SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $969 | $950 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Apply for 2007 annual fish sampling permit from Washington Department of Fish and Wildlife (WD | 12/1/2006 | 12/31/2006 | Concluded | Patrick Connolly (Inactive) | 2/27/2006 4:47:56 PM | |
Description: Apply for 2007 annual fish sampling permit from Washington Department of Fish and Wildlife (WDFW) | |||||||
B | Submit application for modifying current permit for the 2007 field season from NOAA Fisheries | 12/1/2006 | 12/28/2006 | Concluded | Patrick Connolly (Inactive) | 2/27/2006 4:47:56 PM | |
Description: If needed, submit application for modifying current permit for the 2007 field season from NOAA Fisheries. | |||||||
C | Submit a fish collection report to WDFW | 12/1/2006 | 1/31/2007 | Concluded | Patrick Connolly (Inactive) | 2/27/2006 4:47:56 PM | |
Description: Entails providing detailed account of all fish sampled. | |||||||
D | Submit a fish collection report to NOAA Fisheries | 12/1/2006 | 1/31/2007 | Concluded | Patrick Connolly (Inactive) | 2/27/2006 4:47:56 PM | |
Description: Entails providing detailed account of all ESA-listed fish sampled. | |||||||
E | Permit obtained from WDFW | 1/1/2007 | 2/28/2007 | Concluded | Patrick Connolly (Inactive) | 2/27/2006 4:47:57 PM | |
Description: Any later than this would potentially hamper our sampling efforts for the following field season. | |||||||
F | Report any deviations from permit restrictions or unexpected problems | 4/1/2006 | 3/30/2007 | Concluded | Patrick Connolly (Inactive) | 2/27/2006 4:47:57 PM | |
Description: Report any deviations from permit restrictions or unexpected problems to permitting agencies promptly and on a as needed basis throughout the sampling season. Corrective actions will be taken on a as needed basis. If interferes with achieving other milestones, BPA will be notified. | |||||||
G | DELIV | ALL EC compliance completed | 3/30/2007 | Concluded | John Baugher (Inactive) | 3/14/2006 11:11:16 AM | |
Description: State permit obtained and two collection reports submitted 1/31/2006 No sampling can be done until permits are obtained. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|