Manage & Administer Project |
A: 119. Manage & Administer Project |
|
06/30/2019 |
06/30/2019 |
Comply with Environmental Requirements |
B: 165. Environmental compliance for CREP technician duties |
|
06/30/2019 |
06/30/2019 |
Coordinate with (120 total) Private Landowners & Partner Agencies |
C: 99. Landowner Outreach and Project Prioritization |
|
06/30/2019 |
06/30/2019 |
CREP Plan Developed and Approved |
D: 40. New CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
|
CREP Plan Developed and Approved |
E: 40. New CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
|
CREP Plan Developed and Approved |
F: 40. New CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
|
CREP Plan Developed and Approved |
G: 40. New CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
|
CREP Plan Developed and Approved |
H: 40. New CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
|
CREP Plan Developed and Approved |
I: 40. New CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA (location to be determined) |
|
06/30/2019 |
|
CREP Plan Developed and Approved |
J: 40. New CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA (location to be determined) |
|
06/30/2019 |
|
CREP Renewal Developed and Approved |
K: 92. Renew CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
08/29/2018 |
CREP Renewal Developed and Approved |
L: 92. Renew CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
08/29/2018 |
CREP Renewal Developed and Approved |
M: 92. Renew CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
09/06/2018 |
CREP Renewal Developed and Approved |
N: 92. Renew CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA |
|
06/30/2019 |
09/07/2018 |
Planting Plan Developed and Implementation Funding Obtained |
O: 47. Provide technical support to enhance riparian vegetation |
|
06/30/2019 |
06/30/2019 |
Provide Technical Review on Implementation of Conservation Plans |
P: 122. Provide Technical Review on Implementation of Approved Conservation Plans |
|
06/30/2019 |
06/30/2019 |
Completed Annual Report |
R: 132. Submit Progress Report for the Period 7/1/16 - 6/30/18 |
|
08/01/2018 |
09/04/2018 |