This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 46273 REL 8 (05/01/2010 - 06/30/2011) | $41,100 | $41,100 | ||
Work Element Budget (Current Performance Period) | $41,100 | $41,100 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 5/1/2010 | 5/15/2010 | Concluded | David Byrnes (Inactive) | 5/24/2010 2:48:16 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Suggested | Site Plan to include maps, structure types and locations. | 5/1/2010 | 7/1/2010 | Concluded | David Byrnes (Inactive) | 5/24/2010 2:48:16 PM |
Description: Plan all in-water work for FY10 field season. | |||||||
C | Suggested | Materials for structures purchased and staged at implementation sites | 6/1/2010 | 8/1/2010 | Concluded | David Byrnes (Inactive) | 5/24/2010 2:48:16 PM |
Description: Purchase wood and stage on-site. | |||||||
D | Suggested | Completion of all structure implementation for the specific system | 8/1/2010 | 11/1/2010 | Concluded | David Byrnes (Inactive) | 5/24/2010 2:48:16 PM |
Description: Install beaver dam support structures in accordance to EC, annual site plan and ISEMP Bridge Ck IMW experimental design. | |||||||
E | DELIV | In-water work -- Beaver Dam Support | 4/30/2011 | Concluded | David Byrnes (Inactive) | 5/24/2010 2:48:16 PM | |
Description: Install FY10 component of Beaver Dam Support structures, repair FY09 component of Beaver Dam Support structures as described in the BCRMP Biological Opinion |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1387. # of miles of stream with improved complexity | 25.00 | 25.00 | miles of stream with improved complexity | Habitat Miles | |
1388. # of structures installed | 40 | 40 | structures installed | ||
1389. Start latitude of treated stream reach | 44.663368 | 44.663368 | |||
1390. End latitude of treated stream reach | 44.663368 | 44.663368 | |||
1391. Start longitude of treated stream reach | -120.260985 | -120.260985 | |||
1392. End longitude of treated stream reach | -120.260985 | -120.260985 |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
21528 | 44.663368 | -120.260985 | Oregon | Wheeler | Columbia Plateau | John Day |