76826 REL 21: 2002-011-00 EXP KOOTENAI RIVER OPERATIONAL LOSS ASSESSMENT |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Daniel Affonso | Bonneville Power Administration | Yes | Contracting Officer | dxaffonso@bpa.gov | (503) 230-5918 |
Shannon Ehlers | Kootenai Tribe | Yes | Interested Party | sehlers@kootenai.org | (208) 267-3620x555 |
Edward Gresh | Bonneville Power Administration | Yes | Env. Compliance Lead | esgresh@bpa.gov | (503) 230-5756 |
David Kaplowe | Bonneville Power Administration | Yes | F&W Approver | djkaplowe@bpa.gov | (503) 230-5365 |
Jennifer McKenna | Bonneville Power Administration | No | CO Assistant | jmmckenna@bpa.gov | (503) 314-8915 |
Scott Soults | Kootenai Tribe | Yes | Contract Manager | soults@kootenai.org | (208) 267-3620 |
Shelby Therrian | Kootenai Tribe | Yes | Technical Contact | shelby.therrian@kootenai.org | (208) 267-3620 |
Virgil Watts III | Bonneville Power Administration | Yes | COR | vlwatts@bpa.gov | (503) 230-4625 |
Theresa Wheat | Kootenai Tribe | No | Administrative Contact | theresa@kootenai.org | (208) 267-3620 |
Shawn Young | Kootenai Tribe | Yes | Supervisor | young@kootenai.org | (208) 597-4490 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Project Administration & Oversight | A: 119. Oversight and Administration of Planning, Design, and New Project Activities | 11/30/2022 | 11/30/2022 | |
Complete Annual Report for Performance period | C: 132. Produce Annual Progress Report Covering Actions for 2021-2022 | 11/30/2022 | 11/30/2022 | |
Reconnect Technical Review Team | D: 122. Reconnect Technical Review Team | 11/30/2022 | 11/30/2022 | |
Map and Inventory the Areas Planted with Native Species | E: 47. Augment Vegetation on Mitigation Parcels Where Needed | 11/30/2022 | 11/30/2022 | |
Propose New Protection Projects to BPA | F: 114. Identify Potential Mitigation and Future Project Opportunities | 11/30/2022 | 11/30/2022 | |
Complete and Provide all Cultural Resource Documentation as Needed for Potential Implementation. | G: 165. Complete EC and Permitting for Objective F: Identification of potential projects | 11/30/2022 | 11/30/2022 | |
Collaboration between KTOI Wildlife and KRHRP Technical Teams | H: 122. Kootenai River Habitat and Hydrology Coordination Team | 11/30/2022 | 11/30/2022 | |
Completed As-built Report for Nimz North Quad - All Phases | I: 141. Other Reports for BPA | 11/30/2022 | 11/30/2022 | |
Final Assessment Plan | J: 141. Other Reports for BPA | 11/30/2022 | 11/30/2022 | |
Completed building or facility | K: 201. Construct Conservation Nursery at Nimz Ranch | 11/30/2022 | 11/30/2022 | |
Ensure EC documents and permits are in for the nursery project. | L: 165. Complete EC and Permitting for Nimz Ranch – Objective K: Conservation Nursery (WE 201) | 11/30/2022 | 11/30/2022 | |
Completed Work Related to Property Pre-Acquisition | M: 172. Potential Land Acquisition Tasks and Evaluations | 11/30/2022 | 11/30/2022 | |
Completed building or facility | N: 201. Renovation of Nimz CU House and Garage for Admin. Use | 11/30/2022 | 11/30/2022 | |
Ensure EC documents and permits are in for the Nimz house project. | O: 165. Complete EC and Permitting for Nimz Ranch House Site– Objective N: Renovation of Nimz Ranch House and Garage (WE 201) | 11/30/2022 | 11/30/2022 |
Primary Focal Species | Work Statement Elements |
---|---|
Wildlife |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Oversight and Administration of Planning, Design, and New Project Activities | |||||||
B | 185 | Periodic Status Reports for BPA | |||||||
C | 132 | Produce Annual Progress Report Covering Actions for 2021-2022 | |||||||
D | 122 | Reconnect Technical Review Team | |||||||
E | 47 | Augment Vegetation on Mitigation Parcels Where Needed | 10/14/2021 | ||||||
F | 114 | Identify Potential Mitigation and Future Project Opportunities | |||||||
G | 165 | Complete EC and Permitting for Objective F: Identification of potential projects | |||||||
H | 122 | Kootenai River Habitat and Hydrology Coordination Team | |||||||
I | 141 | Other Reports for BPA | |||||||
J | 141 | Other Reports for BPA | |||||||
K | 201 | Construct Conservation Nursery at Nimz Ranch | 12/05/2022 | ||||||
L | 165 | Complete EC and Permitting for Nimz Ranch – Objective K: Conservation Nursery (WE 201) | |||||||
M | 172 | Potential Land Acquisition Tasks and Evaluations | |||||||
N | 201 | Renovation of Nimz CU House and Garage for Admin. Use | 03/24/2023 | ||||||
O | 165 | Complete EC and Permitting for Nimz Ranch House Site– Objective N: Renovation of Nimz Ranch House and Garage (WE 201) |