This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $14,253 | $14,253 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 7/1/2021 | 6/30/2022 | Concluded | Cecilia Brown (Inactive) | 2/18/2021 9:02:03 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff. | |||||||
B | Meet with BPA EC lead to explain project implementation timing and EC compliance | 7/1/2021 | 8/31/2021 | Concluded | Cecilia Brown (Inactive) | 5/13/2021 5:09:16 PM | |
Description: Implementation of this project is planned for late summer 2022, which means that the EC work must be completed during this contract performance period. FWP biologists and BPA EC lead will meet to discuss the time lines for EC completion in order to facilitate the proposed project timing. | |||||||
C | Determine donor stock for the project | 7/1/2021 | 2/26/2022 | Concluded | Cecilia Brown (Inactive) | 5/13/2021 5:09:16 PM | |
Description: Rainbow Lake will likely be treated with piscicide in 2021 to remove non-native fish to prevent downstream hybridization with Westslope Cutthroat Trout. The lake will need to be restocked after piscicide treatment. The work identified in this milestone will identify the donor stock. Options include using a locally adapted stock or using the state-wide M012 conservation stock. Genetic samples were collected in 2019 to evaluate the suitability of several local stocks. The results are currently at the laboratory. The results will be used in the decision. | |||||||
D | Identify implementation timing for non-native fish removal using rotenone. | 7/1/2021 | 11/30/2021 | Concluded | Cecilia Brown (Inactive) | 5/13/2021 5:09:16 PM | |
Description: The non-native fish in Rainbow Lake will be removed using rotenone. This milestone will determine the implementation timing for that work. Timing will be determined by ESA considerations if any, other project activities, and availability of FWP aircraft required for this work. | |||||||
E | write plan | 7/1/2021 | 3/31/2022 | Concluded | Cecilia Brown (Inactive) | 5/13/2021 5:09:16 PM | |
Description: Draft Environmental Assessment completed to fulfill NEPA and/or MEPA requirements. | |||||||
F | DELIV | NEPA/MEPA document | 6/30/2022 | Concluded | Cecilia Brown (Inactive) | 5/13/2021 5:09:16 PM | |
Description: Draft NEPA/MEPA document prepared for agency review and public scoping. Document will potentially include Biological Assessment for ESA analysis. |