2000-015-00 EXP UPPER JOHN DAY CONSERVATION LANDS PROGRAM
Contract Start Date:
4/1/2021
Contract End Date:
3/31/2022
Title:
O: 115 - O&M - Irrigation Monitoring on properties
Description:
Pasture irrigation use will be monitored for duration of use and amount of flow. Irrigation on Oxbow is typically from April until July 1. After July, the project stops irrigating voluntarily to reduce impacts to fish populations. Forrest irrigation is season-long as permitted by the management plan but is also curtailed during low flows. There is no irrigation on Dunstan. This work is in accordance with the management plan objectives.
WE Agreement Type:
Contracted
Deliverable Specification:
Share irrigation use data in annual report.
WSE Effective Budget:
$5,000
% of Total WSE Effective Budget:
0.66%
WSE Start:
04/01/2021
WSE End:
03/31/2022
WSE Completion:
03/31/2022
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $5,000 $5,000

3 Milestones
Sort Type Title Start End Status Modified By Modified Date
A EC Environmental compliance requirements complete 4/1/2021 6/1/2021 Concluded Timothy Ludington (Inactive) 12/14/2020 3:23:49 PM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff.
B Irrigation monitoring 4/1/2021 9/30/2021 Concluded Timothy Ludington (Inactive) 12/15/2020 12:49:23 PM
Description: Flood irrigation activities will be monitored to ensure adequate stream flows are maintained for fish. Flumes, staff gauges, and staff logger recordings will be monitored. Details will be put into the Annual Progress Report. Details include which water rights were used, how long were they used, and use amounts. Irrigation season is April 1 to September 30, but WE will extend an additional month to compile data.
C DELIV Irrigation use data 3/31/2022 Concluded Timothy Ludington (Inactive) 12/15/2020 12:49:34 PM
Description: Share irrigation use data in annual report.

This work element does not require Metrics
Work Site ID Latitude Longitude State County Province Subbasin
36828 44.459559 -118.696581 Oregon Grant Columbia Plateau John Day
36829 44.452974 -118.674972 Oregon Grant Columbia Plateau John Day
36830 44.457504 -118.681055 Oregon Grant Columbia Plateau John Day
36831 44.457393 -118.68164 Oregon Grant Columbia Plateau John Day
89579 44.656077 -118.646936 Oregon Grant Columbia Plateau John Day
89583 44.651009 -118.650541 Oregon Grant Columbia Plateau John Day
89587 44.650154 -118.652687 Oregon Grant Columbia Plateau John Day
89591 44.645941 -118.65376 Oregon Grant Columbia Plateau John Day
89595 44.645636 -118.668523 Oregon Grant Columbia Plateau John Day
105365 44.61039 -118.542051 Oregon Grant Columbia Plateau John Day
105366 44.596213 -118.532267 Oregon Grant Columbia Plateau John Day

Primary Focal Species:
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU; Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened); Lamprey, Pacific (Entosphenus tridentata); Trout, Bull (S. confluentus) (Threatened); Trout, Interior Redband (O. mykiss gairdnerii)
Secondary Focal Species:
Wildlife - Various

This work element does not require RM&E metadata