SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $17,408 | $17,407 | no changes |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Evaluate the reading efficiency with spring chinook salmon | 4/15/2006 | 6/1/2006 | Concluded | 12/6/2005 7:02:51 AM | ||
Description: We will evaluate the reading efficiency of the counting-window interrogation system using inriver tagged spring chinook salmon. | |||||||
B | Evaluate the reading efficiency with summer chinook salmon | 6/1/2006 | 8/1/2006 | Concluded | 12/6/2005 7:02:51 AM | ||
Description: We will evaluate the reading efficiency of the counting-window interrogation system using inriver tagged summer chinook salmon. | |||||||
C | Evaluate the reading efficiency with fall chinook salmon | 8/1/2006 | 9/30/2006 | Concluded | 12/6/2005 7:02:51 AM | ||
Description: We will evaluate the reading efficiency of the counting-window interrogation system using inriver tagged fall chinook salmon. | |||||||
D | Evaluate the reading efficiency with coho salmon | 8/15/2006 | 9/30/2006 | Concluded | 12/6/2005 7:02:51 AM | ||
Description: We will evaluate the reading efficiency of the counting-window interrogation system using inriver tagged coho salmon. | |||||||
E | Evaluate the reading efficiency with steelhead | 4/15/2006 | 9/30/2006 | Concluded | 12/6/2005 7:02:51 AM | ||
Description: We will evaluate the reading efficiency of the counting-window interrogation system using inriver tagged steelhead. | |||||||
F | DELIV | Report summarizing the reading-efficiency analysis | 12/1/2006 | Concluded | Sandra Downing | 2/27/2006 1:03:20 PM | |
Description: Report summarizing the analyses of how well the counting-window interrogation system installed into the Washington Fish Ladder at McNary Dam detected tagged fish from different salmonid populations. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1468. # of draft scientific reports submitted | 1 | part of final report | draft reports submitted | ||
1469. # of draft manuscripts and draft final reports of research findings submitted for publication | 0 | draft reports submitted |