Effective implementation management and timely contract administration |
A: 119. Manage BPA Project |
|
12/31/2024 |
12/31/2024 |
Complete Environmental Compliance |
B: 165. Work with BPA on Environmental Compliance requirements. |
|
12/31/2024 |
12/31/2024 |
Coordinate habitat efforts with CTWS and Hood River Project Partners |
C: 191. Coordinate activities with CTWS and project partners |
|
12/31/2024 |
12/31/2024 |
Inspection of past habitat project complete |
D: 186. Post-Project Inspection and Monitoring |
|
12/31/2024 |
09/30/2024 |
Powerdale corridor feasibility & concept design complete |
E: 175. Powerdale Corridor Feasibility & Concept Design |
|
12/31/2024 |
12/31/2024 |
East Fork Hood River Phase 2 Final Design Completed |
F: 175. East Fork Hood River Phase 2 Design - carried forward from prior agreement |
|
12/31/2024 |
|
East Fork Hood River Phase 3 Design Completed |
G: 175. East Fork Hood River Phase 3 Design - carried forward from prior agreement |
|
12/31/2024 |
|
Designs produced |
H: 175. Neal Creek: Phase 3 Habitat and Floodplain Improvement Design - carried forward from prior agreements |
|
07/01/2024 |
06/30/2024 |
Construction Management Complete |
I: 100. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Construction Management |
|
10/31/2024 |
10/31/2024 |
Aquatic and floodplain complexity actions completed |
J: 29. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Install LWD |
|
11/30/2024 |
11/30/2024 |
Completed channel construction |
K: 30. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Realign main channel and connect side channels |
|
11/30/2024 |
11/30/2024 |
Floodplain enhanced |
L: 180. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Reconnect and enhance floodplain |
|
11/30/2024 |
11/30/2024 |
Vegetation enhanced |
M: 47. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Plant Riparian Area |
|
12/31/2024 |
12/31/2024 |
Final design completed |
N: 175. Baldwin Creek Passage, Habitat and Floodplain Improvement - Produce Design |
|
06/30/2024 |
06/30/2024 |
Construction Management Complete |
O: 100. Baldwin Creek Passage, Habitat and Floodplain Improvement - Construction Management |
|
10/31/2024 |
10/31/2024 |
Removal of fish passage barrier completed. |
P: 85. Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove Full Passage Barrier |
|
10/31/2024 |
10/11/2024 |
Removal of fish passage barrier complete |
Q: 85. Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove Partial Passage Barrier |
|
10/31/2024 |
10/31/2024 |
Baldwin Habitat Enhancement Completed |
R: 29. Baldwin Creek Passage, Habitat and Floodplain Improvement - Install LWD |
|
10/31/2024 |
10/31/2024 |
Completed channel construction |
S: 30. Baldwin Creek Passage, Habitat and Floodplain Improvement - Realign main channel and connect side channels |
|
10/31/2024 |
10/31/2024 |
Complete implementation of approved design |
T: 180. Baldwin Creek Passage, Habitat and Floodplain Improvement - Reconnect and enhance floodplain |
|
10/31/2024 |
10/31/2024 |
Floodplain wetlands enhanced |
U: 181. Baldwin Creek Passage, Habitat and Floodplain Improvement - Reconnect and enhance floodplain wetlands |
|
10/31/2024 |
10/31/2024 |
Plant Vegetation Completed |
V: 47. Baldwin Creek Passage, Habitat and Floodplain Improvement - Plant Riparian Area |
|
12/31/2024 |
|
Invasive vegetation removal complete |
W: 199. Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove vegetation |
|
12/31/2024 |
10/25/2024 |
Completed Annual Report |
X: 132. Prepare and submit annual progress report for work completed under the prior agreement period. |
|
04/15/2024 |
04/15/2024 |