This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 32217 (03/01/2007 - 04/30/2008) | $8,335 | $8,335 | ||
Work Element Budget (Current Performance Period) | $8,335 | $8,335 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Prioritize and select restoration projects for 2008 implementation based on the 10-year Plan | 9/1/2007 | 2/29/2008 | Concluded | David Kaplowe | 2/21/2008 4:30:09 PM | |
Description: Habitat/watershed restoration projects, identified in the 10-year Restoration Plan (WE D), will be prioritized and selected by NPT and NPSWCD for implementation in 2008. | |||||||
B | Obtain permission from landowners | 9/1/2007 | 2/29/2008 | Concluded | David Kaplowe | 2/21/2008 4:30:09 PM | |
Description: On Tribal Trust lands, the NPT Executive Committee will be the final authority for approving projects. On Tribal Allotment lands, many times there are multiple owners, and according to BIA policy, 51% of the landowners and the BIA Superintendent have to sign off on any conservation practice prior to implementation. Landowners will be solicited for project implementation approval on private property. | |||||||
C | Complete designs and cost-estimates for identified projects | 10/1/2007 | 4/30/2008 | Concluded | David Kaplowe | 2/21/2008 4:44:34 PM | |
Description: Once landowner approval of projects is obtained, a design and updated cost estimate will be developed for each practice for implementation in FY 2008. | |||||||
D | DELIV | Project Designs for Areas Prioritized by the 10-year Plan | 4/30/2008 | Concluded | David Kaplowe | 2/21/2008 4:44:34 PM | |
Description: An interdisciplinary team consisting of the NPT DFRM Watershed Division, NPT Water Resources Division, and the Nez Perce Soil and Water Conservation District, will prioritize and determine a final selection of habitat/watershed restoration projects based on recommendations in the 10-year Restoration Plan (WE D) for the Big Canyon Creek Watershed. All prioritized projects (e.g., habitat enhancement, agricultural BMPs, riparian/wetland restoration, livestock exclusion fencing, etc.) will be approved by the landowners and scheduled for implementation in FY 2008. |