This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 69146 (04/15/2015 - 06/30/2016) | $0 | $0 | covered under WE D | |
Work Element Budget (Current Performance Period) | $0 | $0 | covered under WE D |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | RPA.1 | Download RPA questions from cbfish.org | 12/1/2015 | 12/1/2015 | Concluded | Joseph Connor (Inactive) | 11/2/2015 10:36:51 AM |
Description: To prepare for your RPA report, 1) Go to www.cbfish.org and log in, 2) Navigate to your project and select "BiOp Annual Report" from the menu on the left, 3) Click on "Input Needed" for each applicable RPA to find your RPA reporting requirements so you will know how much time to set aside for this task. You may also click the “download RPA doc” button to get all RPA questions in one MS Word document. 4) Use “Request Review” link to email COTR or BPA RM&E RPA lead to request help or for review of draft content. For further guidance, see: https://www.cbfish.org/Content/tutorials/Reporting_Guidance_BiOp_2013.pdf (Milestone start/end: July 1 – September 30) | |||||||
B | RPA.2 | Draft calendar year report in cbfish.org | 12/1/2015 | 4/1/2016 | Concluded | Pamela Nelle | 11/2/2015 10:36:51 AM |
Description: For guidance on completing your report, see: https://www.cbfish.org/Content/tutorials/Reporting_Guidance_BiOp_2013.pdf. If you have questions or would like BPA to review your draft, you may email RMEsupport@bpa.gov and your COTR to send them your working draft in Word or notify them to review in cbfish.org by using the “Request Review” email icon link to e-mail your COTR & BPA RM&E RPA lead. (Milestone start/end: September 30 - February 28) | |||||||
C | RPA.3 | Finalize calendar year report in cbfish.org and click Publish by March 15 | 12/1/2015 | 3/15/2016 | Concluded | Pamela Nelle | 11/2/2015 10:36:51 AM |
Description: The final version is due by March 15. (Milestone start/end: December 31 - March 15) | |||||||
D | DELIV | Submit BiOp RPA Report in Taurus | 3/15/2016 | Concluded | Pamela Nelle | 11/2/2015 10:36:51 AM | |
Description: Note: Information generated by the running of the rotary screw trap will be reported at a programmatic level by ISEMP under Terraqua's contract CR82434. The online BiOp RPA report in Taurus (https://www.cbfish.org/BiologicalOpinionAction.mvc/Index/2014/BiOpRpaStatus) should include the data, analyses, and data management completed no later than December 31st. Any activity after the last day of the Calendar Year should be included in a subsequent BiOp report. For example, if you have completed redd surveys, but have not completed the scale analyses, you will report the preliminary data (# of redds), but not (incomplete) age distributions of carcasses, which would be reported in the subsequent CY report. For each RPA, follow the directions in Taurus for each of the three sections and, input completed graphical or tabular data, accompanied by any complete explanatory text. These are cumulative summary reports and should show relevant results for the life of your project. Each year, note trends and whether they are changing from one year (or groups of years) to the next. |