Work proposed in this statement of work will allow completion of three projects that are ongoing from contract # 57289. Change in ownership of several properties involved in the project for P-16 slowed progress. However, the benefits were increased by then change in ownership. In addition P-16 diversion and sections the pipeline is on the BLM land. The Environmental Assessment development has been much slower than anticipated and was not completed prior to the close of previous contract. All design work is complete. All consultation is complete on the private ground. This pipeline is sized to 8 cfs of the total 21 cfs allowed at this point of diversion with a 13 cfs savings that will remain in-stream in the Pahsimeroi. An additional 11.94 cfs from Big Creek will no longer be diverted and will remain in stream in Big Creek.

P-13 is an un-screen diversion in the Pahsimeroi that is currently a fish barrier. It also intercepts Sulphur Creek, Big Springs Creek and fully de-waters the historic channel of the Pahsimeroi. By working with the three landowners within this system to find alternative irrigation water source this barrier will be removed and several other tributaries reconnected including Sulphur. Delays in gaining landowner approvals and completing the cultural surveys delayed this project. All consultation is complete for the irrigation components of the project. The only remaining item to complete consultation on will be the physical removal of the P-13 ditch and structure and to reconnect the historic channel of Pahsimeroi and Sulphur Creek. Increased in stream flows for this project will be approximately 11 cfs. In addition two reconnects will be accomplished when the P-13 Ditch is closed and all diversions will now have criteria fish screens from the mouth of the Pahsimeroi to Furey Lane.

The next diversion upstream from P1-3 that was to be addressed was P-14 which was recently retired by the owner as a part of the Sulphur Creek project completed in last year’s contract.  P15 will also be closed as part of the Cross Ditch project that will also screen the last unscreened diversion on Patterson/Big Springs Creek.  A new screen will be installed by IDFG. The district will assist in the installation of a sprinkler irrigation system and pipeline that will leave an additional 5 cfs in Patterson/Big Springs Creek and 4.4 cfs additional flows in the Pahsimeroi.  The final step is the replacement of the P-16 diversion and the installation of a fish screen. By modifying existing irrigation practices, providing pipe to transport the flows for irrigation the passage barriers can be removed and replaced with a fish friendly diversion. This will also increase in-stream flows from 10 to 15 cfs in the mid to upper Pahsimeroi. All designs have been completed including landowner approvals. The only remaining component is to complete the easement with the Bureau of Land Management and the 404 Permit for the diversion and the pipe on BLM land.  This is currently an unscreened diversion and will be screened with a criteria screen in cooperation with the IDFG Screen Shop in a separate contract.

This SOW also includes three culvert removals that are serving as passage barriers. The Sulphur Creek Culvert removal will be the final component to address the full reach of Sulphur Creek. The remaining two culvert removals will address passage barriers near McCoy Lane. Also near the upper McCoy Lane an off-site stock water system will be developed to address a feedlot along the same stream.
Account Type(s):
Expense
Contract Start Date:
09/26/2014
Contract End Date:
09/25/2015
Current Contract Value:
$1,092,038
Expenditures:
$1,092,038

