SOW Report
Contract 93974: 1998-021-00 EXP HOOD RIVER FISH HABITAT - HRWG
Project Number:
Title:
Hood River Fish Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
93974
Contract Title:
1998-021-00 EXP HOOD RIVER FISH HABITAT - HRWG
Contract Continuation:
Previous: Next:
91616: 1998-021-00 EXP HOOD RIVER FISH HABITAT
Contract Status:
Issued
Contract Description:
In FY24, the Hood River Watershed Group (HRWG) will complete designs on several projects, conduct landowner outreach, implement a habitat project and a passage project, and monitor pre and post-project physical characteristics at project sites.

This agreement has been coordinated with and approved by the Confederated Tribes of the Warm Springs (CTWS). BPA and HRWG are entering into the agreement in order to continue CTWS habitat actions within the Hood River Basin during a period of staff vacancies and transition at the CTWS Hood River office. This agreement will ease CTWS administrative burden and allow for continued implementation during this transition. A concurrent BPA/CTWS agreement will provide funding for additional CTWS staff, flow monitoring, and EFID work that is not included in this agreement.

FISCAL YEAR 2024 OBJECTIVES:

Goal: Complete feasibility evaluations and project designs for fish habitat restoration projects in high priority stream reaches, as identified in the Hood River Basin Partnership Strategic Action Plan (2021).
Objective 1: Finish lower East Fork Hood River Phase 2 and Phase 3 fish habitat restoration designs.
Objective 2: Finalize Neal Creek Phase 3 fish habitat restoration design.
Objective 3: Finalize Baldwin Creek fish habitat restoration and fish passage design.
Objective 4: Evaluate feasibility of fish habitat restoration actions in the Powerdale Corridor of the Hood River, including removal of the old PacifiCorps powerhouse and modifying railroad infrastructure to allow for floodplain reconnection.

Goal: Implement fish habitat restoration projects in high priority stream reaches, as identified in the Hood River Basin Partnership Strategic Action Plan (2021).
Objective 1: Implement Neal Creek Phase 3 fish habitat restoration project to improve approximately 2 miles of steelhead and coho spawning and rearing habitat.
Objective 2: Remove two fish passage barriers on Baldwin Creek to provide access to 2 miles of upstream habitat; begin riparian and wetland restoration.

Goal: Educate watershed residents on the ecology, fisheries, and tribal involvement in the Hood River Watershed. Recruit and engage private streamside landowners to begin development of additional habitat projects in high priority stream reaches.
Objective 1: Provide 8 public presentations or tours on topics such as watershed ecology and conservation, fish populations and management, tribal history, and completed restoration projects.
Objective 2: Recruit 3 to 5 new private streamside landowners for out-year habitat restoration projects.

Goal: Evaluate the impact of habitat restoration projects.
Objective 1: Conduct pre and post-project monitoring of habitat restoration projects according to joint CTWS-USFS-HRWG habitat monitoring protocol.
Account Type(s):
Expense
Contract Start Date:
01/01/2024
Contract End Date:
12/31/2024
Current Contract Value:
$1,326,944
Expenditures:
$1,185,012

