Complete all required EC and obtain permits prior to implementation of project |
B: 165. Produce Environmental Compliance Documentation |
|
12/31/2016 |
12/31/2016 |
All administrative tasks fulfilled with timely quality products |
C: 119. Manage and Administer Project |
|
12/31/2016 |
12/31/2016 |
Completed Annual Report |
D: 132. Submit Progress Report for the period (Jan 2015) to (Dec 2015) |
|
04/29/2016 |
05/23/2016 |
Bohannon Creek Diversion #3 Final Design |
E: 175. IDFG: Final Design for Bohannon Creek Diversion #3 Removal |
|
12/31/2016 |
12/15/2016 |
Stokes Lower Lemhi Project Final Design |
F: 175. IDFG: Final Design for Stokes Lower Lemhi Project Design |
|
12/31/2016 |
|
Highway 29 Culvert Replacement Final Design |
G: 175. IDFG: Final Design for Highway 29 Culvert Replacement Project |
|
12/31/2016 |
|
Final Design of the Thor Lemhi Rivers Channel Project |
H: 175. IDFG: Final Design for Thor Lemhi River Channels Project |
|
07/31/2016 |
08/07/2016 |
Construction Management Complete |
I: 100. IDFG: Provide construction oversight and management of Thor Lemhi River Channels Project |
|
11/30/2016 |
08/31/2016 |
Thor Large Wood Structures Installed |
K: 29. IDFG: Install Large Woody Structures in Thor Lemhi River Channels Project side channel |
|
12/31/2016 |
08/31/2016 |
Thor Project Revegetated |
L: 47. IDFG: Revegetate disturbed areas in Thor Lemhi River Channels Project |
|
12/15/2016 |
10/31/2016 |
Revegetated Lower Lemhi Rehabilitation Project Sites |
M: 47. IDFG: Revegetate Lower Lemhi Rehabilitation Project Subreach 2 and 3 |
|
12/15/2016 |
|
Lower Lemhi Rehabilitation Subreach #3 Final Design |
N: 175. IDFG: Provide final designs for Subreach #3 of the Lower Lemhi Rehabilitation Project |
|
12/31/2016 |
09/01/2016 |
Construction Management Complete |
O: 100. IDFG: Provide Construction oversight and management of Subreach #3 of the Lower Lemhi Rehab Project |
|
12/15/2016 |
|
Large Woody Structures Installed in Subreach #3 |
P: 29. IDFG: Install Large Woody Structures in Subreach #3 of the Lower Lemhi Rehabilitation Project |
|
12/31/2016 |
|
Completed channel construction |
Q: 30. IDFG: Construct side channel in Subreach #3 of the Lower Lemhi Rehabilitation Project |
|
12/15/2016 |
|
Installation of a pre-engineered modular steel bridge on the Agency Creek county road. |
R: 184. Lemhi SWCD: Agency Creek Culvert Replacement Access Project |
|
12/31/2016 |
09/06/2016 |
Furnish and install 3 phase power to irrigation pump |
S: 203. Lemhi SWCD: Lower Pratt Creek Access & Flow Enhancement: 3 Phase Power |
|
12/31/2016 |
11/30/2016 |
Manage vegetation through noxious weed treatments |
T: 199. Lemhi SWCD: Lemhi Tech Svcs: Noxious Weed Treatments |
|
12/31/2016 |
11/30/2016 |
Rehabilitate project sites through hydroseeding |
U: 47. Lemhi SWCD: Lemhi Tech Svcs: Rehabilitate Project Sites |
|
06/15/2016 |
05/02/2016 |
Produce engineering designs for Lemhi conservation projects. |
V: 175. Lemhi SWCD: Lemhi Tech Svcs: Produce engineering designs for Lemhi conservation actions |
|
12/31/2016 |
12/31/2016 |
Purchase pump |
W: 203. Lemhi SWCD: Canyon Creek Access & Flow Enhancement (CC-03): Pump Purchase |
|
