This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 36039 (01/01/2008 - 12/31/2008) | $36,000 | $11,629 | ||
Work Element Budget (Current Performance Period) | $36,000 | $11,629 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 1/1/2008 | 6/30/2008 | Concluded | Sarah Branum (Inactive) | 9/24/2008 1:25:08 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Completion of landowner contracts | 1/1/2008 | 9/30/2008 | Concluded | Sarah Branum (Inactive) | 9/24/2008 1:25:08 PM | |
Description: Contracts will be completed before construction begins. | |||||||
C | DELIV | Approximately 10 water developments installed | 12/31/2008 | Concluded | Megan Stewart | 9/24/2008 1:43:52 PM | |
Description: Alternative water developments (approximately 10 water developments) will be installed for grazing distribution and to keep domestic stock out of riparian areas. Specific areas that are candidates for water developments are unknown until the landowners contact the District. Knowledge of the specific water development practice availability by the landowner is based on advertising of available programs and the District working with the local landowner. The landowner works with the District on a voluntary basis once the landowner indicates that water development is needed or desired. The District evaluates the site, in conjunction with NRCS staff, to determine the best water development type and location for the specific site. NRCS standards are followed for all water developments and contracts will be secured before construction. BPA funds are used to provide up to 90% cost-share. NRCS Specifications for various standard water development practices are as follows: #574: Spring Development #614: Watering Facilities/troughs/storage tanks #516: Pipe #533: Pumps #642: Wells These various specifications are not included within this statement of work. The specifications include many types of water development practices which are detailed individually within each individual specification. |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
12940 | 46.195601 | -116.995688 | Washington | Asotin | Blue Mountain | Asotin |