Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 67754: 2010-072-00 EXP LEMHI RIVER RESTORATION
Project Number:
Title:
Upper Salmon Basin Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
67754
Contract Title:
2010-072-00 EXP LEMHI RIVER RESTORATION
Contract Continuation:
Previous: Next:
63697: 2010-072-00 EXP LEMHI RIVER RESTORATION
  • 71307: 2010-072-00 EXP LEMHI RIVER RESTORATION
Contract Status:
Closed
Contract Description:
The Lemhi River Restoration Project (2010-072-00) seeks to implement habitat actions  to protect in-stream and riparian habitat, improve stream flow in the Lemhi River, and assist in reconnecting tributary streams to the Lemhi River to benefit all life stages of Snake River spring/summer-run Chinook and Snake River steelhead.

This contract covers calendar year 2015 actions by Idaho Department of Fish and Game (IDFG), Lemhi Soil and Water Conservation District (Lemhi SWCD), Centered Consulting International (CCI), CH2M Hill, Trout Unlimited (TU), and Lemhi Regional Land Trust (LRLT).

IDFG projects include design work for the Bohannon Creek #3 diversion, Highway 29 culvert replacement, Stokes Lower Lemhi River, Hayden Creek side channel, Bohannon Creek Upper culvert replacement, and Lower Lemhi, Eagle Valley Ranch projects.  Other work by IDFG includes identification and development work on new projects, replacing the Upper Bohannon Creek culvert with a prefabricated bridge, and revegetation at the Amonson Upper Lemhi side channel, Snyder project, and Little Springs Creek project.

Lemhi SWCD will complete design work on the Agency Creek County Road Culvert Removal.  They will also complete the Pratt Creek Culvert Replacement, Lower Bohannon Creek Private Culvert Replacement, Eighteenmile Creek Railroad Grade Culvert to Bridge Replacement, and Hawley-Eighteenmile Creeks Intercept Irrigation, as well as some noxious weed treatments.  Lemhi SWCD will also purchase a hydroseeder in order to revegetate the Upper Hawley Creek Water Rights Point of Use Transfer project site, and install a water conservation measure at on Carmen Creek at the SCC-03 diversion.  

CCI and CH2M Hill will continue work started under contract 63697.  CCI is providing support on the Lemhi River Basin Model Development.  CH2M Hill is providing support for the Upper Salmon Basin Ground Water-Surface Water Interactions Study, Phase 2.  

LRLT will complete planning for the Big Timber Project.  

TU will complete planning and design on the Muleshoe and L16/L17 projects.  OSC will also contract for some engineering services at this project site.
Account Type(s):
Expense
Contract Start Date:
01/01/2015
Contract End Date:
12/31/2015
Current Contract Value:
$1,818,673
Expenditures:
$1,818,673

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Bertram Idaho Governor's Office of Species Conservation Yes Technical Contact daniel.bertram@osc.idaho.gov (208) 756-6322
Allen Bradbury Idaho Governor's Office of Species Conservation Yes Technical Contact allen.bradbury@osc.idaho.gov (208) 756-6322
Jessica Buelow-IDFG Idaho Department of Fish and Game (IDFG) No Technical Contact jessica.buelow@idfg.idaho.gov (208) 756-2271
Rossana Callejas Bonneville Power Administration No Interested Party rxcallejas@bpa.gov (503) 230-7558
Sharon Clark Idaho Department of Fish and Game (IDFG) No Interested Party sharon.clark@idfg.idaho.gov (208) 287-2784
Becky Coffey Lemhi Soil and Water Conservation District (SWCD) No Interested Party lswcd@hotmail.com (208) 756-3211x101
Jeffrey DiLuccia Idaho Department of Fish and Game (IDFG) Yes Technical Contact jeff.diluccia@idfg.idaho.gov (208) 756-2271
Hannah Dondy-Kaplan Bonneville Power Administration Yes COR hadondy-kaplan@bpa.gov (503) 230-4071
Mike Edmondson Idaho Governor's Office of Species Conservation No Supervisor mike.edmondson@osc.idaho.gov (208) 334-2189
Abbie Gongloff Idaho Governor's Office of Species Conservation Yes Technical Contact abbie.gongloff@osc.idaho.gov (208) 756-6322
Amy Hines Idaho Governor's Office of Species Conservation Yes Contract Manager amy.hines@osc.idaho.gov (208) 332-1557
Eric (IDFG) Leitzinger Idaho Department of Fish and Game (IDFG) Yes Technical Contact eric.leitzinger@idfg.idaho.gov (208) 287-2798
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Stacey Meyer Idaho Department of Fish and Game (IDFG) Yes Technical Contact stacey.meyer@idfg.idaho.gov (208) 756-6022
Bob Minton Lemhi Soil and Water Conservation District (SWCD) No Technical Contact bobminton@hotmail.com (208) 756-4262
Adair Muth Idaho Governor's Office of Species Conservation Yes Technical Contact adair.muth@osc.idaho.gov (208) 756-6322
Gregory Smith Bonneville Power Administration Yes Env. Compliance Lead gmsmith@bpa.gov (503) 230-5049
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Jody White Quantitative Consultants Inc No Technical Contact jody@qcinc.org (208) 860-5269


