SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $8,000 | $8,000 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 5/1/2021 | 4/18/2022 | Concluded | Jennifer Lord | 4/7/2021 8:28:48 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff. | |||||||
B | Design2 | Contact EC lead to determine compliance strategy | 5/1/2021 | 4/18/2022 | Concluded | Jennifer Lord | 4/7/2021 8:27:51 AM |
Description: Contact EC Lead to determine compliance strategy and EC review requirements. | |||||||
C | Suggested | Provide projected construction start date to BPA COR and EC | 5/1/2021 | 4/18/2022 | Concluded | Jennifer Lord | 4/14/2021 12:49:24 PM |
Description: Provide month and year of projected construction start date to assist in project planning, environmental compliance, planning. Include in WE description if possible. | |||||||
D | CostEst | Determine cost estimate, including cultural surveys, permitting, construction, and M&E | 1/1/2022 | 3/10/2022 | Concluded | Jennifer Lord | 4/16/2021 5:16:35 PM |
Description: All designs must include an engineer's construction estimate (including, but not limited to): volume of materials and cost per volume, hours and rates for each person, equipment hours and rates, delivery costs, travel and per diem costs, supplies, etc. (generally, no lump sums except mobilization). Estimates may NOT include contingency funds. Estimates should be of sufficient detail to be used as documentation for BPA budget requests. | |||||||
E | Design9 | HIP coverage obtained | 5/1/2021 | 4/18/2022 | Concluded | Jennifer Lord | 4/16/2021 5:16:35 PM |
Description: Complete HIP Project Notification Form and document ESA coverage in coordination with EC Lead. | |||||||
F | Design6 | Internal review of 60-80% water development design package. | 3/1/2022 | 4/28/2022 | Concluded | Jennifer Lord | 4/16/2021 5:18:11 PM |
Description: Internal review of design package and review USDA-Natural Resources Conservation Service specification number 614, 574 and 516. Earlier design iterations (15%, 30%) have been done internally and in collaboration with NRCS. Ensure design meets specifications and drawings are consistent with field conditions. Review is typically with landowner, NRCS engineer, and NPSWCD technician. | |||||||
G | Design11 | Upload final design set | 3/1/2022 | 4/28/2022 | Concluded | Jennifer Lord | 4/16/2021 5:16:35 PM |
Description: Upload final approved design plan set and notify COR and EC lead when complete. | |||||||
H | DELIV | Design package for 2 livestock water systems | 4/30/2022 | Concluded | Jennifer Lord | 4/16/2021 5:16:35 PM | |
Description: Prepare engineering and technical designs for livestock water developments that will be implemented during subsequent contracts in 2022 to 2023. Design packages includes surveys, engineering or technical drawings, site maps, construction or installation specifications, material specifications, and cost estimates. |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
107140 | 46.175525 | -116.662503 | Idaho | Lewis | Mountain Snake | Clearwater |