This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $43,173 | $43,115 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 12/1/2014 | 1/31/2015 | Concluded | Nick Bouwes (Inactive) | 10/24/2014 11:30:47 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Conduct marking/PIT tagging | 12/1/2014 | 11/30/2015 | Concluded | Nick Bouwes (Inactive) | 10/28/2014 3:34:22 PM | |
Description: Mark/PIT tag a sample of juveniles collected during seining surveys described in WE 157C. | |||||||
C | DELIV | Mark/Tag salmonids captured in Bridge Creek seining surveys | 11/30/2015 | Concluded | Nick Bouwes (Inactive) | 10/28/2014 3:34:22 PM | |
Description: This work element will be considered complete when the ELR conducts quality assurance and quality control activities and uploads PIT tag codes and accompanying biological information (e.g., length, weight, and life history stage) for sampled fish into regional databases (i.e., PTAGIS) and the ISEMP automated template modules for transfer to the ISEMP status and effectiveness monitoring database as described under WE 157B. All reports and data are due no later than 31/01/2016. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1464. Primary R, M, and E Focal Strategy [Population Status, Hydrosystem, Tributary Habitat, Estuary/Ocean, Harvest, Hatchery, Predation, Multiple Strategies] | Tributary Habitat | Tributary Habitat | |||
1472. Primary R, M, and E Type [Status and Trend Monitoring, Action Effectiveness Research, Uncertainties Research, Project Implementation/ Compliance Monitoring] | Action Effectiveness Monitoring | Action Effectiveness Monitoring | |||
1478. Secondary R, M, and E Type [Status and Trend Monitoring, Action Effectiveness Research, Uncertainties Research, Project Implementation/ Compliance Monitoring] | Status and Trend Monitoring | Status and Trend Monitoring | |||
1495. Secondary R, M, and E Focal Strategy [Population Status, Hydrosystem, Tributary Habitat, Estuary/Ocean, Harvest, Hatchery, Predation, Multiple Strategies] | Population Status | Population Status | |||
1795. # fish tagged with PIT | 7800 | 9357 |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
77870 | 44.592241 | -120.208512 | Oregon | Wheeler | Columbia Plateau | John Day |