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Provide EC documentation A: 165. Provide EC documentation 12/31/2015 12/31/2015
Draft documents for LMBM support B: 174. CCI: Lemhi River Basin Model Development Support: Produce Plan 12/31/2015 12/31/2015
Provide technical review C: 122. CCI: Lemhi River Basin Model Development Support: Provide Technical Review 12/31/2015 03/31/2015
Provide support to IDWR D: 174. CH2M Hill: USB Ground Water-Surface Water Interactions Study P 2 Support: Produce Plan 12/31/2015 12/31/2015
Provide support to IDWR E: 122. CH2M Hill: USB Ground Water-Surface Water Interactions Study P 2 Support: Provide Technical Review 12/31/2015 12/31/2015
Final engineering designs for Agency Creek county road culvert removal F: 175. LSWCD: Agency Creek County Road Culvert Removal Engineering Services 12/30/2015 11/27/2015
Purchase and install a prefabricated modular bridge G: 184. LSWCD: Pratt Creek Culvert Replacement 12/30/2015 10/30/2015
Purchase a pre-engineered modular steel bridge for Lower Bohannon Creek. H: 184. LSWCD: Lower Bohannon Creek Private Culvert Replacement Project 11/30/2015 10/19/2015
Purchase a pre-engineered modular steel bridge for Eighteenmile Creek. I: 184. LSWCD: Eighteenmile Creek Railroad Grade Culvert to Bridge Replacement Project 11/30/2015 09/11/2015
Purchase a hydroseeder for use in revegetation J: 47. LSWCD: Upper Hawley Creek Water Rights Point of Use Transfer 12/31/2015 04/21/2015
Relocate the POD downstream and install a pump and sprinkler irrigation system K: 203. LSWCD: Hawley-Eighteenmile Creeks Intercept Irrigation 11/30/2015 11/30/2015
Treat project sites for noxious weeds. L: 199. LSWCD: Noxious weed treatments 11/30/2015 11/10/2015
Purchase a pump and electrical wire for SCC-03 M: 203. LSWCD: Carmen Creek SCC3 Flow Enhancement Project 05/31/2015 06/05/2015
Develop a project plan for the Big Timber Project N: 114. LRLT: Big Timber Planning and Development 12/31/2015 12/30/2015
Lemhi River Project Identification and Development O: 114. IDFG: Identify and develop new projects 12/31/2015 12/31/2015
Final Design for Bohannon Creek Diversion #3 P: 175. IDFG: Bohannon Creek #3 diversion 12/31/2015
Preliminary design of the new Highway 29 crossing over Eighteenmile Creek/Hawley Creek Q: 175. IDFG: Highway 29 Culvert Replacement 12/31/2015 12/31/2015
Design of the Lower Lemhi Stokes Project R: 175. IDFG: Stokes Lower Lemhi River Project 12/31/2015 12/01/2015
Hayden Creek Side Channel Design S: 175. IDFG: Hayden Creek Side Channel 12/31/2015
Upper Bohannon Creek Bridge Final Design T: 175. IDFG: Bohannon Creek Upper Culvert Replacement 12/31/2015 07/31/2015
Bohannon Creek Bridge Installed U: 184. IDFG: Upper Bohannon Creek Culvert Replacement 12/15/2015 11/30/2015
Lower Lemhi River Restoration Project, Reach 1 Final Design V: 175. IDFG: Lower Lemhi, Eagle Valley Ranch 12/31/2015 08/31/2015
Revegetate all disturbed areas both riparian and upland as needed W: 47. IDFG: Amonson Upper Lemhi sc: revegetate disturbed areas with native vegetation 12/31/2015 07/03/2015
Revegetate all disturbed areas both riparian and upland as needed X: 47. IDFG: Snyder project - revegetate disturbed areas with native vegetation 12/31/2015 08/18/2015
