This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $250 | $250 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | LAMP | Determine if contract work could adversely affect Pacific lamprey | 12/1/2017 | 1/30/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM |
Description: Contractor will review work proposed under this contract and determine the following: 1) Will field work take place in any area where lamprey may be present? (Any tributary or subbasin where anadromous fish exist is also accessible Pacific lamprey habitat.) 2) Are there any stream disturbing activities or instream activities that could adversely impact Pacific lamprey? Examples of activities posing a threat to lamprey may include (this list is not intended to be all-inclusive): aquatic habitat improvements, fish passage improvements, culvert replacements, water diversions, altered management of water flows, dewatering of any portions of streams, or alteration of irrigation practices. If the answer is yes to BOTH 1 and 2, the contractor must implement USFWS Best Management Practices to Minimize Adverse Effects to Pacific Lamprey (Entosphenus tridentatus) http://www.fws.gov/pacific/Fisheries/sphabcon/lamprey/pdf/Best%20Management%20Practices%20for%20Pacific%20Lamprey%20April%202010%20Version.pdf (BMPs). | |||||||
B | ESA | Report lamprey observation and catch data to USFWS by Feb. 15 | 12/1/2017 | 11/30/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM |
Description: All contractors doing instream work (e.g., surveys, habitat improvements, electrofishing, screwtraps, etc.) in anadromous fish areas are required to annually report lamprey observations or catch, including zero, by Feb 15 for the previous calendar year’s work. A data template is available at: (https://www.cbfish.org/EfwDocument.mvc/DownloadFile/11) As per instructions on the form, email your data to christina_wang@fws.gov at US Fish and Wildlife Service and CC your COTR. For identification of lamprey life stages see page 10 of USFWS Best Management Practices to Minimize Adverse Effects to Pacific Lamprey (Entosphenus tridentatus) http://www.fws.gov/pacific/Fisheries/sphabcon/lamprey/pdf/Best%20Management%20Practices%20for%20Pacific%20Lamprey%20April%202010%20Version.pdf. | |||||||
C | ANS | Inspect water craft, waders, boots, etc. to be used in or near water for aquatic invasive species | 12/1/2017 | 11/30/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM |
Description: Aquatic invasive Species Guidance: Uniform Decontamination Procedures: http://www.aquaticnuisance.org/wordpress/wp-content/uploads/2009/01/Recommended-Protocols-and-Standards-for-Watercraft-Interception-Programs-for-Dreissenid-Mussels-in-the-Western-United-States-September-8.pdf -- Best management guidance for boaters: http://www.westernais.org -- Aquatic Nuisance Species newsletter: http://www.aquaticnuisance.org/newsletters -- State Aquatic Invasive Species Management Plans: Oregon: http://www.aquaticnuisance.org/wordpress/wp-content/uploads/2009/01/Recommended-Protocols-and-Standards-for-Watercraft-Interception-Programs-for-Dreissenid-Mussels-in-the-Western-United-States-September-8.pdf -- Washington: http://www.wdfw.wa.gov/publications/pub.php?id=00105 -- Montana: http://www.anstaskforce.gov/Montana-FINAL_PLAN.pdf -- Idaho: http://www.anstaskforce.gov/stateplans.php | |||||||
D | NOXIOUS | Inspect and, if necessary, wash vehicles and equipment infested with terrestrial invasive species | 12/1/2017 | 11/30/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM |
Description: Prevent spread of invasive species | |||||||
E | 106 | Plan for field inventory | 12/1/2017 | 11/30/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM |
Description: Coordinate with EC Lead and BPA archaeologist to determine appropriate approach and methodology for field inventory, if determined necessary by BPA archaeologist. | |||||||
F | PERMS | Obtain/Renew applicable local, state, federal and tribal environmental permits | 12/1/2017 | 11/30/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM |
Description: Work done to obtain permits such as Sec. 401 or 404 (including RGP process), shoreline, NPDES, or any other required federal, state, or local permits. | |||||||
G | Compile and provide annual ESA take reports to NOAA | 12/1/2017 | 4/1/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM | |
Description: Compile annual take report for NOAA: summarize all ESA takes per the project year, and provide to NOAA Fisheries in a Annual ESA Take Report; upload the document to Pisces, and forward link to the BPA EC-lead. | |||||||
H | Work with KEC to complete NEPA/ESA/other environmental compliance work | 12/1/2017 | 2/28/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM | |
Description: Consult with BPA's Environmental Compliance Group (KEC) Environmental Compliance (EC) lead and determine whether project work requires environmental or cultural resource compliance. Arrange for compliance activities in support of project/contract actions, through applicable programmatic agreements and/or the completion of cultural, hazardous materials, and ESA species surveys, or other documentation. Work with BPA's EC-Lead to make sure all requirements are met; and obtain clearance from the KEC EC-Lead that environmental compliance requirements and clearances are complete for contract-period work. | |||||||
I | DELIV | Timely and successful compliance documentation and clearance | 10/30/2018 | Concluded | Russell Scranton | 11/7/2017 3:29:22 PM | |
Description: Provide environmental compliance assistance and documentation to BPA's Environmental Planning and Analysis Group (KEC). Submit needed information as requested by BPA EC lead, including the information to facilitate NEPA and ESA clearances, or to support a categorical exclusion, for data collection activities. Provide ESA take reports to NOAA Fisheries (and copy BPA) through the 4(d) permit, or LSRCP hatchery evaluation project (when the HGMP is approved); consult with NOAA and BPA as needed. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1479. Are herbicides used as part of work performed under this contract? | No | No | |||
1722. Will water craft, heavy equipment, waders, boots, or other equipment be used from outside the local watershed as part of work performed under this contract? | Yes | Yes | Best practices are followed to prevent spread of invasive species. |