SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 32816 (05/01/2007 - 06/30/2008) | $50 | $50 | ||
Work Element Budget (Current Performance Period) | $50 | $50 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Submit invoices | 5/1/2007 | 6/30/2008 | Concluded | Deborah Docherty (Inactive) | 4/16/2008 5:41:19 AM | |
Description: Provide detailed information on materials and labor on a monthly basis. | |||||||
B | ASSEB | Accrual - Submit September estimate to BPA | 9/3/2007 | 9/10/2007 | Concluded | Deborah Docherty (Inactive) | 4/16/2008 5:24:10 AM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Generally, this should be done by September 10. | |||||||
C | DELIV | Project and contract management complete | 6/30/2008 | Active | Deborah Docherty (Inactive) | 4/16/2008 5:43:00 AM | |
Description: Manage SOW and budget for contract period 5/1/2007 - 6/30/2008. Submit accrual reports as requested by BPA. |