This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $4,609 | $4,609 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | DELIV | Deliverable complete | Concluded | ||||
Description: All necessary documents required by BPA to produce a NEPA / ESA compliance letter (e.g., NEPA checklist) | |||||||
B | Submit all necessary | 2/1/2005 | 6/20/2005 | Concluded | |||
Description: Depending on the coverage afforded by previous NEPA / ESA documents, additional information may need to be submitted to BPA to ensure coverage. | |||||||
C | Obtain permits | 2/1/2005 | 7/15/2005 | Concluded | |||
Description: |