Coordination with John Day Partners, Project Selection, and Prioritization |
A: 114. Project Selection and Prioritization |
|
01/31/2018 |
01/31/2018 |
BPA Project Administration Requirements |
B: 119. Manage Administer Projects |
|
01/31/2018 |
01/31/2018 |
Completed Environmental Compliance Documentation |
C: 165. 2016 Documents |
|
01/31/2017 |
01/31/2017 |
Completed Environmental Compliance Documentation |
D: 165. 2017 Documents |
|
01/31/2018 |
01/31/2018 |
Completed Annual Report |
F: 132. Submit Annual Report for the Period (02/01/2014) to (01/31/2016) |
|
12/31/2016 |
12/31/2016 |
Education and Community Relations |
G: 99. Fair Booths/Community Education and Participation/ School Presentations |
|
01/31/2018 |
01/31/2018 |
Data for Compliance, Status and Trend, and Effectiveness Monitoring |
H: 157. Implementation/Effectiveness Monitoring |
|
01/31/2018 |
01/31/2018 |
Data for Compliance, Status and Trend, and Effectiveness Monitoring |
I: 157. John Day Temperature Status and Trends |
|
01/31/2018 |
01/31/2018 |
Flow Data Available on USGS Website |
J: 157. Middle Fork Gaging Station Operation and Maintenance |
|
01/31/2018 |
01/31/2018 |
Rock Creek PIT Tagging |
K: 158. Rock Creek PIT Tag Array |
|
09/30/2017 |
09/30/2017 |
Middle Fork John Day PIT Tagging |
L: 158. Steelhead Fry and Habitat Research |
|
09/30/2017 |
09/30/2017 |
IDIQ Contract |
M: 122. IDIQ Engineering Support |
|
01/31/2018 |
01/31/2018 |
John Day Partnership |
N: 191. John Day Partnership |
|
01/31/2018 |
01/31/2018 |
Easement Management Plan |
P: 193. Canyon Ranch Easement Management Plan |
|
09/30/2017 |
01/31/2018 |
Construct RPB Easement Fence |
Q: 40. RPB Easement Fence |
|
01/31/2018 |
10/15/2016 |
Project Design for Pope Moon Creek Restoration |
R: 175. Design - Pope Moon Creek |
|
12/31/2016 |
06/30/2016 |
Project Design for Dovenberg Habitat Improvement |
V: 175. Design - Dovenberg Habitat Improvement |
|
04/30/2017 |
08/30/2016 |
Dovenberg Habitat Improvement |
W: 29. Dovenberg Habitat Improvement |
|
12/31/2017 |
08/31/2016 |
Project Design for Starr Habitat and Diversion |
X: 175. Design - Starr Habitat and Diversion |
|
12/31/2016 |
07/25/2016 |
Design and Implement a Log and Boulder Revetment and Instream Habitat Complexity |
Y: 29. Starr Habitat and Diversion: Instream Habitat |
|
12/31/2016 |
07/25/2016 |
Starr Habitat and Diversion: Side Channel Creation |
Z: 30. Starr Habitat and Diversion: Side Channel Creation |
|
12/31/2016 |
10/01/2016 |
Starr Habitat and Diversion: Pump Station |
AA: 84. Starr Habitat and Diversion; Pump Station |
|
12/31/2016 |
10/01/2016 |
Breech Railroad Grade in Floodplain |
AB: 180. Dunstan Preserve Flood Plain Enhancement: Phase Two |
|
12/31/2017 |
|
TNC Riparian Planting and Maintenance |
AC: 47. TNC Riparian Planting and Maintenance |
|
01/31/2018 |
12/31/2017 |
Mullin Phase 2 Juniper Removal |
AD: 199. Mullin Phase 2 Juniper Removal |
|
01/31/2018 |
12/31/2017 |
Mascall Phase 2 Juniper Removal |
AE: 199. Mascall Phase 2 Juniper Removal |
|
01/31/2018 |
12/31/2017 |
Lemons Phase 2 Juniper Removal |