* Expenditures data includes accruals and are based on data through 31-Dec-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. Manage BPA Project 12/31/2024 12/31/2024
Complete Environmental Compliance B: 165. Work with BPA on Environmental Compliance requirements. 12/31/2024 12/31/2024
Coordinate habitat efforts with CTWS and Hood River Project Partners C: 191. Coordinate activities with CTWS and project partners 12/31/2024 12/31/2024
Inspection of past habitat project complete D: 186. Post-Project Inspection and Monitoring 12/31/2024 09/30/2024
Powerdale corridor feasibility & concept design complete E: 175. Powerdale Corridor Feasibility & Concept Design 12/31/2024 12/31/2024
East Fork Hood River Phase 2 Final Design Completed F: 175. East Fork Hood River Phase 2 Design - carried forward from prior agreement 12/31/2024
East Fork Hood River Phase 3 Design Completed G: 175. East Fork Hood River Phase 3 Design - carried forward from prior agreement 12/31/2024
Designs produced H: 175. Neal Creek: Phase 3 Habitat and Floodplain Improvement Design - carried forward from prior agreements 07/01/2024 06/30/2024
Construction Management Complete I: 100. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Construction Management 10/31/2024 10/31/2024
Aquatic and floodplain complexity actions completed J: 29. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Install LWD 11/30/2024 11/30/2024
Completed channel construction K: 30. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Realign main channel and connect side channels 11/30/2024 11/30/2024
Floodplain enhanced L: 180. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Reconnect and enhance floodplain 11/30/2024 11/30/2024
Vegetation enhanced M: 47. Neal Creek: Phase 3 Habitat and Floodplain Improvement - Plant Riparian Area 12/31/2024 12/31/2024
Final design completed N: 175. Baldwin Creek Passage, Habitat and Floodplain Improvement - Produce Design 06/30/2024 06/30/2024
Construction Management Complete O: 100. Baldwin Creek Passage, Habitat and Floodplain Improvement - Construction Management 10/31/2024 10/31/2024
Removal of fish passage barrier completed. P: 85. Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove Full Passage Barrier 10/31/2024 10/11/2024
Removal of fish passage barrier complete Q: 85. Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove Partial Passage Barrier 10/31/2024 10/31/2024
Baldwin Habitat Enhancement Completed R: 29. Baldwin Creek Passage, Habitat and Floodplain Improvement - Install LWD 10/31/2024 10/31/2024
Completed channel construction S: 30. Baldwin Creek Passage, Habitat and Floodplain Improvement - Realign main channel and connect side channels 10/31/2024 10/31/2024
Complete implementation of approved design T: 180. Baldwin Creek Passage, Habitat and Floodplain Improvement - Reconnect and enhance floodplain 10/31/2024 10/31/2024
Floodplain wetlands enhanced U: 181. Baldwin Creek Passage, Habitat and Floodplain Improvement - Reconnect and enhance floodplain wetlands 10/31/2024 10/31/2024
Plant Vegetation Completed V: 47. Baldwin Creek Passage, Habitat and Floodplain Improvement - Plant Riparian Area 12/31/2024
Invasive vegetation removal complete W: 199. Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove vegetation 12/31/2024 10/25/2024
Completed Annual Report X: 132. Prepare and submit annual progress report for work completed under the prior agreement period. 04/15/2024 04/15/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 3 instances of WE 175 Produce Design
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 47 Plant Vegetation
  • 2 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 5 instances of WE 175 Produce Design
  • 2 instances of WE 100 Construction Management
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 47 Plant Vegetation
  • 2 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 5 instances of WE 175 Produce Design
  • 2 instances of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage BPA Project
B 165 Work with BPA on Environmental Compliance requirements.
C 191 Coordinate activities with CTWS and project partners
D 186 Post-Project Inspection and Monitoring 01/01/2024
E 175 Powerdale Corridor Feasibility & Concept Design 01/01/2024
F 175 East Fork Hood River Phase 2 Design - carried forward from prior agreement 01/01/2024
G 175 East Fork Hood River Phase 3 Design - carried forward from prior agreement 01/01/2024
H 175 Neal Creek: Phase 3 Habitat and Floodplain Improvement Design - carried forward from prior agreements 01/01/2024
I 100 Neal Creek: Phase 3 Habitat and Floodplain Improvement - Construction Management
J 29 Neal Creek: Phase 3 Habitat and Floodplain Improvement - Install LWD 07/15/2024
K 30 Neal Creek: Phase 3 Habitat and Floodplain Improvement - Realign main channel and connect side channels 07/15/2024
L 180 Neal Creek: Phase 3 Habitat and Floodplain Improvement - Reconnect and enhance floodplain 07/15/2024
M 47 Neal Creek: Phase 3 Habitat and Floodplain Improvement - Plant Riparian Area 07/15/2024
N 175 Baldwin Creek Passage, Habitat and Floodplain Improvement - Produce Design 01/01/2024
O 100 Baldwin Creek Passage, Habitat and Floodplain Improvement - Construction Management
P 85 Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove Full Passage Barrier 07/15/2024
Q 85 Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove Partial Passage Barrier 07/15/2024
R 29 Baldwin Creek Passage, Habitat and Floodplain Improvement - Install LWD 07/15/2024
S 30 Baldwin Creek Passage, Habitat and Floodplain Improvement - Realign main channel and connect side channels 07/15/2024
T 180 Baldwin Creek Passage, Habitat and Floodplain Improvement - Reconnect and enhance floodplain 07/15/2024
U 181 Baldwin Creek Passage, Habitat and Floodplain Improvement - Reconnect and enhance floodplain wetlands 07/15/2024
V 47 Baldwin Creek Passage, Habitat and Floodplain Improvement - Plant Riparian Area 07/15/2024
W 199 Baldwin Creek Passage, Habitat and Floodplain Improvement - Remove vegetation 07/15/2024
X 132 Prepare and submit annual progress report for work completed under the prior agreement period.
Y 185 Periodic Status Reports for BPA