Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73548 REL 152: 2023-001-00 EXP CCT OKANOGAN RESTORATION

Last Modified: John Box, 08/02/2022 9:54 AM   
Basics

Project Number:
Title:
Upper Columbia Habitat Improvement Project (UCHIP)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 33.30%
Okanogan 33.40%
Wenatchee 33.30%
Contract Number:
73548 REL 152
Contract Title:
2023-001-00 EXP CCT OKANOGAN RESTORATION
Contract Continuation:
Previous: Next:
73548 REL 119: 2007-224-00 EXP IMPLMNT OKANOGAN SUBBASIN PLAN
  • CR-365000: 2023-001-00 EXP CCT OKANOGAN RESTORATION
  • CR-365246: 2023-001-00 EXP CCT OKANOGAN RESTORATION
  • 84051 REL 1: 2023-001-00 EXP CCT OKANOGAN RESTORATION
Contract Status:
Closed
Contract Description:
This contract is to conduct aquatic habitat improvement projects in the Okanogan Subbasin.  Projects to be implemented will primarily emphasize benefits to ESA listed spring Chinook, summer steelhead, and bull trout and secondarily to other salmonids and Pacific lamprey.  Work will include regular attendance of coordination meetings with project sponsors and oversight groups to ensure that work is conducted consistent with established needs and in coordination with other existing restoration efforts.

Projects prioritization is based on the 2017 EDT model run for the Okanogan Subbasin, the 2021 Regional Technical Team Biological Strategy and the Upper Columbia Salmon Recovery Boards prioritization.    

Work under this contract cycle will include:

•    Antoine Valley Ranch Floodplain Restoration:  Design
•    Upper Omak Complexity BDAs:  Design

Additionally, CTCR will continue supporting public outreach and educate for local students and the general public about the importance of salmon recovery and habitat improvement in the Okanogan Valley.

Cultural resource surveys as required under Section 106 of the NHPA, unless previously completed prior to this contract period, will be completed by the Colville Confederated Tribes Cultural Resource staff.
    
The contractor (CTCR), its designated agents, sub-consultants and project stakeholders will be available, responsive and will collaboratively address contract related issues during the term of the contract. Contract issues include but are not limited to technical, policy, regulatory, project management and associated elements related to the project. Successful execution of this contract is contingent on alignment of the preceding contract issues with the BPI and BPA contracting processes, project management plans, design review protocols (including but not limited to BPA RRT design review, and integration of input and comments from BPA).

CTCR Contract Manager and design consultants will cooperate, coordinate, collaborate, and maintain effective communication with BPA PM/COR, EC Lead, and BPA ETS, during the entire length of this design contract. CTCR and its subcontractors will address BPA comments and concerns, and the two entities will arrive at a mutual beneficial consensus.


Personnel working on the project are:

John Box- project manager: project oversight, project development, coordinate with interested parties, public relations and funding and cost share developer.  Develop proposals, write reports, internal and external coordination

Chris Fisher - project oversight, project development, coordinate with interested parties, public relations, outreach and education, and funding and cost share developer.

Kirk Truscott - Anadromous Division Lead-Represent the habitat division in upper level management and forums.  Participate with council and internal planning decisions that affect the habitat division.  Help to vet projects through the MOA agreement.

Casey Baldwin - participate in FPRB coordination, work with regional partners and forums to help facilitate habitat project implementation.  Biological expertise.

Dennis Papa - help to develop projects through field exploration, oversee construction implementation, write permits, and maintain habitat improvement projects.

Arnold Abrahamson - oversee construction projects, help on projects with heavy equipment, hauling and transport.  Evaluate habitat needs through field participation, repair fences, and otherwise maintain habitat improvement projects.
Account Type(s):
Expense
Contract Start Date:
11/01/2022
Contract End Date:
10/31/2023
Current Contract Value:
$751,940
Expenditures:
$751,940

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Coordinate with EC lead A: 165. Produce Compliance Documentation 10/31/2023 10/31/2023
Cultural surveys to BPA B: 165. Cultural Resource Surveys 10/31/2023 10/31/2023
Effective implementation management and timely contract administration C: 119. Manage and Administer Project 10/31/2023 10/31/2023
Completed Annual Report E: 132. Restore Salmon Creek annual Report 10/31/2023
Completed Annual Report F: 132. OSHIP Annual Report 10/31/2023 10/31/2023
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces G: 114. Identify and Select Projects 10/31/2023 10/31/2023
Complete watershed coordination H: 191. Contact Landowners and Interested Public Parties, attend Meetings 10/31/2023 10/31/2023
Upload report of completed work J: 29. Small wood Adaptive Management 10/31/2023 10/31/2023
Upload copies of assessments to CBFish K: 115. Okanagan Subbasin Assessments 10/31/2023 10/31/2023
Support the Upper Columbia habitat prioritization process M: 115. Upper Columbia Habitat Prioritization Support 10/31/2023 10/31/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 115 Produce Inventory or Assessment
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 115 Produce Inventory or Assessment
Sockeye (O. nerka) - Okanogan River ESU
  • 1 instance of WE 115 Produce Inventory or Assessment
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 175 Produce Design
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Compliance Documentation
B 165 Cultural Resource Surveys
C 119 Manage and Administer Project
D 185 Periodic Status Reports for BPA
E 132 Restore Salmon Creek annual Report
F 132 OSHIP Annual Report
G 114 Identify and Select Projects
H 191 Contact Landowners and Interested Public Parties, attend Meetings
I 175 Antoine Creek Floodplain 08/30/2023
J 29 Small wood Adaptive Management 08/30/2023
K 115 Okanagan Subbasin Assessments 08/30/2023
L 175 Omak Creek Instream Complexity 08/30/2023
M 115 Upper Columbia Habitat Prioritization Support 08/30/2023