Effective implementation management and timely contract administration |
A: 119. Manage and administer projects |
|
09/30/2021 |
09/30/2021 |
All applicable EC documents |
B: 165. NEPA and ESA documents, & other cultural or environmental clearance |
|
07/30/2021 |
|
Removal of 10,000 - 20,000 lake trout from Flathead Lake by incentivized angling |
C: 190. Remove lake trout from Flathead Lake by incentivized fishing events |
|
05/30/2021 |
05/30/2021 |
Construction of a new boundary fence on Adams property totaling 2,500 feet. |
D: 40. Install and maintain fence on Finley Creek (Adams) property |
|
09/30/2021 |
|
Construction of a new boundary fence totaling 3,500 feet. |
E: 40. Install and maintain fence on the Hummingbird (Hoyt) property |
|
08/30/2021 |
|
Construction of a new boundary fence on Pearlshell property |
F: 40. Install and maintain fence on the Pearlshell property |
|
08/30/2021 |
|
Construction of 10,000 ft of boundary fence on Upper Demonstration Reach property |
G: 40. Construction of fence on Upper Demonstration Reach property |
|
09/30/2021 |
|
Construction of 3,500 ft. of boundary fence on Scott property |
H: 40. Construction of boundary fence on Scott property |
|
09/30/2021 |
|
Install 1,300 ft of fence on Post Creek property |
I: 40. Install boundary fence on Post Creek property |
|
09/30/2021 |
|
Control noxious weeds on 300 acres of acquired properties |
J: 198. Control noxious weeds and/or re-seed acquired properties |
|
07/30/2021 |
09/30/2021 |
Monitoring results on up to 51 acquired properties for trespass and unforeseen problems |
K: 26. Monitor acquired properties for trespass and unforeseen problems |
|
09/30/2021 |
09/30/2021 |
Maintenance of access points and parking areas on Elk Creek and Hoff/Ravalli properties |
L: 188. Construct new public access point on the Elk Creek property |
|
09/30/2021 |
09/30/2021 |
Remove structures and debris from Bird's Eye View property |
M: 27. RESCHEDULED FR 2020: Remove structures/debris from Bird's Eye View property |
|
09/30/2021 |
|
Complete all planned debris removal on Ravalli Curves property |
N: 27. RESCHEDULED FR 2020: Remove structures/debris from Ravalli Curves property |
|
09/30/2021 |
09/30/2021 |
Removal of small cabin from property |
O: 27. Remove structures/debris from Pearlshell property |
|
09/30/2021 |
|
Remove debris from Upper Demonstration Reach property |
P: 27. RESCHEDULED FR 2020: Remove debris/structures from Upper Demonstration Reach |
|
09/30/2021 |
|
Seed about 8 acres with cuttings and nursery-grown native plants. |
Q: 47. Plant dormant willow cuttings and nursery plants and seed native grasses on Ravalli property |
|
07/30/2021 |
|
Plant native grasses and forbs on 25 acres on Post Creek property |
R: 47. Plant native grasses and forbs on the Post Creek property |
|
09/30/2021 |
|
Drill seed 5 acres on Valley Creek property with native grasses and forbs |
S: 47. Plant native grasses and forbs on Valley Creek property |
|
09/30/2021 |
|
Seed five acres of Valley Creek property with native grasses and forbs |
T: 47. Plant woody vegetation on Schall Ranch property |
|
09/30/2021 |
|
Land management plans for up to three newly acquired properties |
U: 193. Produce land management plans on newly acquired properties |
|
09/30/2021 |
03/30/2021 |
Coordination meetings and new project/cost share opportunities |
V: 191. New and ongoing coordination activities |
|
09/30/2021 |
09/30/2021 |
List of projects for FY2021 and beyond |
W: 114. Identify problems and coordinate solutions |
|
09/30/2021 |
09/30/2021 |
Appraisal reports, NEPA documents, surveys, and title reports |
X: 172. Work with project 200200300 on acquisitions & easements |
|
09/30/2021 |
09/30/2021 |
Completed Annual Report |
Y: 132. Submit Progress Report for the period (10/1/2018) to (9/30/2019) |
|
06/01/2021 |
06/01/2021 |
HGM assessments on at least four properties |
AA: 115. Conduct HydroGeoMorphic assessment of conditions on acquired properties |
|
09/30/2021 |
09/30/2021 |
Seed up to 10 acres with native grasses to replace weed infestations. |
AB: 47. RESCHEDULE FROM FY20: Seed Howes acquisition with native grasses to replace weed infestations (weed subcontract) |
|
09/30/2021 |
|
Remove debris |
AC: 27. RESCHEDULE FROM FY20: Remove structures/debris from Upper Demonstration Reach property |
|
09/30/2021 |
|