This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $8,116 | $8,116 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 3/1/2016 | 3/1/2016 | Concluded | Andrew Murdoch | 11/4/2015 1:17:57 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | PIT tag all spring Chinook captured and released upstream of Tumwater Dam | 6/1/2016 | 7/31/2016 | Concluded | Maureen Kavanagh | 11/9/2015 11:26:47 AM | |
Description: PIT tag all spring Chinook captured and released upstream of Tumwater Dam. Adult fish will be tagged in the dorsal sinus cavity and precocious fish will be tagged in the body cavity. | |||||||
C | Submit PIT tag information to PTAGIS | 6/1/2016 | 7/31/2016 | Concluded | Maureen Kavanagh | 11/9/2015 11:26:58 AM | |
Description: Successfully upload tagging files to the PTAGIS database within 14 days of tagging. | |||||||
D | OrderTags | Order PIT tags in TDI system | 11/1/2016 | 11/1/2016 | Concluded | Andrew Murdoch | 11/4/2015 1:25:53 PM |
Description: Submit tag request in the Tag Distribution and Inventory application (TDI) at http://www.ptagis.org/services/tag-distribution-inventory indicating when the tags are needed (one or multiple shipments). Tag orders should be placed during September and October for shipment any time during the fiscal year. Funding for the tags occurs at the project level. | |||||||
E | DELIV | PIT Tag Spring Chinook | 11/1/2016 | Concluded | Andrew Murdoch | 11/4/2015 1:25:53 PM | |
Description: 3000 PIT tagged spring Chinook in the Wenatchee River; PIT tag information submitted to PTAGIS Planned Metrics: RM&E Focal Area - Hatcheries Primary RM&E Type - Uncertainties |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1464. Primary R, M, and E Focal Strategy [Population Status, Hydrosystem, Tributary Habitat, Estuary/Ocean, Harvest, Hatchery, Predation, Multiple Strategies] | Hatchery | Hatchery | |||
1472. Primary R, M, and E Type [Status and Trend Monitoring, Action Effectiveness Research, Uncertainties Research, Project Implementation/ Compliance Monitoring] | Uncertainty Research | Uncertainty Research | |||
1795. # fish tagged with PIT | 3000 | 1244 |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
39943 | 47.616318 | -120.723267 | Washington | Chelan | Columbia Cascade | Wenatchee |