This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 90250 (05/01/2022 - 12/31/2023) | $12,172 | $4,535 | ||
2. Amendment 001 (05/01/2022 - 09/30/2023) | $12,172 | $4,535 | ||
Work Element Budget (Current Performance Period) | $12,172 | $4,535 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 8/1/2022 | 9/15/2022 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:29 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff. | |||||||
B | Update existing landowner contract for project that includes repair, operation, maintenance and long term a management of the fence. | 9/1/2022 | 10/14/2022 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:29 AM | |
Description: Update existing agreement with project landowner to allow maintenance, construction, construction management, long term operation and maintenance of the fence for an additional period of 10 years. | |||||||
C | Hire subcontractor | 9/1/2022 | 10/28/2022 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:29 AM | |
Description: Sponsors shall follow their own procurement process, so long as there is no conflict of interest. Provide BPA COR the updated subcontract budget | |||||||
D | Manage construction and repair of jack post and pole fence on private land on Muddy Springs Creek. | 10/28/2022 | 11/17/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:29 AM | |
Description: Coordinate with contractor to complete construction and repair of fence and oversee work as needed. Plans and specifications have been completed for this project by NRCS. | |||||||
E | Approve construction work | 3/31/2023 | 12/15/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:29 AM | |
Description: Work will be inspected after construction to ensure the fencing meets the needs of the project. | |||||||
F | DELIV | Complete inventory of maintenance and new fence required and installed fence to protect Muddy Springs Creek | 12/22/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:29 AM | |
Description: Complete inventory of maintenance and new fence required and installed fence to protect Muddy Springs Creek in the area of phase 1 of the project. Complete inventory of phase 2 and phase 3 needs. |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
101262 | 44.596857 | -113.957156 | Idaho | Custer | Mountain Snake | Salmon |