Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
RSS Feed for updates to Project 2012-011-00 - Tributary Habitat RM&E BiOp Remand Support Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 2012-011-00 - Tributary Habitat RM&E BiOp Remand Support
Project Number:
2012-011-00
Title:
Tributary Habitat RM&E BiOp Remand Support
Summary:
Under this Project the Northwest Fisheries Science Center, Watershed Program is to provide technical services to support evaluation of BPA's tributary habitat program. This work will include, but is not limited to:

1. Developing a short-term plan to implement the Tetratech/Washington State Salmon Recovery Funding Board approach to tributary habitat action effectiveness monitoring.
2. Developing a future vision for a reasonable and robust programmatic approach for effectiveness monitoring of tributary habitat improvement projects
3. Reviewing retrospective/existing data from Tributary Habitat RM&E programs and identifying potential reporting & analysis uses of that data
4. Preparing a roll up of tributary habitat RM&E results
5. Provide assistance at various Expert Panel workshops by sharing best available science of fish restoration strategies and techniques
6. Other technical support tasks as appropriate (document review, comments, etc.)
Proposer:
Proponent Orgs:
National Oceanic and Atmospheric Administration (Govt - Federal)
Starting FY:
2012
Ending FY:
2016
BPA PM:
Stage:
Area:
Province Subbasin %
Basinwide - 100.00%
Purpose:
Habitat
Emphasis:
RM and E
Focal Species:
Chinook - All Populations
Cutthroat Trout, Westslope
Steelhead - All Populations
Trout, Brook
Trout, Bull
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Special:
Project is BPA Internal Program Support
BiOp Association:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2025
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
There are no cost share summaries to display from previous years.

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
46273 REL 47 SOW National Oceanic and Atmospheric Administration 2012-011-00 EXP TRIBUTARY HABITAT RM&E BIOP REPORTING Closed $373,827 7/1/2012 - 4/30/2014
46273 REL 85 SOW National Oceanic and Atmospheric Administration 2012-011-00 EXP TRIB HABITAT RM&E BIOP REMAND SUPPORT Closed $229,716 5/1/2014 - 3/31/2015
46273 REL 98 SOW National Oceanic and Atmospheric Administration 2012-011-00 EXP TRIB HABITAT RM&E BIOP REMAND SUPPORT Closed $151,177 4/1/2015 - 12/31/2015



Annual Progress Reports
Expected (since FY2004):1
Completed:1
On time:1
Status Reports
Completed:15
On time:5
Avg Days Late:3

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
46273 REL 47 46273 REL 85, 46273 REL 98 2012-011-00 EXP TRIB HABITAT RM&E BIOP REMAND SUPPORT National Oceanic and Atmospheric Administration 07/01/2012 12/31/2015 Closed 15 17 0 0 0 17 100.00% 3
Project Totals 15 17 0 0 0 17 100.00% 3


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

No assessments are available for this project.
Project Relationships: This project Merged To 2016-001-00 effective on 10/1/2015
Relationship Description: 2016-001-00 is merged from 2011-008-00 and 2012-011-00.


Name Role Organization
David Kaplowe Project Manager Bonneville Power Administration
George Pess Project Lead National Oceanic and Atmospheric Administration