AF: 199. Lemons Phase 2 Juniper Removal |
|
01/31/2018 |
12/31/2017 |
Planting and Maintenance |
AG: 198. Beech Creek Riparian Planting and Maintenance |
|
01/31/2018 |
12/31/2017 |
Planting and Maintenance |
AH: 198. Izee Riparian Planting and Maintenance |
|
01/31/2018 |
12/31/2017 |
Planting and Maintenance |
AI: 47. Bridge/Bear Creek Riparian Planting |
|
12/31/2017 |
12/31/2017 |
Project Selection |
AJ: 114. Program Support |
|
01/31/2018 |
01/31/2018 |
Project Design for Olex Diversion and Restoration |
AK: 175. Design Olex Diversion and Stream Restoration |
|
12/31/2017 |
07/31/2017 |
Design and Implement Instream Habitat Complexity on Rock Creek |
AL: 29. Olex Diversion Stream Restoration: Instream Habitat Complexity |
|
12/31/2017 |
|
Design and Implement Removal of Passage Barrier on Rock Creek |
AM: 84. Olex Diversion Stream Restoration: Passage Barrier Removal |
|
12/31/2017 |
|
Project Design for Hewes Diversion and Stream Restoration |
AN: 175. Design Hewes Diversion and Stream Restoration |
|
12/31/2017 |
06/01/2017 |
Project Design for Harper Diversion and Stream Restoration |
AQ: 175. Design Harper Diversion and Stream Restoration |
|
12/31/2017 |
07/31/2017 |
Design and Implement Instream Habitat Complexity at Diversion Removal Site |
AR: 29. Harper Diversion Stream Restoration: Instream Habitat Complexity |
|
12/31/2017 |
12/31/2017 |
Design and Implement Removal of Passage Barrier on Rock Creek |
AS: 84. Harper Diversion Stream Restoration: Diversion Removal |
|
12/31/2017 |
12/31/2017 |
Thirtymile PIT Tag Array |
AT: 70. Thirtymile Creek Steelhead PIT Tag Monitoring |
|
09/30/2017 |
02/01/2016 |
Weed Control |
AU: 199. Noxious Weed Control at Project Sites |
|
01/31/2018 |
01/31/2018 |
Project Design for Larson: One Canyon and Three Berry Creek Push-up Dam Replacements |
AV: 175. Design - Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements |
|
12/31/2017 |
07/31/2017 |
Design and Replace Four Push-Up Dams on Canyon and Berry Creeks |
AW: 84. Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements |
|
12/31/2017 |
09/30/2017 |
Henslee Fox Creek Habitat (Design) |
AY: 175. Design - Henslee Fox Creek Habitat |
|
01/31/2018 |
|
McGirr Fox Creek Habitat & Passage |
AZ: 175. Design - McGirr Fox Creek Habitat & Passage |
|
01/31/2018 |
|
Cavender Riparian Habitat and Wetland Habitat Protection |
BB: 180. Cavender Riparian Habitat and Wetland Habitat Protection |
|
12/31/2017 |
11/15/2016 |
Design and Implement Instream Habitat Work on Bridge Creek |
BD: 29. Bridge Creek Holistic Restoration |
|
12/31/2017 |
12/31/2017 |
Rock Creek Habitat Assessment |
BE: 115. Rock Creek Reach Assessment |
|
11/30/2017 |
11/30/2017 |
Upper Rock Creek Watershed Enhancement |
BF: 199. Upper Rock Creek Watershed Enhancement |
|
01/31/2018 |
01/31/2018 |
Design Review |
BG: 175. Design Review of Projects not covered by HIP III |
|
01/31/2018 |
01/31/2018 |
East Fork Beech Creek Instream and Floodplain Wood Project |
BH: 29. East Fork Beech Creek Wood #1 |
|
12/31/2017 |
09/30/2017 |
Squaw Creek Meadow Restoration: Phase 2: Meadow Restoration |