Revegetate all disturbed areas both riparian and upland as needed Y: 47. IDFG: Little Springs Creek project - revegetate disturbed areas with native vegetation 12/31/2015 08/19/2015
Final engineering designs Z: 175. Design & Engineering for Muleshoe & L16/L17 Projects 12/31/2015 07/17/2015
Develop a project plan for the Muleshoe and L16/L17 projects AA: 174. TU: Project planning for Muleshoe & L16/L17 Projects 12/31/2015 07/17/2015
All administrative tasks fulfilled with timely quality products AB: 119. Manage and Administer Project 12/31/2015 12/31/2015
Attach progress report in Pisces. AC: 132. Submit Progress Report for the period (1/1/14) to (12/31/14) 04/22/2015 04/22/2015
Lower Lemhi Restoration Subreach 2 Jack Fence AE: 40. IDFG: Lower Lemhi Restoration - SubR-2: Install Jack Fence 11/30/2015 11/30/2015
Completed channel construction AF: 30. IDFG: Lower Lemhi Restoration - SubR-2 Construct side channel 10/31/2015 10/31/2015
Increased instream complexity and bank stability AG: 29. IDFG: Lower Lemhi Restoration - SubR-2 install log jams, rootwads, and individual logs 10/31/2015 10/31/2015
Construction Management Complete AH: 100. IDFG: Lower Lemhi Restoration - Construction oversight/management subreach 2 11/30/2015 11/30/2015
Preliminary Designs for Subreaches 1 and 3 AI: 175. IDFG: Lower Lemhi Restoration - assist with preliminary designs for subreaches 1 and 3 12/31/2015
Field work conducted AJ: 174. LRLT: Tyler Bank and Riparian Evaluation Study 12/31/2015 11/06/2015
Purchase pipeline and pivot AK: 203. Lemhi SWCD: Hawley Creek Access & Flow Enhancement (LHaC-01) Pipeline & Sprinkler Purchase 12/31/2015 12/31/2015
Purchase pipeline and pivot AL: 203. Lemhi SWCD: Canyon Creek Access & Flow Enhancement (CC-03) Pipeline & Sprinkler Purchase 12/31/2015 12/31/2015
Purchase pipeline AM: 203. Lemhi SWCD: Hawley Creek Access & Flow Enhancement (LHaC-02) Pipeline Purchase 12/31/2015 12/31/2015
Purchase sprinkler system AN: 203. Lemhi SWCD: Pratt Creek Access & Flow Enhancement (Mulkey) Sprinkler System Purchase 12/31/2015 12/31/2015
Purchase a pre-engineered modular steel bridge for the Agency Creek county road. AO: 184. Lemhi SWCD: Agency Creek Culvert Replacement Access Project: County Road Bridge Purchase 12/31/2015 12/31/2015
Data analysis - in progress AP: 162. RMRS: Lemhi Hydrologic Modeling Using LiDAR Data 12/31/2015 12/31/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 6 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 40 Install Fence
  • 4 instances of WE 47 Plant Vegetation
  • 4 instances of WE 184 Install Fish Passage Structure
  • 2 instances of WE 114 Identify and Select Projects
  • 4 instances of WE 174 Produce Plan
  • 9 instances of WE 175 Produce Design
  • 1 instance of WE 162 Analyze/Interpret Data
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 6 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 40 Install Fence
  • 4 instances of WE 47 Plant Vegetation
  • 5 instances of WE 184 Install Fish Passage Structure
  • 2 instances of WE 114 Identify and Select Projects
  • 4 instances of WE 174 Produce Plan
  • 9 instances of WE 175 Produce Design
  • 1 instance of WE 162 Analyze/Interpret Data
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide EC documentation 01/01/2015
