View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Basinwide | - | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
41072 SOW | Idaho Governor's Office of Species Conservation | 2008-600-00 EXP IDAHO OSC ACCORD PLANNING AND DEVELOPMENT | History | $141,003 | 12/1/2008 - 10/31/2010 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 1 |
Completed: | 1 |
On time: | 1 |
Status Reports | |
---|---|
Completed: | 8 |
On time: | 1 |
Avg Days Late: | 49 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
41072 | 2008-600-00 EXP IDAHO OSC ACCORD PLANNING AND DEVELOPMENT | Idaho Governor's Office of Species Conservation | 12/01/2008 | 10/31/2010 | History | 8 | 12 | 0 | 0 | 5 | 17 | 70.59% | 8 | |
Project Totals | 8 | 12 | 0 | 0 | 5 | 17 | 70.59% | 8 |
Name | Role | Organization |
---|---|---|
Gregory Baesler (Inactive) | Project Manager | Bonneville Power Administration |
Mike Edmondson | Project Lead | Idaho Governor's Office of Species Conservation |
Paul Krueger (Inactive) | Supervisor | Bonneville Power Administration |