2008-603-00 EXP PAHSIMEROI RIVER HABITAT
Contract Start Date:
5/1/2022
Contract End Date:
12/31/2023
Title:
B: 165 - Produce EC documents on identified projects
Description:
Custer SWCD will work with BPA to identify EC requirements as projects develop and to provide EC documentation. This includes cultural survey, HIP IV and permits as required by law. If needed, cultural resource surveys will be completed by a subcontractor and a detailed budget estimate will be attached to the budget spreadsheet.
WE Agreement Type:
Contracted
Deliverable Specification:
Compete all EC required compliance including but not limited to ESA consultation, Section 105 compliance and 404 permit requirements.
WSE Effective Budget:
$6,000
% of Total WSE Effective Budget:
2.35%
WSE Start:
05/01/2022
WSE End:
04/30/2023
WSE Completion:
04/30/2023
WSE Progress:
Concluded
WSE ID Continued From:
n/a
WSE ID Continued To:
n/a
Finite or Recurring:
Recurring

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
1. 90250 (05/01/2022 - 12/31/2023) $5,000 $6,000
2. Amendment 001 (05/01/2022 - 09/30/2023) $6,000 $6,000
Work Element Budget (Current Performance Period) $6,000 $6,000

10 Milestones
Sort Type Title Start End Status Modified By Modified Date
A HIPCOVER Discuss HIP ESA coverage with Bonneville EC lead 5/1/2022 10/28/2022 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: The EC Lead will determine if work under this work element may be able to have ESA-coverage (NMFS & USFWS) under the current version of the Habitat Improvement Program Biological Opinions (HIP BiOps). Work that qualifies must comply with conservation measures in the HIP Handbook. Medium to high risk projects will require a technical review by the Bonneville Engineering Technical Services. Before conceptual design commences, contact the EC lead for HIP applicability, instructions and information requirements. The HIP activity categories and risk criteria are located in the “Note” section of the work element background page here: https://www.cbfish.org/WorkElement.mvc/Summary/165
B VEG BMPS Use Best Management Practices to stabilize soils and prevent spread of noxious weeds 5/1/2022 4/30/2023 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Use applicable BMPs to retain existing vegetation and achieve re-establishment of vegetation in disturbed areas to at least 70% of pre-disturbance levels. For example, see "Shrub-Steppe and Grassland Restoration Manual For the Columbia River Basin" (http://wdfw.wa.gov/publications/01330/wdfw01330.pdf), or "Revegetation for Stream Restoration and Fish Passage Projects" (https://www.wsdot.wa.gov/publications/manuals/fulltext/M25-30/830.pdf) for guidance on re-vegetation in the Columbia River Basin.
C NOXIOUS Inspect and, if necessary, wash vehicles and equipment infested with terrestrial invasive species 5/1/2022 4/30/2023 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Prevent spread of invasive species by identifying and removing invasive species from work vehicles and equipment. Consult resources such as the Plants Database (http://plants.usda.gov/index.html) or the NatureServe Explorer (http://www.natureserve.org/explorer/) with assistance identifying invasive plants. Other resources include state natural resource offices (https://www.fws.gov/offices/statelinks.html) or a local U.S. Fish and Wildlife Service Office (https://www.fws.gov/offices/).
D ESA Participate in ESA Consultation 5/1/2022 4/30/2023 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Work may include drafting BA (or other ESA documentation), completing HIP forms, submitting high risk project designs to the EC Lead, providing copies of Section 10, 4(d), or 6 permits, etc., or submitting Hatchery Genetic Management Plan to BPA for review and ESA consultation initiation, and providing input for the ensuing consultation. Once the program has completed Section 7 consultation and has obtained relevant permits or authorizations (Section 10, 4(d), etc), be familiar with and follow all terms and conditions, including annual reporting, associated with the ESA consultation or permit. Notify BPA immediately of any instances when take has been exceeded or terms and conditions or conservation measures have been violated.
E 106 Provide information for Section 106 Cultural review 5/1/2022 8/1/2022 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Email EC Lead detailed project description, map, and shapefiles so that BPA can initiate Section 106 review.
F 106 Plan for field inventory 5/1/2022 8/31/2022 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Coordinate with EC Lead and BPA archaeologist to determine appropriate approach and methodology for field inventory, if determined necessary by BPA archaeologist.
G PERMS Obtain/Renew applicable local, state, federal and tribal environmental permits 5/1/2022 12/30/2022 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Work done to obtain permits such as Sec. 401 or 404 (including RGP process), shoreline, NPDES, or any other required federal, state, or local permits. Send copies of final permits to EC Lead as requested.
H ANS Inspect water craft, waders, boots, etc. to be used in or near water for aquatic invasive species 5/1/2022 4/30/2023 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Aquatic invasive Species Guidance: Uniform Decontamination Procedures: http://www.aquaticnuisance.org/wordpress/wp-content/uploads/2009/01/Recommended-Protocols-and-Standards-for-Watercraft-Interception-Programs-for-Dreissenid-Mussels-in-the-Western-United-States-September-8.pdf -- Best management guidance for boaters: http://www.westernais.org -- Aquatic Nuisance Species newsletter: http://www.aquaticnuisance.org/newsletters -- State Aquatic Invasive Species Management Plans: Oregon: http://www.aquaticnuisance.org/wordpress/wp-content/uploads/2009/01/Recommended-Protocols-and-Standards-for-Watercraft-Interception-Programs-for-Dreissenid-Mussels-in-the-Western-United-States-September-8.pdf -- Washington: http://www.wdfw.wa.gov/publications/pub.php?id=00105 -- Montana: http://www.anstaskforce.gov/Montana-FINAL_PLAN.pdf -- Idaho: http://www.anstaskforce.gov/stateplans.php
I 106 Cultural resource surveys 7/1/2022 1/31/2023 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Coordinate with EC Lead to schedule cultural resources surveys if required by BPA archaeologist.
J DELIV Complete all EC required compliance. 4/30/2023 Concluded Ryan Ruggiero (Inactive) 9/12/2023 7:14:28 AM
Description: Compete all EC required compliance including but not limited to ESA consultation, Section 105 compliance and 404 permit requirements.

This work element does not require Focal Species
This work element does not require Environmental Compliance
This work element does not require RM&E metadata