B 174 CCI: Lemhi River Basin Model Development Support: Produce Plan 01/01/2015
C 122 CCI: Lemhi River Basin Model Development Support: Provide Technical Review 01/01/2015
D 174 CH2M Hill: USB Ground Water-Surface Water Interactions Study P 2 Support: Produce Plan 01/01/2015
E 122 CH2M Hill: USB Ground Water-Surface Water Interactions Study P 2 Support: Provide Technical Review 01/01/2015
F 175 LSWCD: Agency Creek County Road Culvert Removal Engineering Services 01/01/2015
G 184 LSWCD: Pratt Creek Culvert Replacement 06/18/2015
H 184 LSWCD: Lower Bohannon Creek Private Culvert Replacement Project 06/18/2015
I 184 LSWCD: Eighteenmile Creek Railroad Grade Culvert to Bridge Replacement Project 06/18/2015
J 47 LSWCD: Upper Hawley Creek Water Rights Point of Use Transfer 01/01/2015
K 203 LSWCD: Hawley-Eighteenmile Creeks Intercept Irrigation 06/26/2015
L 199 LSWCD: Noxious weed treatments 10/05/2015
M 203 LSWCD: Carmen Creek SCC3 Flow Enhancement Project 01/01/2015
N 114 LRLT: Big Timber Planning and Development 01/01/2015
O 114 IDFG: Identify and develop new projects 01/01/2015
P 175 IDFG: Bohannon Creek #3 diversion 01/01/2015
Q 175 IDFG: Highway 29 Culvert Replacement 01/01/2015
R 175 IDFG: Stokes Lower Lemhi River Project 08/05/2015
S 175 IDFG: Hayden Creek Side Channel 01/01/2015
T 175 IDFG: Bohannon Creek Upper Culvert Replacement 08/05/2015
U 184 IDFG: Upper Bohannon Creek Culvert Replacement 08/05/2015
V 175 IDFG: Lower Lemhi, Eagle Valley Ranch 04/22/2015
W 47 IDFG: Amonson Upper Lemhi sc: revegetate disturbed areas with native vegetation 01/01/2015
X 47 IDFG: Snyder project - revegetate disturbed areas with native vegetation 01/01/2015
Y 47 IDFG: Little Springs Creek project - revegetate disturbed areas with native vegetation 07/06/2015
Z 175 Design & Engineering for Muleshoe & L16/L17 Projects 01/01/2015
AA 174 TU: Project planning for Muleshoe & L16/L17 Projects 01/01/2015
AB 119 Manage and Administer Project 01/01/2015
AC 132 Submit Progress Report for the period (1/1/14) to (12/31/14) 01/01/2015
AD 185 Periodic Status Reports for BPA 01/01/2015
AE 40 IDFG: Lower Lemhi Restoration - SubR-2: Install Jack Fence 10/12/2015
AF 30 IDFG: Lower Lemhi Restoration - SubR-2 Construct side channel 10/12/2015
AG 29 IDFG: Lower Lemhi Restoration - SubR-2 install log jams, rootwads, and individual logs 10/12/2015
AH 100 IDFG: Lower Lemhi Restoration - Construction oversight/management subreach 2 01/01/2015
AI 175 IDFG: Lower Lemhi Restoration - assist with preliminary designs for subreaches 1 and 3 10/12/2015
AJ 174 LRLT: Tyler Bank and Riparian Evaluation Study 10/12/2015
AK 203 Lemhi SWCD: Hawley Creek Access & Flow Enhancement (LHaC-01) Pipeline & Sprinkler Purchase 10/12/2015
AL 203 Lemhi SWCD: Canyon Creek Access & Flow Enhancement (CC-03) Pipeline & Sprinkler Purchase 10/12/2015
AM 203 Lemhi SWCD: Hawley Creek Access & Flow Enhancement (LHaC-02) Pipeline Purchase 10/12/2015
AN 203 Lemhi SWCD: Pratt Creek Access & Flow Enhancement (Mulkey) Sprinkler System Purchase 10/12/2015
AO 184 Lemhi SWCD: Agency Creek Culvert Replacement Access Project: County Road Bridge Purchase 10/12/2015
AP 162 RMRS: Lemhi Hydrologic Modeling Using LiDAR Data 01/01/2015