Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
Select a work element:
Contract Number:
Contract Title:
2008-603-00 EXP PAHSIMEROI RIVER HABITAT
Contract Start Date:
5/1/2021
Contract End Date:
4/30/2022
Title:
G: 175 - Produce design for in-stream habitat restoration on Muddy Springs
Description:
The area of interest is Muddy Springs Creek, which is a tributary to the Pahsimeroi River. This was one of the four systems re-connected after the P-9 project. This project reach of Muddy Springs within the Hayes property is approximately 10,000 feet of meandering stream. The lower reach was de-watered through most of the year for many years and was reconnected as a part of the P-9 Project in approximately 2015. Much of the stream has recovered on it's own but additional in-stream structure and vegetative plantings could increase it's viability for all species of fish (including juvenile rearing Snake River Chinook and steelhead). This project will improve habitat forms and processes for juvenile spring Chinook salmon and summer steelhead. Juvenile salmonid habitat enhancement will be accomplished through narrowing the channel width by placement large woody debris, channel spanning logs and BDA’s along with extensive riparian planting. Intended flooding in some areas will help reduced sediment in both Muddy Springs and the Pahsimeroi. Project actions will provide overwintering and summer habitat for juvenile fish and address limiting factors for salmonid production in the Pahsimeroi River watershed, such as reduced stream complexity and degraded riparian conditions.

Under this work element engineers will be hired to develop a plan on this reach of Muddy Springs. The stream has been fully fenced and is currently a excluded from grazing. This project will likely be installed in three phases over the next three years.

Work with landowner, Engineer, IDFG and BPA to develop alternatives for Muddy Spring to improve and increase instream habitat in the two mile reach of Muddy Springs. This plan development will provide preferred alternatives for landowner and BPA to consider for funding in the following year BPA contract for implementation. It will also include options that may include alternatives that is desirable for wildlife that can be considered for other funding such as USFWS.

This work was prioritized as HIGH by The Upper Salmon Basin Watershed Tech Team and was ranked 78 (>61 is high priority).
WE Agreement Type:
Contracted
Deliverable Specification:
Complete final design of project
WSE Effective Budget:
$18,815
% of Total WSE Effective Budget:
7.19%
WSE Start:
05/01/2021
WSE End:
04/08/2022
WSE Completion:
01/20/2022
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
1. 87868 (05/01/2021 - 04/30/2022) $44,714 $18,815
Work Element Budget (Current Performance Period) $44,714 $18,815

15 Milestones
Sort Type Title Start End Status Modified By Modified Date
A EC Environmental compliance requirements complete 5/28/2021 7/1/2021 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff.
B Design1 Select design subcontractor 5/1/2021 1/14/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Ensure bid package includes technical review criteria and HIP guidance. All projects are subject to Engineering Technical Services (ETS) review. Sponsors shall follow their own procurement process, so long as there is no conflict of interest. BPA’s preferred method is Engineer/Procure/Construct (EPC) or a two-phase design build selection process. If not included in the bid package, then the construction oversight shall be bid in accordance with the sponsor’s procurement process. Final design budget shall be provided to the COR once a design subcontractor is selected and the line item budget updated as necessary.
C Design2 Contact EC lead to determine compliance strategy 5/1/2021 12/31/2021 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Contact EC Lead to determine compliance strategy and EC review requirements.
D Suggested Provide projected construction start date to BPA COR and EC 2/1/2022 2/26/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Provide month and year of projected construction start date to assist in project planning, environmental compliance, planning and design review timelines. Provide during conceptual design stage and no later than 15% design. Include in WE description if possible.
E Design3 Develop and submit project concepts (typically 15% design) for review 6/12/2021 2/25/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Develop conceptual strategy, restoration approach, and/or preliminary design. Submit conceptual design and expected construction start date to the COR and EC Lead for review. Reviews shall include COR, EC, and ETS. EC Lead to determine other reviews as needed. Allow one month for review. At 15%, coordinate with BPA to schedule a site visit to review project concepts, goals, and objectives. . A typical site visit will include review of limiting factors and pertinent studies or reports that document restoration targets for implementation. Additional data that may be presented and reviewed (e.g., high resolution aerial photography, topographic maps, soil maps, or GIS/CAD data layers).
F Design4 Develop and submit preferred alternative (typically 30%) for review 8/3/2021 4/8/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Develop preferred alternative design and cost estimate. Submit plans, draft Basis of Design Report (BDR), and other supporting documentation (profiles, details, cross sections, quantities, technical analyses/appendixes, etc.) to the COR and EC Lead. Schedule time for review (typically one month for NOAA/USFWS and BPA review). The 30% design should incorporate technical comments and recommendations from previous review and shall address design requirements provided by BPA in the BDR template.
G Design5 Determine cost estimate, permitting, construction, and M&E 8/1/2021 3/31/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: All designs shall include an engineer's construction estimate (including, but not limited to): volume of materials and cost per volume, hours and rates for each person, equipment hours and rates, delivery costs, travel and per diem costs, and supplies
H Design6 Develop and submit permit-ready designs (typically 60% to 80%) for review for phase II design. 9/30/2021 11/30/2021 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Develop and submit permit ready designs to the COR and EC Lead. Schedule time for review, typically one month for NOAA/USFWS and BPA review. Provide 80% designs for final technical, functional, and NMFS/USFWS review. The 80% design shall incorporate technical comments and recommendations from previous design reviews. 80% design submittals should include near-final drawings and specifications, site locations, site plans, profiles, cross sections, details, construction quantities, implementation resource plans, and design technical analyses as summarized in a Basis of Design Report. If technical requirements are not met, additional review may be necessary.
I Design7 Submit completed landowner agreement 2/1/2022 2/26/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Submit landowner agreement to BPA that documents acknowledgement/ approval of project. The COR can provide an agreement template.
J Design8 Cultural resource clearance obtained 9/1/2021 1/29/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: If planning or design work requires ground disturbance including but not limited to geotechnical surveys, ground water monitoring, or well exploration, obtain appropriate cultural resources consultation prior to any ground disturbance. Notify EC Lead well in advance of ground disturbing work. On-the-ground work associated with this work element may not proceed until this milestone is complete. Milestone is complete when BPA environmental compliance staff provides final documentation.
K Design10 NEPA clearance obtained 2/18/2022 3/31/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Project shall not proceed without NEPA sign-off from BPA EC Lead.
L Design11 Upload final design set 2/1/2022 3/26/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Upload final approved design plan set and basis of design to the contract documents and notify COR and EC lead when complete.
M Design12 Provide construction schedule and in-water work window 2/26/2022 3/19/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Provide schedule to BPA outlining construction schedule and in-water work windows. Should unforeseen circumstance arise, notify BPA immediately of resulting changes in schedule and cost.
N Design9 HIP coverage obtained 2/1/2022 3/31/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Complete HIP Project Notification Form and document ESA coverage in coordination with EC Lead.
O DELIV Provide design alternatives and EC documents for BPA review in order to install habitat actions in the following year contract. 3/31/2022 Concluded Timothy Ludington (Inactive) 11/3/2021 6:53:47 AM
Description: Complete final design of project

This work element does not require Metrics
Work Site ID Latitude Longitude State County Province Subbasin
101262 44.596857 -113.957156 Idaho Custer Mountain Snake Salmon

Primary Focal Species:
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened); Steelhead (O. mykiss) - Snake River DPS (Threatened)
Secondary Focal Species:
Trout, Bull (S. confluentus) (Threatened)

This work element does not require RM&E metadata