SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 90250 (05/01/2022 - 12/31/2023) | $1,500 | $0 | ||
2. Amendment 001 (05/01/2022 - 09/30/2023) | $1,500 | $0 | ||
Work Element Budget (Current Performance Period) | $1,500 | $0 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 5/20/2022 | 6/24/2022 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff. | |||||||
B | Prioritize areas to provide riparian protection | 5/20/2022 | 6/24/2022 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM | |
Description: Plantings will be accomplished in "clusters" to allow for wildlife fence to be installed around the new plants. This will be temporary to allow plants to establish without wildlife damage. The area is already fenced for livestock exclusion so the focus is primarily on wildlife. | |||||||
C | Select contractor for construction | 5/20/2022 | 6/10/2022 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM | |
Description: Contractor will be selected to construct wildlife fences and should be mobilized immediately after plantings are complete. Sponsors shall follow their own procurement process, so long as there is no conflict of interest. Provide BPA COR the updated subcontract budget. | |||||||
D | Manage construction of fence on private land on Muddy Springs Creek to protect new plantings. | 10/3/2022 | 12/15/2023 | Active | Ryan Ruggiero (Inactive) | 9/12/2023 8:30:58 AM | |
Description: Coordinate with contractor to complete construction of fence and oversee work as needed. Approximately 20 clumps of vegetation ranging in size from ~110 square feet to 1,000 square feet will be fence to protect from wildlife browsing. | |||||||
E | Approve construction work | 10/12/2023 | 12/8/2023 | Active | Ryan Ruggiero (Inactive) | 9/12/2023 8:30:58 AM | |
Description: Work will be inspected after construction to ensure the fencing meets the needs of the project. | |||||||
F | DELIV | Complete wildlife fencing on Phase I of Muddy Springs. | 12/22/2023 | Active | Ryan Ruggiero (Inactive) | 9/12/2023 8:30:58 AM | |
Description: Complete all fencing required to protect new plantings on Muddy Springs. |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
112306 | 44.605043 | -113.96234 | Idaho | Custer | Mountain Snake | Salmon |