View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Mountain Snake | Clearwater | 100.00% |
|
Description: Page: 6 Figure 1: Location of Analysis Area (shaded yellow). Nez Perce Tribe Treaty Territory is shaded green Project(s): 2002-074-00 Document: P103843 Dimensions: 250 x 332 Description: Page: 6 Figure 2: The major watersheds of the Analysis Area. Project(s): 2002-074-00 Document: P103843 Dimensions: 850 x 1100 Description: Page: 7 Figure 3: Collecting weed data on the GPS/Pocket PCs. Project(s): 2002-074-00 Document: P103843 Dimensions: 407 x 541 Description: Page: 10 Figure 4: This is an example of the kind of road problem identified as a risk factor in road failure. Project(s): 2002-074-00 Document: P103843 Dimensions: 949 x 709 Description: Page: 11 Figure 5: Knapweed in the project area and new invaders in project area along Hwy 12. Project(s): 2002-074-00 Document: P103843 Dimensions: 407 x 526 Description: Page: 11 Figure 6: Knapweed in the project area and new invaders in project area along Hwy 12. Project(s): 2002-074-00 Document: P103843 Dimensions: 638 x 495 |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
11900
![]() |
Nez Perce Tribe | 2002-74 CROOKED FORK CREEK TO COLT KILLED ANALYSIS AREA | History | $306,035 | 9/1/2002 - 11/30/2004 |
20732
![]() |
Nez Perce Tribe | 2002 074 00 P&R CROOKED FORK CR/COLT KILLED CR ANALYSIS AREA | History | $221,048 | 12/1/2004 - 11/30/2005 |
25362
![]() |
Nez Perce Tribe | 2002-074-00 RESTORE CROOKED FORK CR/COLT KILLED CR ANALYSIS AREA | History | $221,048 | 12/1/2005 - 9/30/2007 |
30308
![]() |
Nez Perce Tribe | 2002 074 00 CROOKED FORK TO COLT KILLED WATERSHED RESTORATION | History | $884 | 12/1/2006 - 11/30/2007 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 3 |
Completed: | 2 |
On time: | 2 |
Status Reports | |
---|---|
Completed: | 11 |
On time: | 2 |
Avg Days Late: | 73 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
11900 | 20732, 25362, 30308 | 2002 074 00 CROOKED FORK TO COLT KILLED WATERSHED RESTORATION | Nez Perce Tribe | 09/01/2002 | 11/30/2007 | History | 11 | 33 | 0 | 0 | 19 | 52 | 63.46% | 0 |
Project Totals | 11 | 33 | 0 | 0 | 19 | 52 | 63.46% | 0 |
Assessment Number: | 2002-074-00-NPCC-20090924 |
---|---|
Project: | 2002-074-00 - Restore Crooked Fork Creek |
Review: | FY07-09 Solicitation Review |
Approved Date: | 10/23/2006 |
Recommendation: | Fund |
Comments: | 2007 Revised Budget: Proposed implementation included road removal, culvert replacement, revegetation and necessary weed treatment, and road improvement. All types of proposed work can be implemented but with reduced targets for each year. The Nez Perce Tribe, Clearwater National Forest, and the private landowner will have to meet to prioritze which suite of implementation projects can be completed in a given contract year. |
Assessment Number: | 2002-074-00-ISRP-20060831 |
---|---|
Project: | 2002-074-00 - Restore Crooked Fork Creek |
Review: | FY07-09 Solicitation Review |
Completed Date: | 8/31/2006 |
Final Round ISRP Date: | None |
Final Round ISRP Rating: | Meets Scientific Review Criteria |
Final Round ISRP Comment: | |
This comprehensive proposal clearly takes into account past ISRP advice. The proposal is clearly written and is very thorough, except for needing to complete the biological components. The proposal was a pleasure to review. The proposal contains clear multiple objectives to restore watershed functions and processes, matched to subbasin plan objectives with high priorities (tabulated), etc. Relationship to other projects is not given in as much detail as might be expected. There could be overlap among these several Clearwater projects. (This is not necessarily a bad thing, but how they all fit together should be better explained.)
Monitoring is factored into the objectives, except that the biological M&E is missing. A biologist is needed on the team. The project history is adequate for the short time project has existed (as a 2002 designation). However, it is stated in the facilities and equipment section that "This project has been on-going since 1996 with the cooperation of the Clearwater National Forest." If so, greater explanation of physical and biological results should appear in the history section. For full ISRP comments on "protect and restore" type projects, please see heading "General comments concerning Nez Perce Tribe proposals to protect and restore various watersheds" at the beginning of the ISRP comments on project # 199607702, Protect & Restore Lolo Creek Watershed. |
|
Documentation Links: |
|
Assessment Number: | 2002-074-00-INLIEU-20090521 |
---|---|
Project Number: | 2002-074-00 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 10/6/2006 |
In Lieu Rating: | Problems May Exist |
Cost Share Rating: | 3 - Does not appear reasonable |
Comment: | Road decommissioning and culverts; appears to be mostly on Clearwater NF; confirm that BPA-FS MOU covers this, and the can be a "1"; otherwise, it would be 2.2 if can confirm that screening or other criteria in place to ensure that specific activities not already required of another entity. |
Assessment Number: | 2002-074-00-CAPITAL-20090618 |
---|---|
Project Number: | 2002-074-00 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 2/27/2007 |
Capital Rating: | Does Not Qualify for Capital Funding |
Capital Asset Category: | None |
Comment: | None |
Project Relationships: |
This project Merged To 2007-395-00 effective on 7/2/2007
Relationship Description: All work & budgets from projects 1996-077-03, 2002-074-00 and 2007-255-00. This new combined effort will follow the ISRPs recommendations of integrated weed control and management. |
---|
Name | Role | Organization |
---|---|---|
Rebecca Lloyd (Inactive) | Project Lead | Nez Perce Tribe |
David Kaplowe | Project Manager | Bonneville Power Administration |
Jeremi Syron (Inactive) | Project Lead | Nez Perce Tribe |
David Byrnes (Inactive) | Supervisor | Bonneville Power Administration |