BI: 30. Squaw Creek Meadow Restoration: Phase 2: Meadow Restoration |
|
12/31/2016 |
09/30/2016 |
Squaw Creek Restoration: Phase 2: Instream Habitat |
BJ: 29. Squaw Creek Meadow Restoration: Phase 2: Instream Habitat |
|
12/31/2016 |
09/30/2016 |
Camp Creek Headwater Restoration: Instream Habitat |
BK: 29. Camp Creek Headwater Restoration: Instream Habitat |
|
12/31/2016 |
09/30/2016 |
Camp Creek Headwaters Restoration: Riparian Plantings |
BL: 47. Camp Creek Headwaters Restoration: Riparian Plantings |
|
12/31/2016 |
09/30/2016 |
MFJDR Galena Tailings Design |
BM: 175. Design - MFJDR Galena Tailings |
|
01/31/2018 |
01/31/2018 |
John Day River and Reynolds Creek Project Design |
BN: 175. Design - John Day River and Reynolds Creek Habitat |
|
01/31/2018 |
01/31/2018 |
Completed Annual Report |
CC: 132. Submit Annual Report for the Period (2/1/2010) to (1/31/2014) |
|
12/31/2016 |
12/31/2016 |
South Fork John Day Riparian Planting |
CE: 47. Tier 2: South Fork John Day Riparian Planting |
|
01/31/2018 |
12/31/2017 |
Complete Technical Memorandum |
CF: 162. Dunstan Groundwater Well Analysis |
|
06/30/2017 |
06/30/2017 |
Design of Cottonwood Creek Basin WASCOBs |
CG: 175. Design Cottonwood Sediment Control |
|
12/31/2017 |
12/31/2017 |
Produce Design |
CH: 175. Design Fox Creek Habitat |
|
10/31/2017 |
09/30/2017 |
Produce Design |
CI: 175. Design Rock Creek Diversion |
|
12/31/2017 |
|
Install Pipeline |
CJ: 203. Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements - Pipeline |
|
04/30/2017 |
12/01/2016 |
Install bridge, fencing, water development, and riparian planting |
CK: 184. CCR-38546 Upper John Day River Crossing |
|
12/15/2017 |
12/15/2017 |
Produce accessible, error-checked datasets |
CL: 157. CCR-38546 Collection of Fish Data (Biological, Physical, Demographic) |
|
01/31/2018 |
|
Complete Mark-Recapture Activities, will be determined when abundance is known. |
CM: 158. CCR-38546 Mark-Recapture Studies |
|
01/31/2018 |
|
Data Analysis |
CN: 162. CCR-38546 Analysis and Interpretation of Field Data Collected from Fisheries Surveys |
|
01/31/2018 |
|
Fox Creek Design Reach 18 |
CO: 175. CCR-38546 Fox Creek Design Reach 18 Instream Restoration |
|
01/31/2018 |
01/31/2018 |
Harvest Whole Trees for Instream Restoration Work |
CP: 199. CCR-38546 Fox Creek Harvest Whole Trees for Instream Restoration |
|
01/31/2018 |
12/31/2017 |
Remove Juniper |
CQ: 199. CCR-38546 Fox Creek Juniper Removal |
|
01/31/2018 |
12/31/2017 |
Planting Plan |
CR: 174. CCR-38546 Fox Creek Vegetation and Planting Plan |
|
01/31/2018 |
12/31/2017 |
Fox Creek Mid Reach 10 Habitat Project Phase 1 |
CS: 30. CCR-38546 Fox Creek Mid Reach 10 Habitat Restoration, Phase 1 |
|
01/31/2018 |
|
Pre-acquisition Activities |
CT: 172. CCR-38546 Pre-Acquisition Activities for GSG Easement |
|
01/30/2018 |
|
Project Development and Data Management |
CU: 98. CCR-38546 JDBO Project Development and Data Management |
|
01/31/2018 |
01/31/2018 |
Conduct Lonerock Ridge Juniper Project |
CV: 199. CCR-38546 Lonerock Ridge Juniper Project |
|
01/31/2018 |
|