12/31/2016 |
12/30/2016 |
Purchase pump |
X: 203. Lemhi SWCD: Hawley Creek Access & Flow Enhancement (LHaC-01): Pump Purchase |
|
12/31/2016 |
12/30/2016 |
Purchase irrigation appurtenances |
Y: 203. Lemhi SWCD: Hawley Creek Access & Flow Enhancement (LHaC-02): Purchase Irrigation Appurtenances |
|
12/31/2016 |
12/30/2016 |
Produce engineering designs for the Upper Lemhi bank & Riparian Restoration Project |
Z: 175. LRLT: Produce engineering designs for Upper Lemhi bank & Riparian Restoration |
|
10/06/2016 |
12/31/2016 |
NEPA and ESA compliance, cultural survey and report |
AA: 165. LRLT: Upper Lemhi Bank & Riparian Restoration NEPA and ESA Compliance |
|
11/01/2016 |
09/30/2016 |
Enhance and restore riparian vegetation on the Upper Lemhi easement. |
AB: 47. LRLT: Upper Lemhi Bank & Riparian Restoration Plant Vegetation |
|
11/30/2016 |
11/30/2016 |
Manage vegetation on the Upper Lemhi Easement through noxious weed treatments |
AC: 199. LRLT: Upper Lemhi Noxious Weed Treatments |
|
11/30/2016 |
|
Install riparian fence |
AD: 40. LRLT: Upper Lemhi Riparian Fence |
|
12/01/2016 |
12/31/2016 |
Develop a project plan for the Big Timber Project |
AE: 174. LRLT: Big Timber Planning and Development |
|
12/31/2016 |
12/31/2016 |
Data analysis - in progress |
AF: 162. RMRS: Lemhi Hydrologic Modeling Using LiDAR Data |
|
12/31/2016 |
12/31/2016 |
Purchase pipe and a pump station |
AG: 203. IDFG: Purchase Irrigation Pipe and Pump Station for Bohannon Cr #3 |
|
12/31/2016 |
|
Produce 50% design |
AH: 175. TU: Wimpey Creek Restoration - Produce 50% Design |
|
12/31/2016 |
12/31/2016 |
Produce final design for revegetation and fencing of the Little Springs project site |
AI: 175. TU: Little Springs Revegetation and Fencing - Produce Final Design |
|
12/31/2016 |
10/05/2016 |
Produce preliminary designs |
AJ: 175. TU: Little Sawmill Creek Restoration - Produce Preliminary Design |
|
12/31/2016 |
11/15/2016 |
Produce conceptual design |
AK: 175. TU: Lower Haynes - Produce Conceptual Design |
|
12/31/2016 |
12/31/2016 |
Produce final design for Eighteenmile Creek restoration |
AL: 175. Lemhi SWCD: Eighteenmile Creek Restoration - Produce Final Design |
|
12/31/2016 |
|
Produce final design |
AM: 175. LRLT: Big Timber 2 Diversion Removal & Revegetation - Produce Final Design |
|
12/31/2016 |
12/31/2016 |
Produce preliminary design |
AN: 175. LRLT: L-63 Siphon Removal - Produce Preliminary Design |
|
12/31/2016 |
12/31/2016 |
Replace fence at staging area |
AO: 40. Lemhi SWCD: Agency Creek Culvert Replacement Access Project: Fence |
|
12/01/2016 |
|
Purchase of a pre-engineered modular steel bridge |
AP: 184. Lemhi SWCD: Sandy Creek Culvert Replacement: Bridge purchase |
|
12/31/2016 |
12/31/2016 |
Purchase a pump station |
AQ: 203. Lemhi SWCD: Bohannon Cr #3: Purchase Pump Station |
|
12/31/2016 |
12/31/2016 |
purchase of irrigation infrastructure |
AR: 203. Lemhi SWCD: Middle Pratt Creek Access Improvement Project (Snook): Irrigation purchase |
|
12/31/2016 |
12/31/2016 |
Furnish irrigation infrastructure. |
AS: 203. Lemhi SWCD: Upper Pratt Creek Access and Flow Enhancement Project (Moulton): Irrigation purchase |
|
12/31/2016 |
12/31/2016 |