This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 36039 (01/01/2008 - 12/31/2008) | $4,000 | $5,000 | ||
Work Element Budget (Current Performance Period) | $4,000 | $5,000 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Obtain sign-off from BPA's EC Group that EC requirements are complete for 2008 | 1/1/2008 | 12/20/2008 | Concluded | Sarah Branum (Inactive) | 9/24/2008 1:25:07 PM | |
Description: On the ground activities will not go forward until environmental clearance is received from BPA. | |||||||
B | Obtain/renew applicable local, state, federal, and tribal permits as needed | 1/1/2008 | 12/31/2008 | Concluded | Sarah Branum (Inactive) | 9/24/2008 1:25:07 PM | |
Description: Review needed permits for each project site and apply through the appropriate agency. | |||||||
C | Contact BPA's EC Group to determine what will be needed for 2009 | 10/1/2008 | 12/31/2008 | Concluded | Sarah Branum (Inactive) | 9/24/2008 1:25:07 PM | |
Description: For 2009 SOW. | |||||||
D | DELIV | All environmental clearances & permits obtained before work begins | 12/31/2008 | Concluded | Sarah Branum (Inactive) | 9/24/2008 1:25:07 PM | |
Description: Upland and Riparian NEPA Checklist submitted to BPA earlier in 2005. Will work with Environmental Specialist to ensure NEPA coverage is secured. Potential permits may include local, state, federal and tribal permits, including permits such as Jarpa, NEPA, SEPA, EPA, DOE, US Army Corps of Engineers, NOAA Fisheries. Specific permits required are dependent on each specific project and will be determined on a case-by-case basis. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1479. Are herbicides used as part of work performed under this contract? | Yes | Yes |