This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $2,500 | $2,500 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 3/1/2023 | 6/1/2023 | Concluded | Jennifer Lord | 9/16/2022 4:37:42 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff. | |||||||
B | Suggested | Provide projected construction start date to BPA COR and EC | 4/1/2023 | 4/30/2023 | Concluded | Jennifer Lord | 9/16/2022 4:37:42 PM |
Description: Provide month and year of projected construction start date to assist in project planning, environmental compliance, planning and design review timelines. Provide during conceptual design stage and no later than 15% design. Include in WE description if possible. | |||||||
C | Assure that landowner intentions and constraints are addressed; obtain permissions and agreement to proceed | 4/1/2023 | 5/31/2023 | Concluded | Jennifer Lord | 9/16/2022 4:37:42 PM | |
Description: Reaffirm landowner needs and interests; address implementation constraints and concerns via ongoing design review and evaluation; confirm participation and obtain permission to proceed. | |||||||
D | Finalize and upload permit-ready designs (typically 60% to 80%) for review | 1/2/2023 | 5/31/2023 | Concluded | Jennifer Lord | 12/8/2022 4:34:07 PM | |
Description: Note: design work products were initiated and advanced to an intermediate design stage (60-80%), within BPA contract funds provided to the CCD for the Tucannon Watershed: #89883 (FY22). Design development continues in the FY23 District contract (CR-360602). Develop and submit permit ready designs to the COR and EC Lead. Schedule time for review, typically one month for NOAA/USFWS and BPA review. If technical requirements are not met, additional review may be necessary. Provide 80% designs for final technical, functional, and NMFS/USFWS review. The 80% design shall incorporate technical comments and recommendations from previous design reviews. 80% design submittals should include near-final drawings and specifications, site locations, site plans, profiles, cross sections, details, construction quantities, implementation resource plans, and design technical analyses as summarized in a Basis of Design Report. | |||||||
E | DELIV | Produce final construction design and site plan: Phase III/IV | 6/1/2023 | Concluded | Jennifer Lord | 12/8/2022 4:32:07 PM | |
Description: Upload (attach) to this WE in Pisces (Documents Tab): the Final Design, Report (BDR), and revised/final construction or site plan for PA-26 (Phase III-IV). Finalize restoration designs and design report advanced in the prior contract, following any late plan revisions, adjustments to review or clearance requirements, or in response to changes in channel morphology, to: (a) confirm engineering or design specifications, technical drawings, materials list, timeline or construction schedule, and budget or cost-estimates; (b) satisfy engineering design review, coordinate permitting, inform environmental compliance documentation, and plan construction details and scheduling; and (c) guide and manage the installation of the design and the construction of the project in the Tucannon Watershed at: PA-26, targeted for implementation of the Phase III-IV component of the overall project during the summer/fall of 2023-2024. |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
100393 | 46.441953 | -117.762091 | Washington | Columbia | Columbia Plateau | Tucannon |