1987-100-01 EXP BIRCH CREEK FLOODPLAIN RESTORATION RM-2.3
Contract Start Date:
2/1/2024
Contract End Date:
1/31/2025
Title:
C: 175 - PA-2 Pendleton 2A Levee setback design and permitting
Description:
PA-2 Pendleton 2A Levee setback including the full 408 permitting process for new setback levee and removal of existing levee.
WE Agreement Type:
Contracted
Deliverable Specification:
CTUIR will work with subcontractor engineering firm to compete and upload design and permitting documents for the 90-100% deliverable.
WSE Effective Budget:
$127,135
% of Total WSE Effective Budget:
13.85%
WSE Start:
02/01/2024
WSE End:
01/31/2025
WSE Completion:
WSE Progress:
Other
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $127,135 $127,135

13 Milestones
Sort Type Title Start End Status Modified By Modified Date
A Design2 Contact EC lead to determine compliance strategy 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: Contact EC Lead to determine compliance strategy and EC review requirements.
B Suggested Provide projected construction start date to BPA COR and EC 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: CTUIR will provide month and year of projected construction start date to assist in project planning, environmental compliance, planning and design review timelines.
C Design4 Develop and submit preferred alternative (typically 30%) for review 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: CTUIR and subcontractor are developing the preferred alternative design and cost estimate. Submit plans, draft Basis of Design Report (BDR), and other supporting documentation (profiles, details, cross sections, quantities, technical analyses/appendixes, etc.) to the COR and EC Lead. Schedule time for review (typically one month for NOAA/USFWS and BPA review).
D Design5 Determine cost estimate, permitting, construction, and M&E 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: CTUIR will include an engineer's construction estimate (including, but not limited to): volume of materials and cost per volume, hours and rates for each person, equipment hours and rates, delivery costs, travel and per diem costs, and supplies
E Design6 Develop and submit permit-ready designs (typically 60% to 80%) for review 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: CTUIR will develop and submit permit ready designs to the COR and EC Lead. Schedule time for review, typically one month for NOAA/USFWS and BPA review.
F Design7 Submit completed landowner agreement 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: Submit landowner agreement to BPA that documents acknowledgement/ approval of project.
G Design9 HIP coverage obtained 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: Complete HIP Project Notification Form and document ESA coverage in coordination with EC Lead.
H Develop and submit permit-ready designs (90% to 100%) for review. 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: CTUIR will provide 90-100% designs for final technical, functional, and NMFS/USFWS review.
I EC Environmental compliance requirements complete 2/1/2024 1/31/2025 Concluded Jude Love 1/16/2024 4:39:45 PM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff.
J Design11 Upload final design set 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: Upload final approved design plan set and basis of design to the contract documents and notify COR and EC lead when complete.
K Design12 Provide construction schedule and in-water work window 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: Provide schedule to BPA outlining construction schedule and in-water work windows.
L Imp3 Subcontractor hired for implementation 2/1/2024 1/31/2025 Active Jude Love 1/16/2024 4:39:45 PM
Description: CTUIR will follow their own procurement process, so long as there is no conflict of interest.
M DELIV Produce Design - PA-2 Levee setback design and permitting for the 90-100% deliverable. 1/31/2025 Active Jude Love 1/16/2024 4:38:19 PM
Description: CTUIR will work with subcontractor engineering firm to compete and upload design and permitting documents for the 90-100% deliverable.

This work element does not require Metrics
Work Site ID Latitude Longitude State County Province Subbasin
127239 45.654602 -118.8795 Oregon Umatilla Columbia Plateau Umatilla

Primary Focal Species:
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU; Coho (O. kisutch) - Unspecified Population; Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened); Trout, Bull (S. confluentus) (Threatened)
Secondary Focal Species:
None

This work element does not require RM&E metadata