Contract 84044 REL 12: 2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Project Number:
Title:
Red River/Newsome Creek Watershed Restoration
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
84044 REL 12
Contract Title:
2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
74017 REL 98: 2002-072-00 EXP RED RIVER WATERSHED RESTORATION
  • 84044 REL 39: 2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Contract Status:
Issued
Contract Description:
Red River & Newsome Creek are main tributaries to the South Fork Clearwater River and have historically been strongholds for steelhead, bull trout, and Chinook salmon. Past land management activities have severely degraded spawning and rearing habitat for these species. This project proposes to restore degraded habitats through a comprehensive restoration program focusing primarily on the mainstem channels, floodplains, and riparian corridors.

The Tribe proposes to address the primary limiting factors to abundance and productivity of the focal species. The Tribe and Forest Service have prioritized restoration projects to address these limiting factors based on the Clearwater Subbasin Plan (NPCC 2005), South Fork Clearwater River Landscape Assessment (USDA 1998), Newsome Creek Ecosystem Analysis at the Watershed Scale ((EAWS), USDA 2002), Red River EAWS (USDA 2003), and the 2016 Clearwater Expert Panel process.

The resulting habitat improvements will increase survival for the following fish populations: Snake River Steelhead (O. mykiss) - ESA Threatened and Designated Critical Habitat, Snake River spring/summer Chinook (O. tshawytscha), bull trout (S. confluentus) - ESA Threatened and Designated Critical Habitat, Westslope cutthroat trout (O.c. lewisi), rainbow trout (O. mykiss), and Pacific lamprey (Lampetra tridentata).

This project is part of the Nez Perce Clearwater National Forest, Nez Perce Tribe, and BPA Watershed Restoration Partnership.  Since the project’s inception, we have shared project planning, costs, and implementation responsibilities.  This contract period's work will consist of plant maintenance on the past larger riparian planting efforts in the  Lower Red River Meadow & Newsome Creek project areas, as well as annual fence maintenance on the RR Meadow Conservation Easement.  Work may continue on the Red River Corrals property (planning of future potential projects).   We will subcontract designs (conceptual) for LWD/Boulder placement for both Red River & Newsome Creek, as well as completing environmental compliance activities.  There has also been interest from several other landowners within Red River to look at their meadow properties for potential restoration activities. We will be working towards partnerships with interested landowners as their properties are key components to restoring river processes both within the Red River Watershed and South Fork Clearwater River subbasin.

Projects for 2023/2024 that are finishing up and/or continuing the planning phase are: Newsome Phase II (covers approximately seven miles of mainstem stream habitat complexity through LWD and boulder placement); Lower Red River LWD (up to 8 miles of river habitat complexity through addition of LWD); Red River private property restoration; and re-visiting the Siegel Creek Culvert replacement.  Implementation will consist of riparian planting on the Red River Wildlife Management Area (WMA) as well as the replacement of 2 fish barrier culverts on Trapper Creek (a main tributary to Red River).
Account Type(s):
Expense
Contract Start Date:
02/01/2023
Contract End Date:
01/31/2024
Current Contract Value:
$759,884
Expenditures:
$649,226

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Stephanie Bransford Nez Perce Tribe Yes Contract Manager stephanieb@nezperce.org (208) 983-0675
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Thomas Delorenzo Bonneville Power Administration Yes Env. Compliance Lead tdelorenzo@bpa.gov (503) 230-4419
Heidi Haserot Bonneville Power Administration No Interested Party hmhaserot@bpa.gov (503) 230-3115
Arleen Henry Nez Perce Tribe No Technical Contact arleenh@nezperce.org (208) 621-3833
David Kaplowe Bonneville Power Administration Yes Supervisor djkaplowe@bpa.gov (503) 230-5365
Eric Leitzinger Bonneville Power Administration Yes F&W Approver ejleitzinger@bpa.gov (503) 230-3534
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023
Ryan Ruggiero Bonneville Power Administration Yes COR RCRuggiero@bpa.gov (503) 230-3789
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Frederick Walasavage Bonneville Power Administration No Interested Party fwalasavage@bpa.gov (541) 296-3615
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Complete B: 165. Submit Environmental Compliance Documentation to BPA 01/31/2024 01/31/2024
Red River Meadow (RR WMA) Planted C: 47. Red River Meadows Planting - 2023 01/31/2024 09/25/2023
Red River & Newsome plant maintenance completed F: 198. Red River & Newsome Plant Maintenance 09/14/2023 08/10/2023
Red River meadow fence maintained. G: 186. Red River Meadows Fence Maintenance (Private Property) 07/31/2023 06/16/2023
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces H: 114. Red River/Newsome Project Selection 01/31/2024 01/31/2024
Effective implementation management and timely contract administration I: 119. Management and Administration of FY23 Contract 01/31/2024 01/31/2024
Watershed Coordination Completed J: 191. Coordinate with partner agencies in restoration planning in the Red River basin 01/31/2024 01/31/2024
Technical review of partner documents completed K: 122. Review of Proposed Partner Actions 01/31/2024 01/31/2024
Completed Annual Report L: 132. Submit Progress Report for the period February 2023 to January 2024 01/31/2024 01/31/2024
Supplies/materials/equipment purchased and delivered M: 184. Purchase and deliver materials for Trapper Creek culvert replacements 01/31/2024 12/04/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 47 Plant Vegetation
  • 2 instances of WE 184 Install Fish Passage Structure
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 47 Plant Vegetation
  • 3 instances of WE 184 Install Fish Passage Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Submit Environmental Compliance Documentation to BPA
C 47 Red River Meadows Planting - 2023 06/09/2023
D 184 Trapper Creek Culverts (Culvert #1) 06/09/2023
E 184 Trapper Creek Culverts (Culvert #2) 06/09/2023
F 198 Red River & Newsome Plant Maintenance 06/09/2023
G 186 Red River Meadows Fence Maintenance (Private Property) 06/09/2023
H 114 Red River/Newsome Project Selection
I 119 Management and Administration of FY23 Contract
J 191 Coordinate with partner agencies in restoration planning in the Red River basin
K 122 Review of Proposed Partner Actions
L 132 Submit Progress Report for the period February 2023 to January 2024
M 184 Purchase and deliver materials for Trapper Creek culvert replacements 06/09/2023