* Expenditures data includes accruals and are based on data through 31-Dec-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain or complete Environmental consultation documents and provide to BPA A: 165. Produce EC documents on identified projects 08/31/2015 08/31/2015
Produce Design and/or Specifications B: 175. Produce Design and/or Specifications 07/31/2015 07/31/2015
Install Pipeline and infrastructure to allow the closure of P-15 Diversion and water conservation. C: 149. Install pipeline near Furey Lane from the Cross Ditch 08/28/2015 08/28/2015
Remove and replace P-16 Fish Barrier on Pahsimeroi with fish friendly structure and pipeline. D: 84. Replace Furey Push Up Dam with Fish Passable Structure at Furey -P-16 08/28/2015 08/28/2015
Install pipeline to provide water conservation on Pahsimeroi E: 149. Furey Lane Pipeline - P-16 09/25/2015 09/25/2015
Install irrigation systems to replace current flood irrigation to water conservation for P-17 F: 150. Install Sprinkler Irrigation to Replace Flood on P-16 properties from Furey P-16 09/25/2015 09/25/2015
Provide materials for approximately 3750 feet of Riparian Jack Post and Pole Fence G: 40. Install Jack Fence on Easement Property on Furey Lane 08/28/2015 12/26/2014
Remove partial barrier on Spring Creek/Pahsimeroi near McCoy Lane H: 85. Remove Fish Barrier near McCoy Lane #1 09/25/2015
Install Bridge or/bottomless arch culvert to replace undersized existing culvert. I: 184. Install bridges near McCoy Lane #1 09/25/2015
Remove fish barrier culvert on McCoy Lane on the County Road J: 85. Remove Fish Barrier near McCoy Lane #2 09/25/2015
Install Bridge/bottomless culvert on McCoy Lane on the County Road K: 184. Install bridges near McCoy Lane #2 09/25/2015
Install stock-water wells, pipeline & stock tanks to replace in-stream stock water from Pahsimeroi L: 34. Install off Stream Stockwater at McCoy Lane 09/25/2015
Install pipeline and infrastructure to allow for the removal of P-13 diversion, ditch & fish b M: 149. Install pipeline to provide infrastructure to remove P-13 Diversion and consolidate into P-12 09/25/2015 06/01/2015
Remove P-13 Fish Barrier on Pahsimeroi N: 85. Remove P-13 Fish Barrier on Pahsimeroi 09/04/2015 09/01/2015
Install pipeline and infrastructure to allow for the removal of P-13 diversion, ditch & fish barrier O: 149. Install pipeline to provide infrastructure to remove P-13 Diversion and consolidate in new POD 08/28/2015 08/03/2015
Install stock-water wells, pipeline & stock tanks to replace in-stream stock water from Pahsimeroi. P: 34. Install off Stream Stockwater at P13 Project 05/29/2015 05/29/2015
Remove partial barrier on Sulphur Creek Q: 85. Remove Fish Barrier on Sulphur Creek 09/25/2015 08/15/2015
Install bottomless arch culvert to replace culvert in lower Sulphur Creek R: 184. Remove Sulphur Creek Culvert and Replace with Fish Passable Structure 09/25/2015 09/25/2015
Install stock-water wells, pipeline & stock tanks to replace in-stream stock water from Hamilton S: 34. Install Off Stream Stockwater at P16 to replace Hamilton/P16/Pahsimeroi Stockwater 09/25/2015
All administrative tasks fulfilled with timely quality products T: 119. Manage and administer projects within this contract for FY 13/14 09/25/2015 09/25/2015
Attach Pahsimeroi Contract 2008-603 Progress Report in Pisces V: 132. Submit Progress Report for the period May 1, 2013 thru September 30, 2014 11/30/2014 12/08/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 3 instances of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 84 Remove/Install Diversion
  • 4 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 4 instances of WE 149 Install Pipeline
  • 1 instance of WE 150 Install Sprinkler
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 3 instances of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 84 Remove/Install Diversion
  • 4 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 4 instances of WE 149 Install Pipeline
  • 1 instance of WE 150 Install Sprinkler

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce EC documents on identified projects 09/26/2014
B 175 Produce Design and/or Specifications 09/26/2014
C 149 Install pipeline near Furey Lane from the Cross Ditch 04/20/2015
D 84 Replace Furey Push Up Dam with Fish Passable Structure at Furey -P-16 06/03/2015
E 149 Furey Lane Pipeline - P-16 06/18/2015
F 150 Install Sprinkler Irrigation to Replace Flood on P-16 properties from Furey P-16 06/18/2015
G 40 Install Jack Fence on Easement Property on Furey Lane 09/26/2014
H 85 Remove Fish Barrier near McCoy Lane #1 09/21/2015
I 184 Install bridges near McCoy Lane #1 09/21/2015
J 85 Remove Fish Barrier near McCoy Lane #2 09/21/2015
K 184 Install bridges near McCoy Lane #2 09/21/2015
L 34 Install off Stream Stockwater at McCoy Lane
M 149 Install pipeline to provide infrastructure to remove P-13 Diversion and consolidate into P-12 09/26/2014
N 85 Remove P-13 Fish Barrier on Pahsimeroi 06/18/2015
O 149 Install pipeline to provide infrastructure to remove P-13 Diversion and consolidate in new POD 08/15/2015
P 34 Install off Stream Stockwater at P13 Project 09/26/2014
Q 85 Remove Fish Barrier on Sulphur Creek 09/09/2015
R 184 Remove Sulphur Creek Culvert and Replace with Fish Passable Structure 09/09/2015
S 34 Install Off Stream Stockwater at P16 to replace Hamilton/P16/Pahsimeroi Stockwater 06/03/2015
T 119 Manage and administer projects within this contract for FY 13/14 09/26/2014
U 185 Periodic Status Reports for BPA 09/26/2014
V 132 Submit Progress Report for the period May 1, 2013 thru September 30, 2014 09/26/2014