All administrative tasks fulfilled with timely quality products |
B: 119. Manage and administer projects within this contract for FY 15/16 |
|
09/25/2016 |
09/25/2016 |
Upload prioritized project list to Pisces |
C: 114. Identify and Select projects based on partnership coordination with Pahsimeroi Group |
|
07/01/2016 |
07/05/2016 |
Obtain or complete Environmental consultation documents and provide to BPA |
D: 165. Produce EC documents on identified projects |
|
09/25/2016 |
09/25/2016 |
Produce Design and/or Specifications |
E: 175. Produce Design and/or Specifications for P-17 |
|
09/23/2016 |
09/23/2016 |
Progress Report has been published |
F: 132. Submit Progress Report for the period September 26, 2014 thru September 25, 2015 |
|
02/19/2016 |
02/05/2016 |
Remove partial barrier on Spring Creek/Pahsimeroi near McCoy Lane |
G: 85. Remove Fish Barrier at Lone Pine near McCoy Lane |
|
03/31/2016 |
10/27/2015 |
Install Bridge to replace undersized existing culvert. |
H: 184. Install bridge at Lone Pine near McCoy Lane |
|
03/31/2016 |
10/30/2015 |
Remove fish barrier culvert on McCoy Lane on the County Road |
I: 85. Remove Fish Barrier near McCoy Lane #2 |
|
03/31/2016 |
10/30/2015 |
Install Bridge McCoy Lane on the County Road |
J: 184. Install bridge near McCoy Lane #2 |
|
03/31/2016 |
11/30/2015 |
Install stock-water pipeline & stock tanks to replace in-stream water from Hamilton Ditch |
K: 34. Install Off Stream Stockwater at P16 to replace Hamilton/P16/Pahsimeroi Stockwater |
|
09/25/2016 |
09/25/2016 |
Install remaining sprinkler irrigation for Furey Lane Project |
L: 203. Install remaining sprinkler irrigation for Furey Lane Project |
|
09/01/2016 |
09/23/2016 |
Install Riparian Post and Wire Fence to meet wild life specifications. |
M: 40. Install riparian fence near Furey Lane diversion and fish screen |
|
03/31/2016 |
11/30/2015 |
Install stock-water, pipeline & stock tanks to replace in-stream watering from Pahsimeroi/Goldberg |
N: 34. Install off Stream Stockwater at McCoy Lane |
|
08/31/2016 |
09/25/2016 |
Install berm/erosion control barrier on Lone Pine to address confined cattle area |
O: 55. Install erosion control barrier on Lone Pine to address confined cattle area. |
|
09/23/2016 |
|
Install Post and Pole Fence along sediment barrier on Lone Pine to exclude livestock |
P: 40. Install riparian fence along sediment barrier on Lone Pine |
|
09/23/2016 |
09/23/2016 |
Remove Culvert at Flying Joe |
Q: 85. Remove Flying Joe Culvert |
|
09/23/2016 |
|
Install Flying Joe Bridge |
R: 184. Install Bridge to Replace Flying Joe Culvert |
|
09/23/2016 |
|
Remove Culvert on Muddy Springs (Phase I) |
S: 85. Remove Culvert on Muddy Springs (Phase I) |
|
09/23/2016 |
|
Breach P-15 irrigation diversion from the Pahsimeroi |
T: 85. Remove and Rehab Closed P-15 Diversion |
|
09/23/2016 |
09/16/2016 |
Install Bridge at the DR Ranch in the Upper Pahsimeroi |
U: 184. Install Bridge at DR Ranch in Upper Pahsimeroi |
|
09/23/2016 |
09/19/2016 |
Purchase Pipe for the P-17 pipeline project |
V: 203. Purchase Pipe for P-17 Water Conservation Project |
|
09/23/2016 |
|
Provide designs and specifications for 2 bridges in the Upper Pahsimeroi |
W: 175. Contract with Private Engineer to Produce Designs and Specs for two Bridges |
|
08/12/2016 |
05/27/2016 |
Install Fence on the DR Ranch to protect the Pahsimeroi |
X: 40. Install Fence on DR Ranch to protect the Pahsimeroi |
|
09/23/2016 |
|
Complete maintenance on approximately 6000 feet of existing Jack Post and Pole Riparian Fence |
Y: 186. Monitor, maintain and extend fencing contracts on existing BPA investments |
|
09/23/2016 |
09/23/2016 |